  • Operator

  • Excuse me, everyone. We now have John Baker, President and CEO of Florida Rock Industries Incorporated in conference.

  • Please, be aware that each of your lines is in a listen-only mode. At the conclusion of John Baker's presentation, we will open the floor for questions. At that time, instructions will be given as to the procedure to follow if you would like to ask a question.

  • I would now like to turn the conference over to John Baker. Mr. Baker, you may begin.

  • John Baker II - President, CEO

  • Good morning and thank you. I am John Baker and with me this morning are John Milton, our Executive Vice President and Chief Financial Officer, and Wally Patzke, our Vice President and Chief Accounting Officer.

  • You are cautioned that any statements we make this morning which relate to the future are by their very nature subject to risks and uncertainties that could cause actual results and events to differ materially from those indicated in such forward-looking statements. These include general business conditions, competitive factors, political, economic, regulatory, and weather conditions, pricing, government spending levels on transportation projects, interest rate changes, energy and transportation costs, and technological contingencies. Additional information regarding these and other risk factors and uncertainties may be found in the Company's filings with the Securities and Exchange Commission.

  • Last night, after the close of the market, we released our earnings for our fiscal first quarter ended December 31, 2006. While sales for the quarter were down from last year's first quarter by 3.6% to $295.3 million, earnings were up 5.4% to $44.3 million or $0.67 per diluted share. Driving these increased earnings were higher average selling prices in all three segments of our business. Conversely, volumes were down in all three segments as the slowdown in home building further manifested itself in all our markets.

  • Our aggregates tons sold were down 5.6% versus last year. Cement tons were down 19.2%. Cubic yards of ready-mix concrete were down 13% and concrete block units were 32% lower. Earnings in our aggregate and cement groups were up while concrete profits were down. The cement segment earnings include a $4 million gain from the sale of property in Tampa. This matches an almost identical gain on real estate in last year's quarter which was partially reflected in aggregates and partially in other income.

  • During the quarter, we made progress on the expansion of our Newberry cement plant and we remain on target to finish this $165 million project by summer of 2008. Our new $35 million rock plant in Miami will begin its shakedown next week and we hope to be operational in March. This will increase our capacity from 4 million tons to 5 million tons, but more importantly will cut our costs at our very inefficient old plant there considerably.

  • Ironically, as this plant is ready to operate, we await a court decision from the federal court in Miami on the permits ourselves and several of our competitors in Miami. The final briefs were submitted on January 29 and the court could rule at any time. Clearly, we have no idea what to expect but we have prepared contingency plans to supply our customers in the event that the permits are vacated.

  • As we look forward, we continue to perceive very challenging markets. Volumes in all our segments continue to drop. Prices have held up remarkably, but we are seeing some lower prices on newly bid work in our concrete markets. Our average prices however are void by price escalators in some of the work we booked last year. Price increases in Florida on cement and concrete scheduled for January 1 caught very little traction. Aggregate price increases on the other hand were generally effective beginning on January 1. While these will vary from market to market, we expect net $0.80 to $1.00 per ton on average. We expect to get concrete price increases in our northern markets effective April 1.

  • The quarter has started off very slow, some of which is caused by normal winter weather and some is because business is just plain slow. And while the aggregate price increases will help us, I remind you that we have a very tough comparison with last year's second quarter when weather was incredibly mild and business was booming. We're very focused on getting our costs down commensurate with our volumes. It's not the part of the business we enjoy, but you have a management team that has done it many times before and knows how to right-size the operations.

  • As always, I appreciate your interest in our Company. While clearly we have some bumpy roads ahead, in the near term we remain incredibly optimistic about the long-term prospects of our business. We continue to spend money to grow and improve our facilities and we love the long-term demographics of our markets.

  • Now, if there are any questions, we would be happy to try to respond.

  • Operator

  • Thank you. [OPERATOR INSTRUCTIONS] Our first question comes from David MacGregor, Longbow Research.

  • David MacGregor - Analyst

  •  Good morning, gentlemen.

  • John Baker II - President, CEO

  • Good morning, David.

  • David MacGregor - Analyst

  •  On the aggregate price increases, how much carry over benefit should we anticipate from 2006?

  • John Baker II - President, CEO

  • The way I think you should look at it and I'm trying to remember -- we had price increases in July that were effective and very certainly will carry over and then you get the new price increases on January 1.

  • David MacGregor - Analyst

  •  Okay. Any chance you could quantify that for us?

  • John Baker II - President, CEO

  • Let me try. The -- and I'm looking at our producing locations which is, I think, the best gauge for looking at it. The prices - the price on aggregates a year ago at our producing locations in this same first quarter was $7.02. At the end of the prior quarter, the September 30 quarter, our price was $8.10 and at the end of this quarter it's $8.34.

  • David MacGregor - Analyst

  •  So is $8.34 at 12-31?

  • John Baker II - President, CEO

  • That's the quarter average.

  • David MacGregor - Analyst

  •  For 12-31?

  • John Baker II - President, CEO

  • Yes.

  • David MacGregor - Analyst

  •  Okay. Maybe I could follow-up with you a little further on that after the call. I guess at this stage I'm interested in your thoughts on the prospects for a midyear price increase in aggregates. It seems to be the one area of your business that's doing well from a pricing standpoint. Is there further upside there do you believe?

  • John Baker II - President, CEO

  • You know, I would expect in Florida that we will try to do one. We did not have success in cement and so I would expect that we would try a cement price increase at midyear and probably would do one in aggregates as well. And if my understanding is accurate, in the Georgia, Virginia, and Maryland markets, I believe our competitors are telling our customers that there's going to be just one price increase this year. Obviously, that's something we'll just have to watch.

  • David MacGregor - Analyst

  •  Okay. Good. And then just finally, John, you made mention of the fact that you were starting to see maybe a little softness in ready-mix prices in Florida. I was just wondering if you could elaborate a little further on that.

  • John Baker II - President, CEO

  • Well, people -- as people bid on jobs, trying to maintain volume, you're seeing some somewhat lower prices and it's all over the map depending on market. But we're seeing lower prices on bid work, not on everyday work. And what's buoying that up is we're also getting price increases as we get escalators that are built into our old contracts that were bid last year and in last year.

  • David MacGregor - Analyst

  •  Is there any way you could give us some sense of proportion on the amount of the business you're seeing that's experiencing price declines?

  • John Baker II - President, CEO

  • I really can't. And what we're going to try to do is continue to put out our volumes and prices on a monthly basis as we've done, to give you that same visibility that we've got.

  • David MacGregor - Analyst

  •  that's been very helpful too, by the way. Thank you very much. Okay. Thanks. That's it for me. Good luck.

  • John Baker II - President, CEO

  • Thanks, David.

  • Operator

  • Thank you. Our next question comes from Frank Wooten, CJS Securities.

  • Frank Wooten - Analyst

  • Good morning, gentlemen. Congratulations on a great quarter.

  • John Baker II - President, CEO

  • Thank you.

  • Frank Wooten - Analyst

  • You guys have particularly strong margins in your cement segment. Is there anything in particular that's contributed to that?

  • John Milton Jr. - EVP, CFO

  • The biggest thing we've had is we've had very low prices on imported cement and of course our only cement plant is -- well, not brand new but certainly state of the art. So we've had both things going for us. We -- we've stated that the low price cement contract that we had was set to expire on December 31. Not all the cement that was included in that contract was delivered last year and so there's a spill over into this year certainly through the first quarter of the calendar year. So I think it's the combination of those two things that make our margins look good.

  • Keep in mind too that the real estate gain that John mentioned earlier is in the operating profit of the cement segment for this quarter. So that makes the margin look unusually higher to the extent of the real estate gain.

  • Frank Wooten - Analyst

  • Got you. That entire 2.5 flows through. Okay. Thank you.

  • Operator

  • Thank you. Our next question comes from Arnie Ursaner, CJS Securities.

  • Arnold Ursaner - Analyst

  • Hi. Just -- it's Arnie. Just a follow-up to Frank's question. You mentioned that the real estate gain both last year and this year is a mix of impacting margin as well as other income. Can you break it down into the four components, which piece is in the segment margin, which piece is in other income for both last year and this year, please?

  • John Baker II - President, CEO

  • Arnie, I'm having a hard time hearing you but I think what you said was can we help you with last year's real estate and where it was put. $1.2 million of the real estate gains in fiscal '06 were in aggregates for the quarter and $2.8 million were in other income.

  • Arnold Ursaner - Analyst

  • And the same thing for this year, please?

  • John Baker II - President, CEO

  • This year, all $4 million are in cement.

  • Arnold Ursaner - Analyst

  • Okay. The second question I have relates to your capital spending plans. Obviously, there's a change in legislation regarding trucks and diesels. Can you comment on whether you did accelerate your capital spending in Q4 and what we should look for for D&A on a go-forward basis, please?

  • John Baker II - President, CEO

  • We did accelerate but that has been our plan for - for a while. So there's no change that was caused by that acceleration. We have $340 million budgeted for this fiscal year for CapEx and I think we spent about $92 in the first quarter. John or Wally, would you all comment on what our anticipated depreciation is for this year?

  • John Milton Jr. - EVP, CFO

  • For this year, Arnie, we have budgeted $84 million as our fiscal 2007 depreciation and amortization.

  • Arnold Ursaner - Analyst

  • Okay. One question on volume. While your volume was down, you actually did a heck of a lot better than your two other public comps in the aggregate space and in the whole business. Are you gaining share from them or is there specific reason why you believe they were down dramatically more than you were?

  • John Baker II - President, CEO

  • I don't think we're gaining share. We're trying to be very focused on maintaining share at this point. We did add a quarry in -- on the -- in Kentucky on the Mississippi River system that is in this year's numbers but not in last year's numbers and that could have some effect. That's -- it's not a big quarry. 600,000, 700,000 tons. I think what really makes our aggregate numbers look better than perhaps our competitors was a year ago in this quarter we had the hurricane. And we had severe disruption of aggregate shipments. And of course we didn't have that this year. So I think that's probably the biggest thing that makes the numbers look different than our competitors.

  • Arnold Ursaner - Analyst

  • Okay. Thank you very much.

  • Operator

  • Thank you. Our next question comes from John Fox, Fenimore Asset Management.

  • John Fox - Analyst

  • Yes, hi, good morning. I had a couple questions. John, you went a little quick for me when you talked about the cement and concrete pricing. Could you just go over that again, please?

  • John Baker II - President, CEO

  • Absolutely, John. I'm sorry to go too quick for you. I thought us Southern boys talked slow.

  • John Fox - Analyst

  • I knew I was going to get a reaction to that comment.

  • John Baker II - President, CEO

  • Let me see. We spelled out the tons --

  • John Fox - Analyst

  • I met in reference to the January price increases.

  • John Baker II - President, CEO

  • Okay. Okay. Cement and concrete prices in Florida did not go up on January 1.

  • John Fox - Analyst

  • Okay.

  • John Baker II - President, CEO

  • We have announced a price increase in our Virginia and Maryland operations effective April 1. We're optimistic at this point.

  • John Fox - Analyst

  • Okay. Okay. And do you have - maybe for John Milton, do you have the breakdown of manufactured and imported cement? Tons?

  • John Milton Jr. - EVP, CFO

  • I think I can help you with that, John. The tonnage that came out of our Newberry facility for the quarter this year is a little mixed up because we shipped a little bit of clinker out of there and so it distorts it. We had 196,251 tons of cement and masonry out of Newberry last year and no clinker. This year we --we sold 166,934 of cement and masonry and 22,842 tons of clinker. The rest of the volume, which total volume for the quarter, this quarter, was 470,730. The rest of that volume was imports.

  • John Fox - Analyst

  • Okay. Great. And in terms of the aggregates, the $0.80 to $1.00, that's additive to the $8.34? Is that correct?

  • John Baker II - President, CEO

  • That's right.

  • John Fox - Analyst

  • Okay. And when you -- on cement and concrete, you said your price increase did not go through so we just assume those prices are flat at this point? They did not go down?

  • John Milton Jr. - EVP, CFO

  • They did not go down.

  • John Fox - Analyst

  • Okay. And you gave us the dollar amount of CapEx and obviously you have the Newberry expansion. But could you maybe list some of the other major CapEx items for this year?

  • John Baker II - President, CEO

  • Sure. We've got a new plant, as I mentioned, a rock plant in Miami. We have a plant in -- near Auburn, Alabama that is -- we opened several years ago but we've built -- we're building a 2 million ton plant there which will serve unit trains in north Florida and south Alabama. That's probably about $30 million something --

  • John Milton Jr. - EVP, CFO

  • We've got about $34 million in Miami and I think $35 or so at Auburn.

  • John Baker II - President, CEO

  • Okay. We're building three new sand plants, one in Maryland, two in Florida. We've got several ready-mix plants throughout our system that we're adding. We have bought a bunch of rail cars. John, how much - ?

  • John Milton Jr. - EVP, CFO

  • I think we ended up buying just under $30 million worth of rail cars.

  • John Fox - Analyst

  • Okay.

  • John Baker II - President, CEO

  • And really doing a lot of upgrades to plants, trying to modernize and make them more efficient. It's sort of across the board. But a far amount of Greenfield stuff, a fair amount of efficiency projects, and then of course our replacement CapEx which was mentioned earlier was stimulated by our desire to buy trucks before the new engines went in 2007.

  • John Fox - Analyst

  • Right. Right. Okay. Thank you.

  • Operator

  • Thank you. Our next question comes from Barry Vogel, Barry Vogel and Associates.

  • Barry Vogel - Analyst

  • Good morning, gentlemen.

  • John Baker II - President, CEO

  • Good morning, Barry.

  • Barry Vogel - Analyst

  • I want to go back to that imported cement price issue because, you know, it's not clear. And according to your prior comments in the past, as of December 31, '06, that contract was going to expire and you were hopeful that you might have some cement price increases to make up for that in terms of effects on profitability.

  • John Baker II - President, CEO

  • That's true.

  • Barry Vogel - Analyst

  • Alright. The fact that you having no traction for price increases in Florida in cement and notwithstanding that you just made that comment that you might have had some of that less expensive import spill over into the second quarter, could you elaborate what effect, assuming you have no price increases in cement for the balance of the fiscal year which is a likely -- it could be a likely scenario. What's going to be the negative effect on profitability in your cement segment if volumes should stay the same in the second, third, and fourth quarter?

  • John Baker II - President, CEO

  • I think we're going to have the cheap cement clearly through March and probably into April or May. And then we would be at the market prices. We've been very hesitant to get tied down on a cement purchase contract because we feel like with fuel coming down that the prices - and with the market slowing worldwide that the prices could come down. Having said all that, Barry, we're looking at $20 per ton increase in cost would be a ballpark estimate

  • Barry Vogel - Analyst

  • For the imported cement volume?

  • John Baker II - President, CEO

  • For the imported cement volume.

  • Barry Vogel - Analyst

  • Okay. Now, you are trying to -- are you negotiating new contracts as we speak to continue to bring in imported cement? Obviously. But it would be at a new price?

  • John Baker II - President, CEO

  • We are not negotiating new contracts right now. We're hiding from people. And we would hope to do that in a couple months.

  • Barry Vogel - Analyst

  • Okay. So let me just get this straight. Probably you're okay through May and we shouldn't - it shouldn't be an issue through May, your price of imported cement.

  • John Baker II - President, CEO

  • April or May, yes.

  • Barry Vogel - Analyst

  • Let's call is May for argument's purposes.

  • John Baker II - President, CEO

  • Okay.

  • Barry Vogel - Analyst

  • Starting June, meaning the last four months of the year, last four months of fiscal 2007, you may have a $20 per ton cost increase for imported cement versus the year before. Is that a good way to look at it?

  • John Baker II - President, CEO

  • Yes.

  • Barry Vogel - Analyst

  • Okay. Second question. In terms of the aggregate price increases you talked about effective 1-1-07, you talked about $0.80 to $1.00. Last year, it was amazing. You had what you would call instant traction. What is the traction now so that if we had a look at your average price for producing locations which were in - I think $8.34 on average in the second quarter, what might be your guesstimate for the average price in new quarter given the fact that you've raised prices?

  • John Baker II - President, CEO

  • I would say you're going to get instant traction on the aggregates on at least the $0.80 of it.

  • Barry Vogel - Analyst

  • Alright. So $0.80. That means you'd be at $9.14 in the next quarter. Average.

  • John Baker II - President, CEO

  • That's the arithmetic.

  • Barry Vogel - Analyst

  • Okay. All things being equal. Right?

  • John Baker II - President, CEO

  • Yes, sir.

  • Barry Vogel - Analyst

  • Okay. Now. As far as the effect of the slowdown in concrete, you made a comment that lower prices on bid work, however, escalators are helping somewhat to offset that. You believe that based on current trends that your prices for, I guess it's block and yards, will continue to trend down as the year progresses from where it was in the quarter ending December?

  • John Baker II - President, CEO

  • I'm hesitant to answer you in the affirmative on that because if I rely on my experience the answer would be "yes". I have been absolutely amazed at our ability to maintain our prices through the last few months and as you can see on our website, there's been a little bit of erosion. I mean, a percent or two in the block prices. The concrete prices have not eroded. We're going to give you those numbers every month so you know what we know.

  • Barry Vogel - Analyst

  • Well, that's pretty good. I must admit, when your stock was much cheaper, you had no transparency. Now you have all this transparency and of course, your stock has been doing fine, but -- because investors have enormous confidence in you guys and your whole management team. But there's an old axiom on Wall Street, "The more transparency, the more information you have, sometimes the least money you make." Anyway, I wanted to ask you another question on the DOT program, the Florida DOT program. You've been kind enough to give us charts and tables on that and I think it was a fiscal June year. Can you give us an idea what in fiscal '06, the number was and what your estimate is for fiscal '07 and maybe fiscal '08?

  • John Milton Jr. - EVP, CFO

  • Barry, those charts are - as much as we know is on the investor presentation on the website. We have no more current information for next year. That budget generally doesn't get finalized till - we usually don't get it till July.

  • Barry Vogel - Analyst

  • Alright. So fiscal '06 -- do you remember what the number was?

  • John Milton Jr. - EVP, CFO

  • I don't remember, Barry. It's right on the presentation.

  • Barry Vogel - Analyst

  • Okay.

  • John Milton Jr. - EVP, CFO

  • The problem is we never got confirmation of what the actual spend was in '06. All we got was what they had projected.

  • Barry Vogel - Analyst

  • Okay.

  • John Milton Jr. - EVP, CFO

  • And for the last several years, they have projected more than they have spent.

  • Barry Vogel - Analyst

  • Okay. And as far as the federal highway program? Have you seen their kick in, John?

  • John Milton Jr. - EVP, CFO

  • Yes. Yes. What -- for the rest of the people, what Barry is referring to is the -- is Congress passed in their budget the amount that was authorized by the -- I guess it's the T2 program or T21 program whereas they were - under the previous Congress was just going to hold it flat. So that adds about $3 or $4 billion I believe to the highway program.

  • Barry Vogel - Analyst

  • Now, I have one other question on pricing because, again, it's confusing when you talk about Florida versus Virginia and Maryland.

  • John Milton Jr. - EVP, CFO

  • Sure.

  • Barry Vogel - Analyst

  • You were talking about Virginia and Maryland in terms of pricing. What were you talking about in terms of pricing -- change in terms of product category for Virginia and Maryland, April 1?

  • John Baker II - President, CEO

  • That's our concrete operations in Virginia and Maryland have price increases then. You know, the history of the northern markets is that they like to announce price increase April 1 because that's when the season starts. In Florida we've always done it January 1. So that's the reason for the confusion and the distinction.

  • Barry Vogel - Analyst

  • Alright. The fact that you made that beautiful acquisition last year, it was almost sort of hidden in your public data. And I think that they were a big competitor of yours in the Virginia, Maryland area?

  • John Baker II - President, CEO

  • Yes.

  • Barry Vogel - Analyst

  • Did that help you have a price increase in concrete versus not having made that acquisition?

  • John Baker II - President, CEO

  • You know we feel good about the price increase. Let me put it that way.

  • Barry Vogel - Analyst

  • And so you haven't announced any particular number, have you?

  • John Milton Jr. - EVP, CFO

  • I think we're different in different markets up there. But it's in the $4.00 to $6.00 range.

  • Barry Vogel - Analyst

  • What is that percentage-wise?

  • John Milton Jr. - EVP, CFO

  • Well --

  • Barry Vogel - Analyst

  • Is that per yard?

  • John Milton Jr. - EVP, CFO

  • Yes. That's per yard and that's 4% to 6%.

  • Barry Vogel - Analyst

  • Okay. Sounds great. Keep up the phenomenal work, you guys. Oh -- and one other question. I'm assuming you didn't buy any shares back?

  • John Baker II - President, CEO

  • We did not.

  • Barry Vogel - Analyst

  • Alright. You're true to form. True to form. Which is fine.

  • John Baker II - President, CEO

  • Okay. We'll get rid of that transparency because we want to make some more money.

  • Barry Vogel - Analyst

  • Okay. Great. Thank you.

  • Operator

  • Thank you. Our next question comes from Rob Norfleet, Davenport and Company.

  • Rob Norfleet - Analyst

  • Hey, John and John. Nice quarter.

  • John Milton Jr. - EVP, CFO

  • Thanks, Rob.

  • John Baker II - President, CEO

  • Thank you.

  • Rob Norfleet - Analyst

  • Just a couple quick questions. First -- and most of my questions have been answered. But you'd cited and we've seen some of the statistical data that shows some of the non-res work in Florida cooling off certainly towards the end of the year. I wanted just to get your take on whether or not we're seeing some potential bleed over from clearly the extreme decline in residential maybe feeding into the non-res sector or if you basically think it's more kind of an anomaly or seasonality issue.

  • John Baker II - President, CEO

  • From a purely anecdotal point of view, I think it's more of an anomaly. Everything I read says that non-res construction should be up and to me there's no reason why Florida and Virginia and Maryland and Atlanta would be any different and -- but the numbers don't lie. When we added them up, they were a little bit less than they had been.

  • Tom Brinkman - Analyst

  • Good morning, guys. This is Tom Brinkman, also with Davenport here.

  • John Baker II - President, CEO

  • Hey, Tom.

  • Tom Brinkman - Analyst

  • I just had a question about the Florida highway contracts in particular. I know that contract lettings in the southeastern U.S. have been strong in October and November, but I'm wondering about how December and January have been and particularly other cases where you guys have seen some highway contracts trying to be -- to be bid less in the fall, but being deferred because of higher than expected costs and maybe some pent up demand now that liquid asphalt and diesel prices have come down a little bit. Are you seeing any of that?

  • John Baker II - President, CEO

  • I don't have a feel for that to be completely honest with you. The one thing that I do know is that the big job that we're really focusing on is the I-75 job down in the Fort Meyers area which will be huge and that will be coming out I think this spring.

  • Tom Brinkman - Analyst

  • Okay.

  • John Baker II - President, CEO

  • So that'll be -- I mean, that's something we're looking forward to. There's been a lot of gnashing of teeth by the Department of Transportation because of higher prices of liquid and aggregates. But to my knowledge, I don't know that they've postponed a lot of work because of that.

  • Tom Brinkman - Analyst

  • Okay. How about your more northern markets in Virginia? I hear that area's doing really well with highway contracts.

  • John Baker II - President, CEO

  • There are some more highway contracts than there have been in Virginia, but it's been pretty pathetic. Georgia, we're very encouraged of. Georgia has been great. Virginia and Maryland are better, but they're still not very well funded.

  • Tom Brinkman - Analyst

  • Okay. Thanks for your time, guys. Good quarter.

  • John Baker II - President, CEO

  • Thank you.

  • Operator

  • Thank you. Our next question comes from Jack Kasprzak, BB&T.

  • Jack Kasprzak - Analyst

  • Thanks. Good morning, everyone.

  • John Milton Jr. - EVP, CFO

  • Good morning.

  • John Baker II - President, CEO

  • Hi, Jack.

  • Jack Kasprzak - Analyst

  • I was going to ask how housing in Florida and particularly in light of some comments Rinker made earlier this week about seeing some stabilization for example in the Orlando market which I think was one of the first parts of Florida where we really saw a huge inventory increase and a more bigger slump earlier in residential activity. Are you seeing a sort of similar stabilization, at least in pockets of Florida? And how would you describe sort of your best guesstimate of where we are in the housing slowdown because it's been so severe to this point?

  • John Baker II - President, CEO

  • Jack, I'm blind. I have no transparency. You know it seems as our numbers have shown, you know, you may see pockets here and there where a builder starts -- a big customer of ours starts to build. I've heard comments that some of the bigger builders are talking about resuming building in April or May. But I don't have any sense that I could share with you where we are in this cycle. It is -- it's very definitely slowed down. Whether we're at the bottom, I don't know. I just don't have a sense of it.

  • Jack Kasprzak - Analyst

  • Based on your experience, John, would you think that you would get sort of a qualitative feel from your sales guys? Would they be coming back and saying, "Centex, Lennar, KB Home -- they really look like they're starting to ramp up again" and that might give you some improved visibility? Or could it really just be something that turns on a dime one week or one month?

  • John Baker II - President, CEO

  • We've heard that earlier comment about guys are getting reading to ramp up and this and that. In all honesty, Jack, you can't believe it.

  • Jack Kasprzak - Analyst

  • Alright.

  • John Baker II - President, CEO

  • I mean, it either happens or it doesn't. And it's really at the whim of somebody deciding whether to pull the trigger or not and them saying they're going build in April or May is -- I almost feel like that's their effort to try to get things going a little bit, to increase the -- decrease the gloom and doom that's in the market by putting out some bright things. I think - I know you're trying to predict how long this is going to last and I'm not being much help. But I'm trying to be honest. I don't know.

  • Jack Kasprzak - Analyst

  • Fair enough. I was going to ask too, different subject, on aggregates longer term source of supply. You hear various other aggregates companies talk about looking offshore in the Caribbean. Of course, there are already operations in the Bahamas and the Yucatan that supply coastal U.S. Is that something you guys have or would look at and how feasible do you think that is? Is there a quality of material out there? A lot of people talk about Cuba but excluding Cuba which is a different matter entirely I suppose, is there - are there feasible opportunities out there long-term in your view?

  • John Baker II - President, CEO

  • Yes, I think there are. The -- I've spent my life, because I'm a bone fisher, looking for a ripe deposit in the Bahamas. And have been frustrated by that, because until now they have not wanted to open up something like for instance Mark Marietta has in Freeport. That was done through the Freeport Harbor business and the government of the Bahamas is -- up to this point has been very reluctant to let something like that happen again. And so you head south with your ideas and people have been looking in Haiti and the Dominican Republic and there's great rock down there. So you've got the natural resource available. The real trick is you're going to spend a huge amount of money to build the infrastructure to build a rock plant down there. We looked at one facility, at one place where we had a couple of miles to get to deep water and the dredging costs for that were $100 to $125 million. So -- and then you start talking about, "I'm in the middle of nowhere and I've got to have generating capabilities, electrical generating. I've got to build a community for my workers." It will happen, but it is a big swallow for somebody to take.

  • Jack Kasprzak - Analyst

  • Great. Okay. Fair enough. Thanks and congratulations on the quarter.

  • John Baker II - President, CEO

  • Thank you.

  • Operator

  • Thank you. Our next question comes from David MacGregor, Longbow Research.

  • David MacGregor - Analyst

  •   Yes, just as a follow-up, can you talk a little bit about what your competitors are doing with respect to new capacity in Florida. There's been a lot of announcements. But do you get the sense that anybody's moving ahead or not moving ahead? What's changing on that front?

  • John Baker II - President, CEO

  • Cement is the only area where you hear of any new capacity being added. There were two cement plants announced in central Florida, northwest of Orlando. It's my understanding that at least one of them has ordered equipment and perhaps both. So my sense is that they are going forward and we can expect them to be in business maybe two years from now.

  • David MacGregor - Analyst

  • Okay, that's helpful. Thanks. And then the other question I had was just more with respect to the aggregate business. I know you've got a mixture of different aggregates in your model but how should we think about replacement costs and reserves and is there a range that you think about and maybe just help us with a little color there.

  • John Baker II - President, CEO

  • Boy, that's a subject for, obviously, a lot more than in a conference call. But let me try to be succinct on it. In Florida, the replacement cost is the Dominican Republic on stone. It's phenomenal, what it would cost to replace it. If you were talking about Atlanta or Virginia or any of the -- our general markets, what you'd almost have to say is, "Number one, I'm going to go find a rock deposit. I'm going to get it zoned." And if I can do that and let's say there's a one in three or one in five chance that you could get it zoned, even once you found that deposit, then you've got to go through the ordeal of building a plant. And as I mentioned to you, we're building a plant in Auburn, Alabama. $35 million for a 2 million ton quarry. That's -- that's what it costs. And that used to be a lot less than that but the price of steel has skyrocketed. So you've got that scenario and then you've got the opening costs in a quarry and what we're finding in a hard rock quarry of any magnitude, you're probably going to lose $2 million a year for 5 years just in opening up the pit, getting it to where you can mine efficiently at a volume that makes sense. So when you start to add up all those numbers, it is daunting to want to come in and open up a new stone quarry. If you happen to own a discounted cash flow program, you'd never open one. And so -- and then having said all that, you throw in the fact that you're probably going to be 20 miles further from the market than an existing competitor and unless they are about to run out of reserves, you're really behind that eight ball. So it's a --

  • David MacGregor - Analyst

  •   Is that why you're losing $2 million a year for the first five years?

  • John Baker II - President, CEO

  • Yes.

  • David MacGregor - Analyst

  •  Just you're waiting for the market to grow out to you?

  • John Baker II - President, CEO

  • No. It's going in and stripping the overburden and the sap rock and if you're in limestone, typically a lot of the top rock has got pinnacles or mud seams or if you're in granite, you've got a lot of sap rock. I mean, it's just getting down to the good, high-quality rock, establishing a pit with benches that are efficient to mine. It's a bear.

  • David MacGregor - Analyst

  •  Okay. So I guess to the bottom-line then, can you talk then about the discrepancy between what you're getting paid for your rock now and what it costs you to replace that in your reserves? My guess, from what you've just gone through is it's still rather substantial?

  • John Baker II - President, CEO

  • It's rather a substantial thing. We did - we've been opening up new plants and we thought we were so much smarter than everybody else because we would go and do the zoning headaches and get the new rights and as we go back and postmortem them, you're probably always better off to acquire than to build new ones.

  • David MacGregor - Analyst

  •  Last question, I realize there's a limit on how much you want to say here, but are you any closer now to expanding beyond your existing geographic base?

  • John Baker II - President, CEO

  • Not really.

  • David MacGregor - Analyst

  •  Okay. Okay. I guess you've got your sort of longer-term road map?

  • John Baker II - President, CEO

  • We're working on it, but you asked the right question and we're not any closer.

  • David MacGregor - Analyst

  •  Yes. Okay. Thanks very much, guys.

  • Operator

  • Thank you. Our next question comes from Mike Betts, JPMorgan.

  • Mike Betts - Analyst

  • Yes, hi, good morning. Two questions if I could. The first one is just a point of clarification. You mentioned a figure of $8.34 for aggregate. It actually shows $9.32 on the slides. Is that just haulage? And then secondly and probably more importantly, you were talking earlier about taking costs out of the business. Are you prepared or able to quantify how much cost you've taken out? I'm sure you're aware, you've heard the Rinker number which is for a much bigger business. But do you have a number that you're prepared to share with us as the costs that you've taken out?

  • John Baker II - President, CEO

  • John, why don't you answer the first question?

  • John Milton Jr. - EVP, CFO

  • On your first question, the difference in the number we quoted here and the one you see on the website is the one on the website includes all the tonnages that we sell not only at the producing locations but at our terminals. And so it will be a slightly higher average price. It will be consistent time over time because we're giving you the total one. For purposes of measuring price increases, we like to go back to the FOB price at the quarry because that's the purest measure. That's why the difference.

  • Mike Betts - Analyst

  • Understood. Thank you very much.

  • John Baker II - President, CEO

  • And on the -- with regard to the cost numbers -- we don't try to aggregate it like Rinker has where we go in and add up the amount of cost saves we've done. I can tell you that if you look at, for example, our personnel expense this quarter versus the previous quarter, our personnel expense is down about 10%. So we're going in there, we're cutting hours back, we are limiting the work force, we're closing ready-mix plants. Some not permanently, but every day it's closed. Others are closed just depending on the day and it's a question of making sure that we right-sized our business, not -- we have not tried to amalgamate it and put a number on it.

  • Mike Betts - Analyst

  • Okay. Understood. And just a finally follow-up if I could, because obviously you're opening a new cement plant in the future. I mean, if demand declines now, do you just go down reducing sales with the level of demand or do you try to build up some market share for when you have this new cement plant. I mean, how does that play out? Or is that new cement plant far enough away not to worry about that yet?

  • John Baker II - President, CEO

  • No, it's not so -- too far off that we're not going to worry about it. What our strategy has been is that we are going to replace immediately - we're going to replace imports with the new production of the plant at Newberry. So we would intend to keep our market share and instead of importing material at an average cost of $70 or $80, we'll just ship it down from our own facility.

  • Mike Betts - Analyst

  • And your cost will be what? About $30? Or less than that at the new facility?

  • John Baker II - President, CEO

  • I wish they were. We're thinking they'll be about $38 cash costs on the new facility.

  • Mike Betts - Analyst

  • That's great. Thank you very much.

  • Operator

  • Thank you. Our next question comes from Aynsley Lammin from Citigroup.

  • Aynsley Lammin - Analyst

  • Hi. Good morning. I wonder if you could just give us a kind of indication of what you expect cost inflation to be, you know, under the line cost inflation in your aggregates business for the next 12 months? And secondly, you mentioned that if the court was to withdraw the permits you would be -- you've got contingency plans to bring in rock from elsewhere. I'd like to ask where else, where would you bring that rock in from and kind of what would be the additional transportation costs of doing that? Thanks.

  • John Baker II - President, CEO

  • We're very optimistic that the cost of fuel going down like it is is going to limit the inflation in our costs in the aggregate business, to what I would say would be at least what normal inflation, 3% and I'm hopeful that it's going to be closer to 0%. Obviously, steel prices and what goes on in that arena will have an effect, but generally we had huge price increases a year ago on the things, our supplies and services, and we're not seeing those today anywhere near to that extent. With regard to your second question, we have -- we've been shipping 4 million tons out of Miami. We have a quarry in Fort Meyers which is on the other side of the state. We ship 4 million on a single shift at the quarry in Fort Meyers and we have - we've taken a drag line over to Fort Meyers which will enable us to double the size of the production by going to two shifts. So we could supply the stone to our markets from Fort Meyers. Clearly, the problem that you're going to run into is getting truck drivers and transportation to make that happen. That's what we'll have to face when we see exactly what happens if the worst does occur.

  • Aynsley Lammin - Analyst

  • That's great. Thank you.

  • Operator

  • Thank you. Our next question comes from Robert Zelton, shareholder.

  • Robert Zelton - Analyst

  • Thank you. I have one specific, short question, and then I'm going to play devil's advocate with regard to the residential real estate market down there for a second, John, and maybe have you respond to it. The first question is, with regard to royalties that you pay, are you protected if prices go down or up? Is it a set price that you pay for what you take out? Or is it a function of the pricing structure?

  • John Baker II - President, CEO

  • It's - you know, every contract is different. But I'd say if you wanted a universal answer, you'd say it's tied to the price of the material that we ship.

  • Robert Zelton - Analyst

  • Okay. And the second point is, this is very specific and perhaps it's anecdotal and you could dismiss it, obviously, if you want to. But I recently spent several weeks in Florida and it was localized, it's basically from the Melbourne area down to Port St. Lucie on the coast. And the more I read and the more I talked to real estate agents and the more I looked at individual units, I kind of came away with the impression that at least as regards to residential construction, that things have a long way to go yet before they turn around. And I would say that it is based on several factors.

  • One is a report by United Van Lines that they actually moved more families out of Florida than into Florida in the year 2006 which was the first time that happened in forever, I guess. And one of the things that of course that the papers and everything ascribe it to is the high cost of living down there with regards to property taxes and property insurance rates. I also noted that every time I talked to a real estate agent, they were just begging for offers. In spite of what they say publicly, there's just a tremendous overhang of housing units both new construction and existing construction, I believe.

  • And then I was also - kind of saw a bigger trend this year in the fact that local governments were seeming to float bond issues and purchasing the development rights on big tracts of land, the few open spaces that are left in many of the more desirable areas there. So you know, the bottom-line is and I'm very much a long-term investor and heard you speak very positively about the longer-term and your optimistic look on things, but in Florida, I'm just wondering if we're seeing a secular change and not just a little bit of a bounce in the curve. Sometimes it's down and then it bounces back. I'm just wondering if there are some fundamental changes here that might make Florida residential construction a little less ecstatic than it was in the past.

  • John Baker II - President, CEO

  • Let me go at you bit by bit. I think you can go -- and like as you said, it's anecdotal and you go from market to market and you can get gloom and doom or you can get optimism depending on who you're talking to and what's going on. There is no question that right now we're -- most of the big builders aren't building. And I would suggest to you that it's hard to go much below zero. And that's where they are in a lot of these cases. The smaller builders have kept right on building and because they're building to a buyer and building for a buyer. I don't have a sense of whether we're at the bottom or how long it would be, but I think you're talking months, not years in any scenario.

  • With regard to the more macro, secular change, the one thing that's going on in Florida right now in our government is that the new governor has called a special session. They're dealing with property taxes. They're dealing with insurance rates. They -- they're very much focused on the issues that you're talking about, a lot of which have been caused by the boom and also the hurricanes. And I think our state government is reacting and coming up with solutions that long term will make Florida continue to be the place you want to be.

  • Not to be flip about it, but the weather hasn't changed that much. And there is a lot of open land in Florida if you fly over it. If you look at it, the coast line is pretty crowded. As you get into the interior of the state, there is a ton of land. I think we have got a very long-term boom ahead of us in this state as the baby boomers turn 65.

  • Robert Zelton - Analyst

  • Thanks. You've been right more often than I have, for sure. So that's great.

  • Operator

  • Gentlemen, at this time there are no further questions.

  • John Baker II - President, CEO

  • Well, thank you so much. As always, we appreciate your interest in our Company.

  • These are tough times and our employees are bearing a lot of the brunt of it. But we have got a great crew and we'll get through this thing and I keep coming back -- what - and the last question is really a great one because when things get slow, the tendency is to say, is to just draw in and not move forward. I can tell you, we're doing just the opposite. We're moving forward. We're spending money. We're getting this Company ready for when things come back and we'll be in a stronger, more competitive position than we were a year ago or five years ago.

  • Thank you all for your interest and we'll talk to you next quarter.