使用警語:中文譯文來源為 Google 翻譯,僅供參考,實際內容請以英文原文為主
Operator
Good day, and welcome to the Sempra Energy third-quarter earnings results conference call. Today's conference is being recorded. At this time, I would like to turn the presentation over to Mr. Rick Vaccari. Please go ahead, sir.
- VP of IR
Good morning, and welcome to Sempra Energy's third-quarter financial presentation. The live webcast of this teleconference and slide presentation is available on our website under the investor section. With me in San Diego are several members of our management team: Debbie Reed, Chairman and Chief Executive Officer; Mark Snell, President; Joe Householder, Chief Financial Officer; Martha Wyrsch, General Counsel; Trevor Mihalik, Chief Accounting Officer; Dennis Arriola, Chief Executive Officer of SoCalGas; Jeff Martin, Chief Executive Officer of SDG&E; and Octavio Simoes, President of Sempra LNG.
Before starting, I would like to remind everyone that we will be discussing forward-looking statements on this call within the meaning of the Private Securities and Litigation Reform Act of 1995. Actual results may differ materially from those discussed today. The factors that could cause our actual results to differ materially are discussed in the Company's most recent 10-K and 10-Q.
It's important to note that all of the earnings-per-share amounts in our presentation are shown on a diluted basis, and that we will be discussing certain non-GAAP financial measures. Please refer to the presentation slides that accompany this call and to Table A in our third-quarter 2016 earnings press release for a reconciliation to GAAP measures.
I'd also like to indicate that the forward-looking statements contained in this presentation speak only as of today, November 2, 2016, and the Company does not assume any obligation to update or revise any of these forward-looking statements in the future. With that, please turn to slide 4, and I'm going to hand the call over to Debbie.
- Chairman & CEO
Thanks, Rick. During the third quarter, our strong operating and financial performance continued across the Company. Our third-quarter financial results keep us on track to achieve our 2016 adjusted earnings guidance of $4.60 to $5 per share.
I would like to start off with an update on Cameron LNG. Last week, Cameron JV EPC contractor gave indication that the project is facing delays. Cameron JV and the partners are assessing the information. Any delay would likely cause 2018 and 2019 Cameron earnings to be lower than anticipated, but those earnings would be made up over time. Most importantly, our NPV should be substantially maintained as the tariff adjusts as a result of the delay. I will go into further detail in a moment.
Moving on to other important elements in our base plan, I'm pleased to say that since our analyst conference in July, our team has been successfully executing on our projects. At IEnova, we have closed the approximately $1.1 billion acquisition of Pemex's interest in the joint venture, and issued $1.6 billion of follow-on equity. At the California utilities, we continue to make progress on our $12 billion five-year capital plan. Most recently, the CPUC has approved the Sycamore Penasquitos Electric Transmission Project at SDG&E.
We've also made progress on securing development opportunities that can enhance our value proposition. At IEnova, we plan on adding approximately 400 megawatts of new renewable projects. It SDG&E, we received CPUC approval to own and operate 37.5 megawatts of energy storage that we expect to be placed into service in the first quarter of 2017.
Now please turn to slide 5. Let me start with an update on Cameron Trains 1 through 3. Last week, Cameron JV received indications from its EPC contractor that the in-service date for each train may be facing delay. The contractor's information reflects updated in-service dates as follows: mid-2018 for Train 1; late 2018 for Train 2; and mid-2019 for Train 3. Sempra and our partners are assessing this new information and ways to mitigate any impact.
We're disappointed with the short-term delay, because at Sempra, we take great pride in delivering projects on time and on budget. But under a lump-sum turnkey construction agreement, the contractor retains the responsibility and overall control of the project schedule. The good news is, the EPC contract does provide for liquidated damages for certain delays. Those damages would be factored into the tariff and would eliminate some of the impact to Cameron's customers. As a reminder, our JV partners are also our customers.
The terms of our agreements provide that EPC scheduled delays and changes in cost result in tariff adjustments. The adjustments are designed to substantially maintain the expected NPV on the project. Therefore, delays are not likely to impact the project's overall NPV.
However, any construction delays would likely defer a portion of 2018 and 2019 Cameron earnings. We had originally anticipated all three trains being in service by the end back up 2018. To give you a sense of the impact, Sempra's expected quarterly earnings from the project when all three trains are in service in 2019, are approximately $80 million.
Moving to Cameron Train 4, any expansion of Cameron beyond the first three trains requires unanimous consent from our equity partners. One of the partners has indicated they do not want to invest additional capital for an expansion. Discussions among the partners have been going on for several months, and we are considering a variety of options that may result in a clearer path to an expansion. Although we can't project timing until we receive the necessary approvals, we continue to believe a Cameron expansion would be well-positioned as one of the lowest-cost sources of global LNG supply. As a reminder, LNG expansions have never been part of our base plan.
Now please turn to the next slide for an update on IEnova. We are proud of our recent accomplishments in Mexico. Our new investments in IEnova are underpinned by dollar-based, long-term contracts consistent with Sempra's strategy. They enhance Sempra's Mexico's value proposition by diversifying its growth platforms and customer base.
IEnova recently completed the purchase of Pemex's 50% equity interest in our shared joint venture. In October, IEnova raised $1.6 billion in a follow-on equity issuance, primarily to finance the Pemex acquisition and other growth.
The equity offering was the largest follow-on deal in Mexico in the last two years. It was substantially oversubscribed, and priced at a 5% premium to the launch of marketing. Sempra purchased $351 million of IEnova stock, and now owns approximately 66% of the company. The strong deal showing is market confirmation that we have been successful with our strategy in Mexico.
In September, IEnova announced nearly 400 megawatts of additional renewable projects that are in addition to the base plan. This includes the acquisition of the 252-megawatt Ventika wind facility. Ventika went into service in April of this year, and is the largest wind farm in Mexico. We expect to close the transaction in the fourth quarter.
And 141 megawatts of solar capacity awarded in Mexico's second renewable auction. Operations are scheduled to come online in the first half of 2019. We continue to see a large amount of growth opportunities in Mexico that fit our strategy.
Now please turn to slide 7 for several other business updates. As noted in the press, we are working on an agreement to purchase a 50% equity interest in the Southern Peru Pipeline project. It is an approximately $6.5 billion natural gas pipeline. We are hopeful an agreement can be reached, but there is no assurance, and we are still resolving several significant issues. We are not able to comment on this further at this time.
Moving on to Aliso Canyon, SoCalGas has made significant infrastructure technology and safety enhancements to the facility. We are continuing the process to resume injections by requesting authority from DOGGR and the CPUC this week, which could be approved by year-end. Regarding the root cause analysis, we expect to receive the final report sometime in the first half of 2017, but the timing is dictated by DOGGR, the CPUC and Blade Energy.
Next, we settled the only criminal suit with the LA County District Attorney's Office for approximately $4 million. The settlement covers a small fine and penalty, and enhancements the safety and methane monitoring at the site. The settlement is still subject to court approval.
Also if you will recall, we previously stated our insurance coverage was over $1 billion. We are now providing a more precise range of $1.2 billion to $1.4 billion. We have received a total of $94 million in insurance proceeds to date. The total cost estimate has increased to $763 million.
The increase is primarily related to updated cost estimates for the third-party root cause analysis, and the claims recovery process associated with a temporary relocation program. Please refer to our third-quarter 2016 10-Q for more detail on the costs included and excluded from our estimated cost, and our insurance coverage.
Before I hand the call over to Joe, let me discuss the management changes we recently announced. Mark Snell is going to retire in March of 2017. Although we are sad to see Mark leave, we appreciate his many contributions to Sempra.
We also announced several other management changes as part of our succession planning. One of our strengths is the ability to develop an experienced and diverse leadership team. We strive to identify talented leaders within our organization and expand their experience across different areas of our business. These management changes are part of our succession planning process to ensure all leadership transitions can be made smoothly, with no disruptions to our business. With that, I will hand it over to Joe for his last time as CFO, to review the quarterly financial results, starting on slide 8.
- CFO
Thanks, Debbie. Earlier this morning, we reported third-quarter earnings of $622 million or $2.46 per share. On an adjusted basis, we reported third-quarter earnings of $259 million or $1.02 per share. Compared to third-quarter adjusted earnings in 2015 of $248 million or $0.99 per share.
This quarter, we had three adjustments to GAAP earnings. First, as Debbie mentioned, we completed the acquisition of Pemex's interest in the GdC joint venture and recorded a gain of $350 million, which represents the step-up in value of our previously existing ownership interest. Second, US Gas & Power closed the sale of its southeast utilities and recorded a gain of $78 million.
And finally, as part of the TdM sales process, additional market information became available this quarter that required us to reconsider its current book value. As a result, we recorded a net $65 million non-cash charge at Sempra Mexico. All three of these items are excluded from third-quarter 2016 adjusted earnings and our 2016 adjusted guidance.
I'd like to point out that this quarter, we adopted a new accounting standard on stock-based compensation, resulting in a benefit of $34 million, retroactive to January 1, 2016. Which is reflected in the results for the nine months, but had no impact on third-quarter results.
Please turn to slide 9, and I will discuss the key factors impacting our quarterly earnings. Quarter over quarter, adjusted earnings were impacted by the following items. At the California utilities, we had $21 million of higher earnings, primarily due to higher CPUC base margin, net of operating expenses.
Sempra International had $13 million of lower earnings, including a $4 million unfavorable impact from foreign currency transactional affects and inflation in the current year. Compared to a $16 million favorable impact in 2015, as a result of significant devaluation of the Mexican peso versus the dollar in 2015. This was partially offset by $5 million of higher operational earnings in Mexico and Peru.
I would also like to mention an item that didn't impact this quarter, but it could moving forward. Now that we have closed the Pemex JV acquisition, we have larger deferred tax balances in Mexico. This increases our exposure to Mexican peso movements in the future. You can find individual financial results for our business in the business unit earnings section.
I will wrap up by going over a few of our highlights. Based on our financial results, we are reaffirming our 2016 adjusted EPS guidance of $4.60 per share to $5 per share. Our 2016 GAAP EPS guidance is $5 per share to $5.40 per share. Our primary focus as a Company is executing on our base plan. We had a strong quarter, with IEnova closing the Pemex JV acquisition and completing a $1.6 billion equity issuance.
We're also working to drive additional growth with new development opportunities. Just this past quarter, additional battery storage was awarded at SDG&E, and approximately 400 megawatts of renewable projects were announced at IEnova. Incremental projects like these that fit our strategy can enable us to grow during and beyond the five years of our base plan. With that, we will conclude our prepared comments, and stop to take your questions.
Operator
(Operator Instructions)
Julien Dumoulin-Smith, UBS.
- Analyst
Hi, good morning.
- Chairman & CEO
Hi, Julien.
- Analyst
Quick question, following up on the LNG piece first. Can you elaborate a little bit on what the impact is to 2020? Just if you suggest that the NPV remains the same, does that mean the tariff is actually adjusting up to keep the NPV for you? And so what does that mean for EPS? And then secondly, can you elaborate a little bit on the nature of the delay?
- Chairman & CEO
Yes, let me try to just give a little more color around the situation. We received notice last week of this. And what they indicated when they gave us notice was just, the in-service dates that they anticipated for the three trains that I went over in the prepared remarks. But that would be Train 1, mid-2018; Train 2, the end of 2018; and Train 3, mid-2019.
They didn't give us any indication officially of the cause of the delay. But on their call, they indicated that there had been rain at the site and at their fabrication facility that's located near Baton Rouge. And apparently they had some flooding, particularly at their fabrication facility.
In terms of 2020, we are not going to revise any guidance for 2020 at this point. Obviously we have a lot going on between this and potential of the Peruvian pipeline. And so we're not going to do any update to guidance. But we tried to give you an indication of the economics of the three trains, and all three chains are operating, and that what this delay would be. Because we had said previously we expected all three trains to be in service by the end of 2018. So I think with what we've given, you can calculate what you would anticipate.
In terms of the NPV -- and this is very important -- the way the tariff works is that the IRR was established when we signed the contracts for the projects. And at the end the construction of the first train, then all of the assumptions are trued up -- what the capital costs are, and then what the amount is of the toll, in order to maintain the IRR that was agreed upon. And so that will occur.
So we will collect those dollars to achieve the same NPV on the project as we would have had, had it gone in-service on the originally planned day. And the toll actually goes up in future years as the way that it's calculated. But this will cause a delay in 2018 and 2019 earnings, as I stated in my comments. I hope that was clear, Julien. Was that helpful?
- Analyst
Absolutely, thank you. And then just quickly, if you can actually, on the Peru piece, I know you didn't want to comment too much, but what is the nature of the, I think, quote, significant issues you are resolving?
- Chairman & CEO
Well, I mean, there's commercial issues that are in the final stages of resolution. And then we will have a number of conditions [present then] if we can reach a conclusion of the commercial issues, in order to be sure that we have done the kind of diligence we want on the assets. And so I would not at all say that this is near a done deal. But we are working on it, there's still meetings going on. And so we are hopeful, but we're also cautious.
- Analyst
Absolutely. Thank you very much.
- Chairman & CEO
Thank you.
Operator
Greg Gordon, Evercore ISI.
- Analyst
Thanks. Just to clarify your answer to Julien on the IRR, it doesn't sound like it would have a material accretive impact on any one given year, given that you probably -- one presumption would be that you just have an increase in the levelized toll over the course of the life of the contract, in order to get back to your IRR. Is that a fair way to think about it?
- Chairman & CEO
That's a fair way to think about it. And when you calculate the NPV, with a delay or without a delay, it ends up being basically the same number, close to the same number. And so that's exactly what happened. So it increased earnings in future years as the result of a delay. And the same thing happens if there's an increase in project costs and the toll gets adjusted.
- Analyst
Okay. At what point would you be in a position to start to get liquidated damages? Are you implying a six-month delay does not tip you into that zone in the contract, but a further delay would?
- Chairman & CEO
Liquidated damages would apply, depending on what the source of the delay is. And that's one of the things that is going to be a subject for discussion. As I said, we just got this notice last week, and the partners have not had the opportunity to sit down with CBI and Chiyoda, and really understand what is the source of the delay, what can be done to mitigate some of those delays. None of those discussions have occurred since this notice came last week. And those will be occurring in the next several weeks.
I will say, many of us visited the site last week. Construction is progressing, and there is a lot of work that's been done on the site. But that until we really sit down and understand what's driving some of the schedule changes, it's too early to speculate what the liquidated damages would be. But the contractor does have delay-liquidated damages as part of their contract, and those go against capital costs for the project, and reducing capital costs. So that's the way it works.
- Analyst
Got you. What was your peso exposure before, and what is it now?
- Chairman & CEO
I'm going to have Joe address that in terms of the change with the -- I think you are talking about looking at the change now with the acquisition of the --
- Analyst
In other words, before the deal, what was your exposure to a given change in the exchange rate, and what is it now?
- CFO
Hi, Greg. So what we wanted to do here is make sure that everybody had the visibility into the fact that we have monetary assets and liabilities, and we have deferred taxes. And because the tax system calculates all of our taxes in pesos, these dollar-denominated items, when they are converted to pesos, obviously can move. And so we see some impact of that. Over the last number of years, it's generally been a pretty close push between what was happening if the currencies are all moving in the same direction. What's happened in Chile, Peru and Mexico kind of offset each other.
What we wanted to explain is, because we have more deferred taxes now, because we are acquiring the other half of this joint venture, our exposure to peso dollar movement will move on that deferred tax liability, and some of our monetary assets and liabilities. It's hard to predict, because obviously we would have to forecast what the effect of the dollar peso movement would be over the course of a year. Last year, we actually had a positive -- a significant positive benefit to earnings because of this.
We -- just to remind everybody -- we do hedge our current tax liability. So if there is a cash impact, then we hedge that to make sure we don't have a cash impact. But we don't hedge the deferred tax liabilities, because it's just an accounting item that moves up and down, and that would be costly to do. So I can't give you a precise number.
What we wanted to give you some visibility into is, we've been saying for the past five years or so that we have a natural hedge between Chile, Peru and Mexico when the currencies are moving in the same direction against the dollar. Now it will be a little more tilted to Mexico. It can move up, and it can move down, and it will. And so there will be a little bit more exposure, but again, it's a non-cash exposure.
- Analyst
Got you. Final question -- can you give us what the earnings impact is of the renewable energy projects on page 6 that you have won are, relative to the base case that you gave out at Analyst Day?
- Chairman & CEO
No, we don't give project-by-project earnings. What we will do is, when we give you our updates on the February call for 2017, and then we give you our updates at the analyst conference for 2018, we'll give you that information as part of our adjusted projection. So we don't do them by project. But they are the same -- what I would say is, our renewable projects are all like high single-digit returns, and that this is about 400 megawatts in total of the adds that will come in over the next three years or so.
- Analyst
When you say returns, do you mean return on equity? IRR?
- Chairman & CEO
Non-levered IRR.
- Analyst
Okay, thank you.
- CFO
Thank you.
Operator
Chris Turnure, JPMorgan.
- Analyst
Good morning. Sticking with Cameron Trains 1 through 3 for a second, I just wanted to understand maybe some context with other larger projects that you guys have done in the past and any issues that you might have had there. When you see something like this get announced by the contractor this early in the process, and take into consideration that you have built in time and cost contingencies into the overall package so far, where do we shake out here? Is this the contractor being especially conservative, and maybe there is a chance down the road that the get back on schedule? Or is this kind of a sign of something even worse to come?
And then just a point of clarification as well on the NPV staying whole. Are you guys being made whole for that? If the contractor is not responsible, then just, I guess mathematically, it would be the counterparties that are absorbing all of that potential risk? If that is correct?
- Chairman & CEO
Okay, let me try to address -- I think there were multiple questions in there, so let me try to address those. If you look at the delay notice -- like I said, we just got it last week. We have not had the opportunity to sit down with a contractor and discuss it. We will be doing that within the next week or so.
What I will say, though, is that the project is about 57% complete in total, and all of the materials our on-site for the construction. We were there last week. All of the cooling units were on Train 1. There's been a lot of construction progress. So it's not like early -- not really early on, I would say, in the progress of the project.
And it's the contractor's responsibility, when they feel that there is a potential for a delay, to give us those notifications, and that's what they did to us last week. As I said, all we know is that on their call, they said that there was rain at the site and at their fabrication facility that caused some flooding. We don't know what the actual cause of the delay is. Until we get in and have the chance to have them explain to us what they are looking at, and then look at what the potential is to mitigate some of those, it's really hard for us to assess the likelihood of it getting better through those discussions. But we will be making every effort to have that occur.
I'm not sure if I answered all your questions with that. I think there was one other thing that I might have missed.
- CFO
About the NPV, if it's not the contractor, does it go to our customer?
- Chairman & CEO
Yes, and it does go through the toll to the customers, and that was the agreement that was established. But all the LDs would go against the capital cost, which would also reduce the toll to the customer. So to the extent there is a delay that's caused by the contractor, the customer benefits from that in a reduced toll, because it reduces capital costs. But to the extent that there is a delay and that, that increases the toll -- and that's the way we designed it, was everyone with full knowledge.
Part of the thing that's actually very good is that, when we did our contract, we really tried to mitigate the risk for Sempra in terms of the long-term value of this project. And so we set it up to where we were not the ones that bore the risk for these things, and that the NPV of the project remain the same, and that the contractor had responsibility for delay. And the contractor has a lump-sum turnkey contract. The only way that they can increase cost is by change order. So that was the design of the project, to really mitigate the risk long term to our shareholders. And I think it's showing that is pretty effective in doing that in the long term, while it may affect some of the shorter term.
- CFO
I think it's important, too, to have a perspective about the over-four-year construction project starting when we took FID in 2014, and going through now. And this is moving from their information to us, a fairly small amount in terms of that. But we wanted you to all understand what the impact could be to some of the earnings numbers that we have given you. Because even though it's a small percentage of the construction timeline, we want everybody to see the visibility to that.
- Analyst
Okay, thanks for that extra clarity there. That's helpful to hear. And just on the Peruvian project, I understand that you can't give us much in the way of detail around the negotiations right now, or maybe the timing of that specifically. But were you to be successful, would this require Sempra-level equity? And what would that mean in terms of the current plan to end the repatriation of cash at the end of, I think, 2018?
- Chairman & CEO
All I can tell you on that is, those are all things we're looking at right now, and looking what the alternatives are. And that until we know if we have the project and we know what it would cost, and we know what the cash flows are going to be on it, it's really difficult to give any speculation. I'm not going to speculate on that. When we update our numbers, you will see some of that. And if we get the project, then our numbers will be updated when we do the call and the analyst conference.
- Analyst
Okay. And that was something where, previously when you were negotiating for that a couple of years ago, you hadn't given any numbers out at that time either.
- Chairman & CEO
No, we haven't given any numbers. We don't give numbers until we know we have something, until we know how we're going to finance it, and that we have some confidence in the numbers.
- Analyst
Okay, that's clear. Thanks, guys.
- Chairman & CEO
Thanks.
Operator
Stephen Byrd, Morgan Stanley.
- Analyst
Hi, good morning.
- Chairman & CEO
Good morning, Stephen.
- Analyst
Most of my questions have been hit on. I just wanted to discuss Aliso Canyon. You've given an updated insurance range. I wondered if you could just talk at a high level as to what caused the adjustment to that range? And then sort of related, when you look at all the claims, how are you generally feeling in terms of ability to your insurance to cover those claims?
- Chairman & CEO
We are still feeling good about our insurance ability to cover the claims. And when we looked at -- we look at our reserve on an ongoing basis, based upon new knowledge of costs. One of the key things that caused our estimate to go up is the work that's being done on the root cause analysis, and the fact that the third parties that are doing work on that are expecting a delay. And with the expectation of a delay and getting the outcome there, we would expect the cost to be slightly higher, and so we took that into account.
And then the other thing is, we're going through, now, recovery with our insurance on all the relocation expense, and validating all of the claims that we have full insurance recoverability. And that in going through that, that has taken a lot more detailed-type of work to get the claims ready. And so we included some of the costs associated with that. Those were the two drivers for the change in cost.
I will say these costs will be updated over time, though. As we get into litigation, as we get into knowing what legal costs we are incurring and knowing what litigation claims, any settlements that have been reflected with parties on any of the potential claims, fines or penalties, or other claims. As an example, in this reserve, we did reach a settlement with the LA County DA district attorney on the criminal charges, and reached a settlement on that. And so once we could quantify that, then that goes into the reserve number that we give you.
So those are the kinds of things that would continue to flow through in updates of that reserve. We've also spent, though, time looking at our insurance and looking at, with the types of claims we have, the types of claims that have been filed, and what the insurance coverage is, and being able to refine that a bit. And so we are able to give you a better estimate of what the range of insurance we believe is available.
- Analyst
Great. That's all I had. Thank you.
Operator
Faisel Kahn, Citigroup.
- Chairman & CEO
Hi, Faisel.
- Analyst
Hi, good morning. I just want to understand, with the delay in Trains 1 through 3, does that affect the marketing at all of Train 4?
- Chairman & CEO
Not directly, but, I think, indirectly, in that, in order to go forward with Train 4, we need a few things. We need our partner consents, and as I said, we are working with one of the partners to try to get their consent. They have decided to not put equity in, and so we are trying to look at how we would structure to move forward without them contributing equity. And have been having numerous ongoing discussions and communications with them about trying to resolve that.
The other thing is, we need lenders consent to move forward with Train 4. And the lenders are going to want to see that we have made reasonable progress on Trains 1 through 3 before giving that. So that would be how I would see it having some impact. But it's not a direct impact.
- Analyst
Okay, got it. And then on the renewable projects in Mexico, I'm just trying to understand at a high level the potential growth in the renewables business within Mexico. Is the transmission system within the country well-developed enough to handle all this wind and some of these solar projects coming online? I'm trying to understand if these megawatts make it to market, or are we getting too far ahead of ourselves before the transmission is developed?
- Chairman & CEO
Actually, that was one of the things that we looked at very carefully when we looked at -- the one we acquired is already in operation, so the transmission is there. And the two projects that we bid on, the solar projects that we won, we looked very carefully at what the transmission was. And we were very selective on what we bid, based upon that.
But there's great opportunity in transmission in Mexico. They are expecting two bids to be out in 2017 that would each be about $1.2 billion, for transmission upgrades to their system. And that's a great opportunity for IEnova to participate in those bids. I think you will see a lot more -- as you've seen in other markets where renewables start getting integrated, I think you'll see a lot more investment in electric transmission occurring in Mexico. But in the near term, they have already announced those two bids.
- Analyst
Okay, got you. And then your guys decision to participate in the equity offering, the amount that you guys decided to take down the equity offering, was there some calculus behind that in terms of how you came to that amount?
- Chairman & CEO
I'm going to ask Joe to talk about that, because there was a lot of thought about where we wanted to be and where we wanted to position ourselves for now. But I'm going to ask Joe to address that.
- CFO
Thanks, Debbie. Hi, Faisel. We said last year when we announced the deal for the Pemex JV, that we would basically take two years of the dividend flows from IEnova to us, to hold those in our Mexican holding company, and reinvest that. And we said it would probably be in the $300 million to $350 million range.
And Mark and I spent a lot of time with Carlos talking about how much time we should take. We got up a lot of advice from our IEnova investors of how you guys should maybe not do it, we want to own more. So definitely there was a lot of demand for this equity, which was great.
The road show was very similar to the IPO. We got a lot of orders every day, and it was a really amazing road show with the investors. At the end up of the day, we wanted to make sure, because we really love these assets and this business, that we maintained a strong ownership interest in it. So we went to the max because we were actually issuing more equity than we originally put on the table when we started the road show, and upsized it to that amount. So we did about the top end of what we said we were going to do.
- Analyst
Okay, got it. And then just on Aliso, is it possible -- can the in-service date or the return of the service storage facility, can that be before the root cause analysis is done? Or do we have to wait for that to get done? I'm just trying to understand if that can actually happen before there is resolution?
- Chairman & CEO
Yes, it can happen before the root cause analysis is done. Let me have Dennis walk you through what the process is that DOGGR and the CPUC will use over the next month or so. Because we did make our filing yesterday to put the field back in service, and for DOGGR and CPUC to do the certification that's required. So Dennis, do you want to kind of walk --?
- CEO of Southern California Gas Company
Sure. Hi, Faisel. When the new law, SB-380, was put in place, it was established independently of when the root cause analysis was going to be completed. There are basically two different tracks there. We have complied with everything that's required under, we believe, under SB-380, and that's why we made the filing yesterday.
So the process now is that DOGGR and the Public Utilities Commission are going to be reviewing all the data and the information that we submitted. They are required under the law to hold a public hearing, which they have to give 15-day notice to. And we expect that sometime soon, they will establish the date for that and they will go through the process. But as Debbie mentioned, they are independent tracks altogether, the root cause analysis, as well as the satisfaction of the comprehensive safety review that is laid out in SB-380.
- Analyst
Okay, that makes sense. And then I just wanted to wish Mark well in his retirement in case (laughter).to talk to him before the next quarterly call.
- President
Thanks, Faisel.
Operator
Steve Fleishman, Wolfe Research.
- Chairman & CEO
Hi, Steve
- Analyst
Yes, hi, Debbie. I know you don't have specifics on why the six-month delay. But is there a way you could make us more comfortable that six months doesn't turn into 12 or 18? Just, you talk about it that or less, but why shouldn't we be worried about it being more?
- Chairman & CEO
I think that if you look at where construction is now, a lot of the major pieces of construction have been done. And some of the issues that were the most critical, that had more time sensitivity, dealt with all the foundational work, and that's all been done. So I think when you see the progress -- and some of you will see the progress when you visit the facility -- you'll get a sense that the work is moving forward. That it's up to the contractor to give us the best estimates of the timeframe, and it's probably not in their interest to give us something that they don't feel like they're going to be able to meet.
So at this point in time, we feel, all we have is their estimate, and that we have to have some credibility. I think our view is that there are some things that might be done that could actually shorten some of the timeframes. But we don't know what the issues are that were driving the delay. So that's one of the things we need to spend some time on. And so I'd love to give you comfort, but until we get through some of those discussions with the contractor, I don't think it's something I should be doing.
I think we need to go through those discussions, have those discussions, understand the delay, look at a mitigation plan to the extent possible to try to reduce delays, and then come up with what we really all feel is the correct information. And we did not want to not tell you about this, because we got this notification. We know it also puts us in a difficult position, because we feel that we can work some of this, but we haven't had the time to do that yet. And we will, and by the time we talk to you again, we will have that information.
- Analyst
Okay.
- Chairman & CEO
And Octavio, do you want to add anything to that? Octavio Simoes, President of Sempra LNG
- President of Sempra LNG
No.
- Chairman & CEO
Okay.
- Analyst
And just one other clarification on Cameron is -- are weather conditions and flooding and things like that something that would be a force majeure on the timing, or no?
- Chairman & CEO
Not just weather conditions, no. There are certain provisions of the contract that are very well-defined, is what constitutes a force majeure. And just having rain and bad weather would not be a force majeure.
- Analyst
Okay, great. Switching gears just to detail clarifications, the $34 million of stock-based comp change, is that pretax or after-tax? And would you still be in your range for this year if that did not happen?
- Chairman & CEO
No. Trevor will talk about it. Trevor Mihalik, Chief Accounting Officer
- Chief Accounting Officer
Yes, Steve, this is Trevor. That's a tax item, so it's really an after-tax adjustment.
- Analyst
Okay. And then would you still be in your range this year if that had not happened?
- Chairman & CEO
Yes.
- Chief Accounting Officer
Yes, we would.
- Analyst
Okay. And then just on the Pemex currency volatility, should we assume that it still goes the same way as in the past, i.e., if the Peso weakens, it tends to be a benefit, and if the peso strengthens, it tends to be a hurt? Or is that also unpredictable?
- CFO
Steve, this is Joe. I would say generally, that is correct. Because it measures deferred taxes and monetary assets and liabilities, it could swing around if we had cash positions or depositions, and the deferred taxes, of course, over time will move. So I think directionally, you have it right. It should be in the same direction.
- Analyst
Okay, thank you.
- CFO
Yes.
Operator
Michael Lapides, Goldman Sachs.
- Analyst
Hey, guys, a couple of questions. First of all, your thoughts on US renewable opportunities for Sempra? Just curious in terms of whether you still see significant opportunities at all, or none, for either contracted wins or contracted solar growth for US Gas & Power?
- Chairman & CEO
We see some great opportunities for growth in renewables. And we're working on several projects where we have secured the rights and the contracts, and that are in early stages of development. We have the ability to expand the Mesquite site. We have the ability to expand the Broken Bow wind site. And so we think with all the RPS standards that are coming across the country, that there are some good growth opportunities for renewables.
I will say that the returns on renewables have gone down over time. So what we look at is, do you really have good projects that have decent returns on them? Because we have other ways we can invest our capital. And so we always look at the allocation of our capital to the projects that give us the highest return. And since we're not -- you know, renewables is just one of the things we do. We're not going to just go after building megawatts, we're going to after building megawatts that give us good return on our capital.
- Analyst
Got it. Thank you, Debbie. One other question. Back to the US utilities -- and sorry if I'm staying a little US-centric here. What's not in the CapEx guidance that you laid out at the Analyst Day this summer, but that could provide upside to US utility rate base growth? I'm thinking things like Otay Mesa, which I don't think was in that guidance. But what else was in there that, when I think about the next three to five years, could lead to higher rate base than what you laid out in July?
- Chairman & CEO
Well, you actually named one. So let me turn it to Jeff, and he can talk about SDG&E. And then Dennis can talk about SoCalGas. Because there are a number of things that we're working on right now, including the potential of a DC transmission line. So Jeff? Jeff Martin, Chief Executive Officer of SDG&E
- CEO of San Diego Gas & Electric Company
Good morning, Michael. We laid out at our analyst conference [constantly] those green box items which were not in the plan, that could provide some additional upside. And I'll just give you a brief update. One thing I think we have been relatively successful is, you've got to be able to manage both your GRC capital and the capital which -- for projects which are approved outside the GRC.
So just recently we've had -- just this year, we've had $1 billion of incremental projects approved that's not incremental to the plan, but that's outside the GRC. That's the Cleveland National Forest Project, Sycamore PQ, as well as the batteries which were discussed earlier on the call. So were making great progress there.
For our 2016, 2017 and 2018 capital plan, it was roughly $3.5 billion. $3.25 billion of that has already been approved and is going forward. So that really gives us a lot of confidence in terms of the certainty of our future capital plan.
In terms of things which are not in the plan, Debbie touched on the DC line. This is the southwest power link which originates in Arizona. We think there's an opportunity as we think about providing more reliability, particularly in the LA Basin, of giving access to more renewables and more power from that Palo Verde generating center in Arizona, back into California. That's one project of about $1 billion.
Secondly, we think there's an increased opportunity for batteries. At San Diego Gas & Electric, by the end of Q1, we will have just over 50 megawatts of utility-owned batteries. We think there's an incremental 200-megawatt opportunity. That's really associated with this new bill which was passed this year, which is AB 2868, which calls for 500 megawatts of new batteries to be installed, split one-third between the three investor-owned utilities.
Otay Mesa, you referenced, which is a 600-megawatt combined cycle plant in the heart of our load center, that is subject to a put call arrangement with Calpine. And as you may recall correctly from our last analyst conference, that was not included in our five-year plan.
And then the last thing I would mention is electric vehicles. With the passage of SB 32, we are now required to drive our greenhouse gas emissions footprint in California 40% below 1990 over the next 14 years. And almost 50% of that has to come from the transportation sector. In fact, that's close to 53% or 54% in our service territory.
So big picture on this greenhouse gas issue, Michael, is, you've only got about 10% of the greenhouse gas emissions coming from electric generation that's inside the State of California, maybe another 8% to 10% outside the state. There's no question that if the state is serious about meeting its goals, we have to have a revolution around the transportation sector. And I think almost in every scenario, the California utilities will play big in that space.
- CEO of Southern California Gas Company
Hey, Michael, this is Dennis Arriola. Let me just touch on three things real quick. One is, we expect that going forward there's going to be new national or state rules or regulations on storage. And I think that, that's an opportunity as we continue to enhance the overall infrastructure and the safety of all of our facilities. That's number one.
The second -- and we've touched on this a little bit, but we're seeing more momentum in the state -- is focusing on using natural gas for heavy-duty transportation, so the fueling infrastructure around that. And then thirdly, focusing on the gathering and cleaning of renewable natural gas from landfills and dairies and things. We're not going to give out dollar amounts for those yet, but I think those are three areas that we definitely see opportunity and upside for our gas companies here in California.
- Analyst
Got it. Thank you, guys. Much appreciated. Mark, congrats, and I will look forward to seeing you out fly fishing at some point. (laughter)
- Chairman & CEO
Thanks, Michael.
Operator
Paul Patterson, Glenrock Associates.
- Analyst
Good morning.
- Chairman & CEO
Hi, Paul.
- Analyst
Just want to follow up on the LNG just a little bit more. The joint venture contractors -- can you just review the credit support and what you have with respect to their ability to -- you know, just their financial wherewithal to -- their guarantees and what have you, for the project?
- Chairman & CEO
Sure. I'm going to have -- I can give a high-level, but I will have Joe or Mark address more details. We do have performance assurances in CBI and Chiyoda. They have a joint and several guarantee from each of the parties, and a letter of credit as a backstop. So we have that. I don't know if you guys want to add anything more to that?
- President
We have very strong credit support.
- Analyst
Okay. I just wanted to review that. And then, is it unusual for them to call up and say we've got a problem, but not tell you what the cause of the problem is?
- Chairman & CEO
Well, what they have to do is, they have to lay out the detailed schedule of everything that they expect to happen, like with the construction, in the new detailed schedule. And we just got that -- I think it was Friday of last week. And so that's how they begin the discussion on this, is that they lay out a new detailed schedule, and then the discussion comes around that new detailed schedule.
So as I said, we just got that Friday, I think, it was, of last week. And then that will begin the discussions. So that's the process. They are the ones responsible for giving official notification, and that was the process that they followed.
- Analyst
Okay. And then the Train 4, the partner who dropped out, can you tell us a little bit more about which partner that is, and why they dropped out?
- Chairman & CEO
No. (laughter) But I can just tell you why they have indicated that they don't want to do it. It's a company that has changed their strategy, and it's really focused on some downstream more now, and more clean green energy. And so they are looking not to invest major portions of their capital in LNG. And that's what they indicated to us. It was a strategy change.
- Analyst
Okay. And then the accounting change, the $34 million stock compensation, what triggered that? What was the reason why that happened? And is there any impact past this year for 2017 or beyond?
- Chief Accounting Officer
Yes, this is Trevor. That was as a result of an accounting standard update, which was 2016-09 that we implemented and we early-adopted this year. So historically, what you have done is, you have taken that tax benefit, and it's gone straight to EPIC, or it accumulated -- or the paid-in capital. Now it's trying to simplify the accounting associated with that, and so you take the tax benefit and you push it through the P&L. So going forward, we will treat it the same way.
- Analyst
Meaning, going forward, we will -- I'm sorry to be slow, but what does that mean?
- CFO
Yes, there will be earnings going forward of similar amounts. It won't always be the same, because it will depend on what restricted stock and other stock is best. And many other utilities have also adopted it this year.
- Analyst
Okay. So that should be good for earnings going forward. Am I right?
- Chief Accounting Officer
That's right.
- Analyst
Okay. And then maybe in a similar amount?
- Chairman & CEO
Well, assuming -- it could go --
- Chief Accounting Officer
Yes, it can go either way.
- Chairman & CEO
I don't want to give it inference that you can add $34 million a year. That's not the way it works. So why --
- Chief Accounting Officer
Yes, the way it works is, when the original grant is issued, that stock-based compensation, it's an expense, and you take that tax benefit. If it vests at a higher amount and the stock price increases, then there is more of a tax deduction in those future years. And so historically, the stock price has been rising and the grants have been investing at the multiplier -- meaning that there is a higher tax benefit in future years. That tax benefit has historically gone through adjusted paid-in capital, and now the accounting standards says put it through the P&L.
So going forward, we anticipate, assuming that the stock price continues to rise and that the multiplier effect is in place like it has been in the past years, we would get a similar-type benefit. If it doesn't, if the stock price were to go down and it still vests, it could actually have a detriment to earnings in the future. But that's just how it could go both ways.
- Analyst
What if there was no change in the stock price?
- Chief Accounting Officer
Then you would not have the tax benefit when those stocks vest, because you take that tax benefit when you issue the grants over those periods.
- Analyst
Okay, great. Thanks so much for the clarification. And congratulations to Mark.
- President
Thank you.
Operator
Andy Levy, Avon Capital.
- Analyst
Hi, good morning still.
- Chairman & CEO
Hi, Andy.
- Analyst
On the letter of credit that you mentioned, how large is the letter of credit?
- Chairman & CEO
You're talking about the Cameron letter of credit?
- Analyst
That's correct. How big is it?
- Chief Accounting Officer
I don't remember offhand. I don't remember offhand. We will get it to you.
- Analyst
Is at hundreds of millions, or $100 million?
- Chief Accounting Officer
No.
- CFO
We'll get the information.
- Chief Accounting Officer
Yes, I don't want to give you a bad number.
- Analyst
Fine, that's fine. And what triggers it?
- Chief Accounting Officer
Well, I mean, it would be a default.
- CFO
Nonperformance.
- Chief Accounting Officer
Nonperformance, yes.
- Analyst
It's nonperformance, okay. And then are there any like sureties -- insurers, like surety bonds or anything like that, that --
- Chief Accounting Officer
No. Keep in mind, this is a very large project. There's really not that much bonding capacity in the market.
- CFO
Oh, and very large, credit-worthy counterparties on the other side. It's a big joint venture.
- Chief Accounting Officer
Yes. Right. Yes, and keep in mind, the counterpart of it -- you're talking just about the contractor here. But these are very large credit-worthy companies. And so it would be unusual to have that kind of a bonding capacity on a project this size.
- Chairman & CEO
I also want to stress, as I said, that between CBI and Chiyoda, it's a joint and several guarantee. So they basically assume each other's responsibility.
- Chief Accounting Officer
And I also think too, there's no indication that they are not performing. They have an obligation under the contract to tell us if they think there's going to be a delay. They have notified us of that, and then we will work through it to see if we can mitigate it. But they are not saying that they can't finish the job.
- Analyst
And I know that you haven't spoken to them, but just based on your comments, it seems that the delay seems to be around the flooding, right, and all the rain that you had down there? Is that correct?
- Chairman & CEO
All we can say on that is that they didn't give us any official notification in the information that they sent to us. But when we listened to their earnings call, on the earnings call, they said that there was rain at the site and the site of the fabrication facility that's located near Baton Rouge, that caused some flooding, and they expected some delays in construction. That's what they said on their call. You can listen to their call and get the precise language, I'm just kind of reiterating what they said.
But we don't have any official notification. And we will be meeting with them soon. It's something where all the partners have to sit down with them together, so it's not something that you can do instantly, because this is a joint venture. And so it will be ourself and our three partners sitting down with CB&I and Chiyoda. And I think it's scheduled within the next week or two, for that meeting to occur.
To really go through -- as I said, they gave us this massive package that has a detailed schedule that they produce on the construction. And someone asked me, what gives you some assurances? Well, part of the whole effort is to go through that detailed schedule that they give us, and to ensure that everything has been given consideration. And that's the process we need to go through.
- Analyst
Okay. And the last question I have -- and I apologize, because I'm not as familiar. I'm very familiar with CBI, but Chiyoda, how are they -- and I guess, what, they are a separate company unrelated to CBI? Or are they a subsidiary that does this type of work with them? Or what's the relationship?
- Chairman & CEO
Chiyoda is a huge multinational company that's not at all tied to CBI, other than through this joint venture. It's a Japanese-owned construction company. I don't know what their market cap is.
- Analyst
I get it, yes. I'm not that smart. Okay, thank you very much.
- Chairman & CEO
Yes, thanks. Okay, thanks again for joining us today. We look forward to seeing many of you at EEI in the next few weeks. And if you have any follow-up questions, please feel free to contact the IR team. And have a really nice day.
Operator
That does conclude today's conference. Thank you, everyone, for your participation.