Operator
Good day, ladies and gentlemen, and welcome to the Ocean Power Technologies fiscal year 2012 third-quarter conference call. At this time, all participants are in a listen-only mode. Following managements prepared remarks, we will hold a question-and-answer session. (Operator Instructions). As a reminder, this conference is being recorded and webcast.
I would now like to turn the conference over to the Chief Financial Officer of Ocean Power Technologies, Mr. Brian Posner. Please proceed, sir.
Brian Posner - CFO
Thank you. Welcome to Ocean Power Technologies earnings conference call for the third quarter ended January 31, 2012. OPT issued its earnings press release earlier today, and this coming Monday we will file the company's quarterly report on Form 10-Q with the Securities and Exchange Commission. All public filings can be viewed on the SEC website at SEC.gov, or you may go to the OPT website, OceanPowerTechnologies.com.
With me on today's call is Chuck Dunleavy, our Chief Executive Officer.
Please advance to slide 2 of our presentation.
During the course of this conference call, management may make projections or other forward-looking statements regarding future events or financial performance of the company within the meaning of the Safe Harbor provision of the Private Securities Litigation Reform Act of 1995. As indicated in the slide, these forward-looking statements are subject to numerous assumptions made by management regarding future circumstances over which the company may have little or no control and involve risks and uncertainties and other factors that may cause actual results to be materially different from any future results expressed or implied by such forward-looking statements. We refer you to the company's Form 10-K and other recent filings with the Securities and Exchange Commission for a description of these and other risk factors. I'll now turn the call over to Chuck Dunleavy, OPT's CEO.
Chuck Dunleavy - CEO
Thank you, Brian, and thanks, everyone, for being with us today. Brian and I will be available to answer questions following our prepared remarks.
Turning to slide 3, let me briefly provide an update on recent accomplishments. We are very pleased with the results of the ocean operations of our Littoral Expeditionary Autonomous PowerBuoy, or LEAP unit, developed for the U.S. Navy. The Autonomous PowerBuoy performed much better than the project specifications. At the same time, we have marked progress on advancing the PowerBuoy's energy conversion capability as part of our WavePort project in Spain and have taken steps to expedite development of our planned 19 megawatt project in Australia.
With those projects the PB 150 project in Reedsport, Oregon, and our ongoing business development efforts, we remain clearly focused on getting more PowerBuoys in the water. Our intellectual property position continues to strengthen as we optimize our PowerBuoy technology. Since our fiscal year began on May 1, 2011, we've been granted four patents and applied for three new patents covering a broad range of applications, from the new wave energy power take-off system to improved buoy mooring and anchoring, electrical efficiency innovations, and patents on our Undersea Substation or Pod. In total, we now have 64 patents issued and pending -- quite impressive for a company of our size, and really serves as witness to the creativity and technical innovation of our employees.
Our operating loss for the fiscal third quarter and nine months declined as compared to the comparable prior-year periods. This primarily reflects a greater than 30% decrease in product development costs for both the quarter and the nine-month periods. In addition, our net cash used in operations decreased for the nine-month period versus a year ago.
We ended the quarter with a backlog of nearly $8 million and cash on hand of approximately $38 million. We believe we are well-positioned for continued success with a number of exciting initiatives.
Now let me go into more detail on some of our latest developments. Please turn to slide 4.
Early last month, we reported operating data, which we accumulated and analyzed in connection with the ocean deployment of our LEAP Autonomous PowerBuoy off New Jersey. This buoy, which is significantly smaller and more compact than our utility PowerBuoys, exceeded the project specification for payload power delivery during ocean operations last fall. The buoy was designed by OPT to provide persistent energy for the Navy's radar and communications payload, which called for continuous power of 150 watts.
The actual results showed that the PowerBuoy supplied constant power in excess of 400 watts throughout the entire deployment period and produced peak sustained electrical power of 1500 watts. Such performance more than supported the 150 watt payload 24 hours a day, seven days a week, for the duration of the ocean operations. In fact, the onboard power management and storage system allowed the payload to be operational even during extended periods of zero wave activity. The PowerBuoy operated on a fully autonomous basis, implementing the requisite power management and self protection functions without the need for human intervention.
This all was maintained even as the Autonomous PowerBuoy withstood Hurricane Irene, which hit the New Jersey coast on August 27, 2011 and had waves of up to 53 feet. These results demonstrate strong performance under our contract with the US Navy for their maritime security mission.
More broadly, the fact that we can offer the unique ability to supply persistent levels of power in deep ocean during extended no-wave periods represents an entirely new offering to satisfy offshore power needs for a multitude of applications. We are currently in active dialogue for other potential commercial use of the Autonomous PowerBuoy by the oil and gas industry, as well as by oceanographic data gathering initiatives and desalination companies, all of which could replace diesel generators that are costly, dirty, and require frequent maintenance, replacing more resources in developing these attractive end markets for our autonomous PowerBuoy.
Now let me give you an update on activity in connection with our projects in Spain, as shown on slide 5.
In the third quarter we continued work under the EUR2.2 million WavePort project to deploy a PowerBuoy with an advanced energy conversion system that includes a new wave assessment and prediction model. Ocean Power Technologies is working with a consortium of European companies and institutions that include the University of Exeter, DeGima, the Wave Energy Centre, and Fugro Oceanor. We've begun designing a new wave prediction model with the University of Exeter while concurrently teaming with DeGima to build a PB40 buoy structure to operate with the advanced wave-by-wave electronic tuning capability. When complete the new system will assess the characteristics of each incoming wave before it reaches the PowerBuoy, allowing more time for the electronic tuning to react. It is expected this will boost the output of the PowerBuoy and reduce the cost of energy produced. The PowerBuoy being developed for the project will be installed in an existing mooring site off Santona, Spain, on the north coast.
Turning to slide 6, I would like to give an update on our current activities in Australia and Japan. These two nations have shown strong interest in our products, and we are now conducting business development initiatives focused on converting that interest to orders for PowerBuoys. In Australia, we have started site development and permitting activities, the first steps towards the planned construction of a 19-megawatt wave power station there.
We are looking at locations off the coast of Victoria, where a system of such magnitude could provide enough power for up to 10,000 homes. We also continue to explore strategic alternatives to secure additional project finance such that we can leverage the AUD66 million grant awarded for the project by the Commonwealth Government towards this innovative utility scale application.
In Japan we are making steady progress under our breakthrough agreement with Mitsui Engineering & Shipbuilding toward development of Japan's first utility scale wave power station, which would be conducted in stages. These phases would commence with site development and planning work, progress to a technology demonstration, and proceed to a power station with an initial capacity of several megawatts, scalable to 10 megawatts or more. We've continued to see increasing interest in ocean energy in Japan since the tragic events last year in Fukushima, and we expect to be able to report on developments in 2012.
Turning to slide 7, I'd like to comment briefly on our project in Reedsport, Oregon, where we plan to build and deploy up to 10 PB150's and then connect them to the grid using one of our Undersea Substation Pods for a total power output of 1.5 megawatts.
With the steel structure complete on the first PB150 PowerBuoy for this project, we are continuing the rigorous land testing of the power takeoff and control system at our facility in New Jersey. This buoy's direct drive power takeoff system is expected to be more durable, involve less maintenance, and provide better long-term efficiency than the previous hydraulic-based power takeoff design. We plan to deploy this PB150 in 2012. We are making steady progress and are pleased to have Lockheed Martin as a partner on this project.
As we announced last quarter, Lockheed will provide design for manufacturing, and systems integration expertise to enhance our technology as we move towards large-scale commercialization of the PB150. We believe this expertise will help OPT decrease unit costs to PowerBuoy, paving the way for new customers.
Before handing the call over to Brian, I want to provide some information on another part of our business, which we have recently begun to market -- marine energy infrastructure products and services, which are highlighted on the next slide, number 8.
While OPT is known for its cutting-edge PowerBuoy technology serving utility and autonomous applications, we can also utilize our expertise to further develop marine energy infrastructure and management services that can be sold independently of our PowerBuoys. We have 15 years of experience across three continents deploying and operating wave energy devices, installing power cables, and subsea power aggregation equipment. Our marine infrastructure staff has some of the best qualifications within the marine energy industry. Our proprietary Undersea Substation Pod aggregates energy generated by multiple PowerBuoys. And important to note, in addition to the PowerBuoys, it also can perform that for other offshore energy devices. And it is connected to undersea transmission cables for delivery to the shore-based grid. It purposely has been designed by OPT as a universal platform, and we hope to sell it to a broad variety of marine energy developers. In fact, we have had inquiries from two of our competitors.
OPT can design the balance of plant needed for marine energy projects, no matter what energy production technology is being employed. We can manage the supply chain, logistics, grid connection and maintenance operations to ensure successful deployment and operation. OPT has secured permits for such work in the United States, Australia, and Europe, and we see this as a growth area not dependent on any one marine energy technology, including our own. It's another area of business development opportunity for OPT as we pursue multiple paths to profitability, complementing our utility and autonomous PowerBuoys.
With that, I'll now turn the call over to Brian Posner to discuss our financial performance in detail.
Brian Posner - CFO
Thank you, Chuck. As noted on slide 9, OPT reported revenues of $0.9 million for the fiscal third quarter as compared to revenues of $1.5 million for the three months ended January 31, 2011. This decrease primarily reflects lower revenues related to the company's PB150 being prepared for deployment off Reedsport, Oregon, as well as lower revenue tied to the Navy's LEAP program on a year-over-year basis, as that project was successfully completed this quarter. These revenue declines were partially offset by an increase in revenue from the company's WavePort project off the coast of Spain.
The operating loss for the three months ended January 31, 2012, was $3.2 million as compared to an operating loss of $3.8 million for the three months ended January 31, 2011. The reduction in operating loss year over year was due primarily to a decrease in product development costs, principally for the PB150 system that underwent successful ocean trials off the coast of Scotland in calendar year 2011, partially offset by costs related to the PB150 PowerBuoy in Reedsport, Oregon.
The net loss was $2.2 million for the three months ended January 31, 2012, compared to $3.4 million for the same period in the prior year. This decrease in net loss was due primarily to the decline in operating loss and a higher recorded income tax benefit due to the sale of New Jersey net operating tax losses, partially offset by a decrease in interest income and a higher foreign exchange loss.
Interest income for the quarter decreased to approximately $95,000 compared with $148,000 for the same period last year. This decrease was largely due to the decline in average yield and in the total invested cash and marketable securities.
For the nine months ended January 31, 2012, OPT reported revenues of $4.3 million as compared to revenues of $4.8 million for the nine months ended January 31, 2011. This decrease primarily reflects lower revenues associated with the U.S. Navy's Deep Water Active Detection System project and declines in revenue tied to the company's LEAP program, as well as the PB150 being prepared for deployment off Reedsport, Oregon.
The year-to-date revenue decline was partially offset by increased work on the company's WavePort project in Spain and by the funded development of the PB500 PowerBuoy.
The operating loss for the nine months ended January 31, 2012, was $12.4 million as compared to an operating loss of $15.8 million for the nine months ended January 31, 2011. The reduction in operating loss year over year was due primarily to a decrease in product development costs, principally for the PB150 system off the coast of Scotland and the company's Hawaii project with the US Navy, as these projects neared completion during fiscal year 2012.
Please note that gross profit for the nine months ended January 31, 2011, was negatively impacted by a reduction in revenues of (technical difficulty) due to a change in the Company's estimated revenue recognized in connection with the project off the coast of Spain.
The net loss was $11.1 million for the nine months ended January 31, 2012, compared to $15.1 million for the dame period in the prior year. This significant decrease in net loss was due primarily to the decline in operating loss and lower foreign exchange losses, as well as a higher recorded income tax benefit, partially offset by a decrease in interest income.
Interest income for the first nine months of fiscal 2012 decreased to $342,000 from $547,000 in the prior-year period, reflecting the decline in average yield and in the total invested cash and marketable securities. OPT recognized a foreign exchange loss of $93,000 for the nine months ended January 31, 2012, as compared to a foreign exchange loss of over $200,000 for the same period last year. The difference was due to the relative change in the value of the British pound sterling, euro, and Australian dollar as compared to the US dollar during the two periods.
Turning to slide 10, on January 31, 2012, total cash, cash equivalents, restricted cash and marketable securities were $37.8 million. Net cash used in operating activities was $9.7 million for the nine months ended January 31, 2012, compared to $14 million for the same period last year.
OPT received approximately $1.1 million and $0.4 million in connection with the sale of New Jersey net operating tax losses during the nine months ended January 31, 2012 and 2011, respectively. As previously stated, OPT expects its cash outflows to decrease in fiscal 2012 as compared to the prior fiscal year, reflecting the completion of ocean trials of the PB150 off the coast of Scotland.
Now I will turn the call back over to Chuck for some closing comments.
Chuck Dunleavy - CEO
Thanks, Brian. Turning to slide 11, let me summarize our expected activity and goals over the coming months. As I mentioned earlier, we are on track to deploy our first Oregon PD150 during 2012, which will be an important milestone and provide further momentum to our plans to build out a 1.5-megawatt power station in Reedsport.
Second, we will continue to report on progress with regard to the design of an advanced energy conversion capability under the WavePort project in Spain. And we also expect to provide further updates on our business development initiatives in North America, Australia, Japan, and Europe.
Before opening the call to questions, I also want to note that we recently announced the promotion of Tim Stiven to Managing Director of Ocean Power Technologies Ltd., our UK-based subsidiary. Succeeding Angus Norman, who will serve on the Company's board of advisors, Tim will take on this leading role in overseeing the expansion of our operations in the UK and Europe. We are very proud of Tim's past accomplishments and look forward to seeing him excel in this new position.
Thanks again to our investors for their interest in our progress as we believe the Company is well-positioned for an increasingly active period ahead. We have the right team in place, the right partners, and the right technology to make a significant impact in the ocean-based alternative energy industry, where we see growing demand.
This concludes our prepared statement for the third-quarter review; we'll now open the call for questions. Please go ahead, operator.
Operator
(Operator Instructions). Jason Feldman, UBS.
Jason Feldman - Analyst
So, it looks like for the autonomous buoys in particular, it seems like there's a clear benefit to customers, the technology seems to be where it needs to be. What do you see as the key barriers to adoption, and what will have to happen to see the Navy in particular actually start buying these in any quantity?
Chuck Dunleavy - CEO
Sure. It's interesting and goes -- the answer is interesting. It goes right to the point that we sought to communicate, not only in this call, but in the previous one, which is to focus on the enabling aspects of it. It really is a game-changing technology in a lot of respects.
And the interesting point that I am referring to is that as we talk very extensively with prospective customers in not only the Navy, by the way, but also in other nongovernment venues, that it requires them to all of a sudden start thinking about things that are now possible, that can be done. And if you -- it's just a normal process, I think, of people's thinking that when they are convinced something can't be done, they focus on either other projects, other technologies, other applications.
And so what we have found in terms of -- I'll call it the barrier to getting the order, a contract or a purchase order, is very much involved with the -- our satisfactorily communicating the enabling aspect of our technology, and then getting the people with whom we are speaking to think about how that can help their mission or whatever their particular applications might be.
What we are not finding as issues are cost or pricing barriers, nor is there any issue with respect to what we can accomplish. We think that the LEAP system and the results of the data that we've gotten from that are very helpful. And when we do get in front of people and talk with them, it's gaining some traction.
But -- so I think -- I hope that gives you a little feeling, but it's -- really comes down to the technical aspects of the technology and making sure that the way in which it opens up some applications is fully appreciated by our audience.
Jason Feldman - Analyst
Okay. Thank you. And then also, in Australia, briefly -- how much progress can you make going forward without obtaining the additional financing? It sounds like you're progressing with permitting, site selection, but how much more progress can you make until you get the financing? And also, are those activities in and of themselves going to help, do you believe, facilitate the identification of further financing?
Chuck Dunleavy - CEO
Sure. Well, first of all, we'll just take the second question. These activities that I'm about to expand on definitely help in the selling of the financing aspect of it.
What we are doing right now is focusing on not only the site identification but also developing the site -- and that includes reaching out to local stakeholders as well as addressing the supply chain that's necessary to fulfill the orders.
We are not going to build any buoys until we have the financing lined up, of course. So we are not going at risk in that regard.
We are spending some funds with respect to the areas I just noted, though, and these are very helpful as we are talking with potential or prospective sources of capital for this project.
There's no doubt but that a concern among people who would be the extenders of capital to marine energy projects is -- starts with whether or not this will be well received by the local communities, what is the extent to which it is or is not disruptive for those various stakeholders? So what I am describing is also very much the case and our MO that we've followed in other locations, not only Europe, but also in Oregon, where we spend time up front with those stakeholders. It really is very important with marine energy, particularly since marine energy, as it is seeking to commercialize itself, is in the early stages. So those efforts are very helpful to convincing potential funders that we've addressed a number of risks, which, of course, in this case includes local stakeholder support.
The supply chain -- and I mentioned very quickly, but it also is another important part of it. It's helping us to fine-tune the costs, our cost models, for these systems that we are taking to the financial markets, as well as the prospects for a return.
One final note I'd like to make on it, or to my answer, is that the continuity of the Gillard government in Australia, and in particular the Prime Minister's initiatives with respect to the carbon tax plan there, is something that's been very much sustained within recent legislative developments in Australia, so we are very pleased about that.
And that's helpful as well. It has eliminated some of the uncertainty, and this relates directly to top-line support to our financial models.
Operator
(Operator Instructions). Rob Stone, Cowen and Company.
Rob Stone - Analyst
A couple of questions on LEAP -- why did the system do so much better than the design parameters, if you can shed some light on that?
Chuck Dunleavy - CEO
Sure. Well, there are a couple areas in which it exceeded the design parameters, but the specific one that we mentioned in our prepared comments, I'll start with, which is to say that the Navy set a mission requirement of 150 watts of continuous power, and so that was set by the Navy.
And what we have found is as we were setting about to achieve that, remember, it's also -- part of the mission was to provide that on a nonstop, 24-/7 basis. So one area that was particularly helpful and helped us exceed what was the Navy specs was that we made a big stride in terms of reducing what we refer to as the hotel load of the system.
The term derives from the notion that even at night, the hotel has got to keep certain level of lights on and keep baseline functionings going on even though it's at night. That's the derivation of the term.
In this case, for us, the hotel load is that baseline power requirement to keep some of the computers going, the monitoring devices and other aspects of the system independent of the baseline power generation and consumption related to the payload. We made some very significant strides in reducing the hotel load for this LEAP PowerBuoy.
And what's really neat is that it extends directly to the benefit of our PB150 as well as the 500 technology, so that stride forward in terms of reducing the hotel load applies across our platform of all PowerBuoy sizes. So that is probably one of the major dimensions of why we exceeded the design specs.
The other one relates to its storm capacity, its ability to withstand the forces from very large storm forces, which in this case was Hurricane Irene. I don't -- you know, we weren't exactly expecting that kind of storm forces, but what resulted in our being able to do so well in the face of those 53-foot waves, which is the second part of my answer to your question -- first one, on hotel load.
Second one is just focusing on survivability, is that our mechanical and electrical engineers worked very closely as a team, as a well integrated team, focusing on issues of what happens in the system, not only mechanically in the survival mode, but also electrically, when you have such huge forces? So we addressed and spent a lot of time on thermal absorption, thermal risk areas.
Just think of these huge waves impinging on it; you've got these generators that want to spin and somehow -- and react to that. So what do you do with all that excess energy, and therefore, what do you do with the heat that can accumulate? So that was another aspect of why we exceeded the expectations on that system.
Rob Stone - Analyst
So how is it exactly that it is able to supply continuous power when the seas are calm?
Chuck Dunleavy - CEO
Sure. Unlike our utility systems, it has two aspects to it -- the LEAP system has two aspects to it. One is an actual bank of batteries or cash of batteries that are inside it. And the second aspect is a power management function, which we actually in large part developed under the LEAP program and which serves to strongly benefit this product offering.
So what's happening is that in relatively low-wave states, we have a continuous charge of the batteries; that's not necessarily anything new, that notion. But what's new is the power management system -- in fact, on which we're submitting some patent applications -- that relate to the management of those batteries at the cell level. In other words, within each battery there are a number of cells, which is, of course, common knowledge. But it is the aspect or way in which we are, number one, preventing problems in any individual cells to in any way compromise the rest of the power management function, as well as during the instance where you, let's say, have absolutely no waves, zero waves, in a very metered and controlled fashion, utilize -- draw on the power in that battery cache.
Normally, by the way, just to give you a feeling for what its dimension is or its capability is, normally you've got about maybe four or five days within which you have what our buoy would consider to be no waves, where you're not generating any energy. The system has been designed so as to provide power over a very much extended period of a little over 30 days of absolutely no waves. So at any rate, I hope that gives you a little more color about the capability of the system and its power management capability.
Rob Stone - Analyst
That sounds very helpful. I understand the part about getting potential customers to now realize what's possible. Supposing that you did start to get an influx of orders for LEAP, what would be the steps and how long would it take to set up serial production?
Chuck Dunleavy - CEO
Sure. We've already established that supply chain right now, and we have two different fabricators already online -- not only the one who built this particular system, but we have a backup fabricator. I am thinking now for just the overall geometry for the structure -- the buoy structure itself.
What we do here at OPT at our facility in New Jersey is to assemble and test the internal power takeoff or smart-part, as you've heard us refer to it, and we have that process already well-defined and established, including the supply chain, into that. And typically what we did in all of our systems as we build them and especially in this case with LEAP, is as we were ordering the ones and twos that we needed in quantity for this particular order, we at the same time put out -- we did that on a competitive basis. And in all our RFQ's that we issued, we asked for multiple quantities, not just, again, the ones and twos we needed for this, but what would it be for 50 and an order of 100 or 200 such systems? So that was very helpful, I think, in establishing the price points for our LEAP in larger quantities, as well as, of course, our projections as to profitability.
Rob Stone - Analyst
So to turn all that on -- let's say you decide to flip the switch -- how long would the system take to then come up to speed? It sounds like it would be quite quick.
Chuck Dunleavy - CEO
Yes. And I'm often asked the question, what's the cycle time, just after receipt of order, ARO, to the point where you are delivering a buoy dock side?
In the case of the LEAP system, this is a process over about one to two months, particularly in large production volumes well within about a 45-day period. It's a smaller system, it's less complex, which of course also contributes to the improved hotel load issue I mentioned a little bit earlier.
Rob Stone - Analyst
Thanks. My last question is on the wave-by-wave tuning work that you're going to do on the PB40. Can you quantify the potential impact on cost and output? And when do you expect this development work to be done? And I assume that all of that would translate pretty directly to the PB150.
Chuck Dunleavy - CEO
With respect to your last point, absolutely does translate cross platform, not just with respect to PB40; applies to LEAP, which is much smaller, as well as the larger-sized systems, PB150 and 500. So you're absolutely right about that.
In terms of the timing part of your question, we've held back on giving any specific guidance as to when we expect the system to go into water and when the actual demonstration to occur. And the reason for that, by the way, is that we are one of several consortia members. The other consortia members get their funding directly from the EU, as, of course, does OPT. But we do not serve as the prime contractor in this particular contract. So there is more moving parts over which we have less control than we normally would have, and therefore, we've been guarded in terms of forecasting actual deployment.
But a little more specifically, with respect to the wave-by-wave tuning, that we are, as I noted earlier in the prepared text, we're working very closely with University of Exeter, some very capable people there who are helping us; and supplementing a lot of work as well being done by the OPT team. So we are looking to get a lot more visibility on what will be the expected results when it's put into and implemented into the buoy.
Last -- or actually what I think was the first part of your question -- which is, okay, so what is that going to mean in terms of either costs or cost of energy, more specifically?
We also are not giving any guidance on that at this point. The realm of possibility is a very significant multiplier, but that's in more of a theoretical world. What we are spending a lot of time on right now is certainly the theoretical calculations, but more importantly, doing some wave tank testing as well as computer modeling to give us a little more guidance on what is going to happen when we are out there in the actual ocean with a lot of unpredictable forces?
So it is from those points that derives our caution and our unwillingness, I guess, at this point to give anything specific in the way of numbers or percentages.
But our expectation is absolutely that we'll improve the power output of the system, resulting in a reduction in cost of energy. The verdict is out with respect to the extent or the quantum.
Rob Stone - Analyst
Okay, so we'll just say it's bigger than a bread box and smaller than a tractor-trailer. Thank you.
Chuck Dunleavy - CEO
Okay.
Operator
Jeremy Hellman, Avenue T Fund.
Jeremy Hellman - Analyst
I wanted to talk a little bit more about your new thoughts around marketing PTO systems and the like, excluding the actual PowerBuoys. Could you give us a little perspective on what the addressable market for that might be, either in the near term or maybe over a three- to five-year kind of look and how significant you expect that to be in terms of contribution to your revenues over either this year or the three- to five-year period as well?
Chuck Dunleavy - CEO
Sure. Again, this is with respect to the marine infrastructure?
Jeremy Hellman - Analyst
Yes.
Chuck Dunleavy - CEO
Got it. Just to confirm.
Jeremy Hellman - Analyst
And then a second follow-up to that -- if -- I'll just ask it both at the same time is -- I just wanted to be clear. Are you talking about selling systems and consulting as well, or separated systems or consulting services, essentially hardware and software and management as well?
Chuck Dunleavy - CEO
Sure. The offering that we are putting out there, and which we would like to be providing to customers, includes both product and services. I think the flagship of the product side of it, since it is proprietary to OPT, is our Undersea Substation Pod. We've already built one to order for Iberdrola in Spain, and tested that in ocean trials. So that would be the core of the product. We would in addition -- we are very much in a position to order cabling, oversee the installation of the cabling, as well as the onshore grid connection. We've done that, as I mentioned, in the -- again in the prepared remarks and I'm sure you heard. We've done that a lot over the last 15 years. So we have very -- I think some really good depth on which -- of experience to draw on.
In addition, the offering includes advisory role, which is one also borne of the experience we've had. So it truly -- I think in a way, you know, we are borrowing a page from IBM back in the late '70s and '80s, which is, it's not all just about big metal. It's also about the services that can accompany that and add real value to a customer.
Now to your first point with respect to the size or the addressable market here, that is also something -- using the Rob Stone quantum, is probably where I'd have to come out, which is to say we don't have an exact market determination yet in terms of its exact quantifiable size.
What we are seeing in the market place is in a number of locations internationally, there are not only individual private developers, but also a number of governments at the local as well as either state or federal levels that are very desirous of putting in multi-technology-based -- I'll call them wave hubs. But those are installed infrastructure and facilities which would enable multiple technologies to effectively plug in -- to be deployed at those sites and to provide the resulting energy to the grid.
So we're seeing that in a number of locations internationally. We've gotten a lot of inquiries about this, and we are actively marketing into it. I'm not in a position to quantify that at this point, so I'm not going to be able to satisfy perhaps that part of your question. But it is something for which we have existing services, existing products. It does not require additional investment by OPT of any material nature in order to sell into these markets. So I think that's an important dimension of it.
And one final point is to underscore that our approach here is trying to be technology agnostic in terms of these services. Certainly, our customers don't want to be solely limited to OPT. Absolutely, we are looking to sell our PowerBuoys into those systems, but the way we are approaching this from a marketing viewpoint is to be much more universal with respect to the technologies, and that's exactly how we built our Pod. Again, it can serve any number of different wave and tidal technologies.
So we think it's a burgeoning market; it's an early-stage market in terms of its identification. It's not one you can find a lot of data points out there in terms of the web and what might be available on it.
Jeremy Hellman - Analyst
Okay. Well I guess maybe another way of thinking about it and maybe -- I don't know if it's getting too specific then, but just be curious for your perspective, especially given where you are in New Jersey with respect to the Atlantic offshore wind project that's been debated and seems to be inching forward -- if and when that ever does come to fruition, that would seem to be potentially a multifaceted opportunity for you guys, be it with the LEAP buoys in some form and also -- and/or the Pod systems and the like.
And I'm kind of curious if you're I guess plugged into that potential opportunity and what you might think of it?
Chuck Dunleavy - CEO
Sure. Well I think you are spot on in terms of it representing an opportunity for us, and it's one that actually we are pursuing. We have had dialogue with some of the people involved with not only that project but a few others that concern offshore wind, and not just off New Jersey.
What's an interesting opportunity for us is to -- is the notion of a combined or multiple technology renewable energy site. When you think of all the plant that's being installed for offshore wind, not only the platforms themselves, but the cabling to shore, our systems can be utilized in a number of ways.
Number one, could be a little further out from the shoreline -- our buoys -- to produce power. We've always thought and pointed out and made it very clear that we believe that the ocean resources has a much higher availability than wind at many sites. So it can be, I think, a very powerful offering to the shore-based power consumers from that standpoint. That's just for pure power. And obviously, you have the economies of our systems drawing on the infrastructure already built for those wind stations, which typically are going to be a little bit further -- closer to shore than we would be.
Another dimension of the opportunity for us includes not only marine energy infrastructure services and products that I mentioned a little bit earlier to your first question, but also the LEAP system can provide power for other applications related to that platform -- that wind platform. And it's the same with respect to offshore oil and gas platforms. This includes power for security; that is to say, power for either radar or sonar-based security equipment to protect these offshore facilities, and other uses at lower power that might be made or be important for that offshore wind facility. It's a very interesting opportunity for us and one that we are working.
Jeremy Hellman - Analyst
Great. I think there's a lot to be excited about.
Chuck Dunleavy - CEO
Yes.
Operator
Thank you. That concludes our questioning period. Mr. Dunleavy, you may proceed with any closing remarks.
Chuck Dunleavy - CEO
Well, thank you all, again, for attending today's call and for the questions that we've had. We really do generally look forward to getting the questions and having the dialogue. If anyone does have any further questions, please do not hesitate to contact us. Otherwise, we look forward to speaking with you next quarter.
Operator
Thank you, everyone. That concludes our call. You may now disconnect. Have a great day.