Quanta Services Inc (PWR) 2006 Q2 法說會逐字稿

完整原文

使用警語:中文譯文來源為 AI 翻譯,僅供參考,實際內容請以英文原文為主

  • Operator

  • Welcome to the InfraSource 2006 second quarter results conference call. Today's call will be hosted by David Helwig, chief executive officer, and Terence Montgomery, chief financial officer. As a reminder, today's call is being recorded.

  • Statements made on this conference call may contain forward-looking statements based on InfraSource's current expectations about future events. These statements generally relate to InfraSource's plans, objectives and expectations for future operations and are based upon management's current estimates and projections of future results or trends. These statements are subject to a number of risks and uncertainties and other factors that could cause actual results to differ materially from those described in the forward-looking statements. Listeners are cautioned not to put any undue reliance on these forward-looking statements, which are not a guarantee of InfraSource's future performance. For a detailed discussion of these and other cautionary statements, please refer to InfraSource's filings with the Securities and Exchange Commission.

  • At this time I'd like to turn the call over to Mr. Helwig. Please go ahead, sir.

  • David Helwig - CEO

  • Thank you, Shelley, and good morning. Welcome to our second quarter 2006 earnings conference call. Joining me today is Terry Montgomery, our chief financial officer.

  • Before we discuss the details of our earnings release, let me take a minute to provide a broad overview and perspective on our business and on our market.

  • As we said on our last conference call, our prospects for continued growth are reflective of a number of generally positive and convergent factors, including increased demand for our services in each of our end markets, an increase in the number of projects being undertaken to strengthen the electric grid, provisions of the Energy Policy Act intended to foster additional investment in the electric grid and other energy sectors, as well as a continuing trend toward increased reliance on outsourced infrastructure services and a desire by utility to consolidate their number of service providers. Our business strategy capitalizes on these favorable trends while enhancing our competitive strengths and our value to customers.

  • During the second quarter we saw a number of additional announcements and positive developments that should bode well for increases in demand for electric services. The FERC, Federal Energy Regulatory Commission, issued final rules on long term transmission rights, incentive rates for transmission, and certification of an electric reliability organization.

  • Additionally, FERC approved incentive rate plans for two proposed major transmission line projects in the northeast. Additionally, a map of proposed transmission corridors of national interest on western public lands was released for public comment and there were quite a few announcements of transmission expansion plans by utilities and regional planning organizations.

  • During this last quarter there were also a number of recent studies that confirmed the -- that the anticipated increase in transmission investment is occurring. And NERC updated its survey of planned transmission expenditures, indicating an increase of about 20% for the planning period 2005 to 2009 compared to that previously indicated for 2004 to 2008.

  • And most recently, in the grips of record high temperatures across the entire nation, all seven NERC control areas reported record high electric loads, necessitating voltage reductions, load curtailments, calls for conservation and consideration of rolling blackouts. While a number of distribution level reliability problems did occur, we were fortunate that the transmission systems held up well, although the cost of delivery of power can be expected to be high due to transmission system constraints.

  • The key challenges for us and our industry remain the availability of qualified skilled workforce to address growth opportunities and to utilize a disciplined approach to capitalize on this growth. Workforce availability of course also represents an opportunity for our industry, as it may to serve to increase our customers' interest in outsourcing and taking advantage of our efficiencies in workforce utilization. We are taking the appropriate steps to ensure that we attract and retain the most qualified employees for the work that we see ahead of us, as well as to continue to exercise selectivity in the projects that we pursue.

  • We believe that we are well positioned to further strengthen our leadership position in our markets and capitalize on these opportunities due to our reputation for safety, quality and performance, the strength of our customer relationships, our demonstrated ability to handle large complex projects and the breadth of our services.

  • Now we will discuss our results for the second quarter and our outlook for the balance of 2006. We're generally pleased with our performance for the second quarter, which came in near the upper end of our guidance provided last quarter. Our earnings per share was $0.13 per diluted share, which includes a $0.06 previously announced non-cash charge relating to our debt refinancing and is reflective of strong operating performance on electric distribution and substation projects which were completed in support of customer work to meet summer critical load requirements, including the earning of performance bonuses. This result was achieved despite the recognition of a $0.10 per share charge associated with a loss on one of our transmission projects.

  • Revenues in the quarter were $258 million, or 11% higher than the -- higher than the second quarter in 2005. Revenues from our electric power and telecommunications end markets grew substantially during the quarter. Electric was up 23% to 150 million, telecomm was up 17% to 30 million and natural gas was down 5% to 72 million. The summary of our revenues and backlog by end market is provided in this morning's press release.

  • Net income for the second quarter 2006 was $5.3 million. Income as adjusted was $8.5 million for the quarter versus a loss as adjusted of $300,000 a year ago. EBITDA as adjusted was $22.5 million, or 165% higher than for the second quarter 2005. Terry will provide more detail on these results and our recent debt refinancing in a few moments.

  • Our total backlog of $916 million at the end of the second quarter increased 9% over the second quarter of 2005 and decreased 2% over the first quarter of this year. The recent decrease in our backlog is attributable to the expected 16% decline in our natural gas backlog and 5% decline in our telecommunications backlog, which was largely offset by a 14% increase in our electric backlog, including the two projects, two major projects that we previously announced.

  • Our changes in backlog for the second quarter by end market are as follows. Our electric backlog of $435 million is up 65%,or $173 million, compared to the second quarter of 2005 and up 14%, or $54 million, over the first quarter of this year. Electric transmission backlog of $215 million is up 82%, or $97 million, over the second quarter '05 and up 22%, or $39 million, over the first quarter.

  • Among our awards during the quarter were nine scopes of transmission work in Maine, Texas, California, Wisconsin, Pennsylvania and Canada, including the previously announced Bangor Hydro transmission line where we have already begun work.

  • Progress continues on our Power Up Wisconsin project as well as on our other large transmission projects in Texas, Georgia, Connecticut and Nevada. Looking forward, we are tracking numerous additional large transmission project opportunities. However, as always, the timing of such awards and whether we will be awarded the work remains uncertain.

  • Our substation backlog of $137 million is up 46%, or $43 million, over the second quarter of 2005 and roughly equivalent to the first quarter of 2006. Among our awards during the quarter were eight scopes of substation work in Texas. Our other electric power backlog of $88 million was up 61%, or $33 million, over the second quarter 2005 and increased 21%, or $15 million, over the first quarter of 2006. This work consists largely of distribution work for utilities and work for our industrial customers.

  • Among our awards during the quarter were three scopes of this work in West Virginia, Wisconsin and Minnesota, including the previously announced emissions control project. We continue to see a great deal of activity in the emissions control arena and have seen signs of strengthening industrial activity.

  • With regard to natural gas, our backlog of $247 million is down 33%, or $122 million, versus the second quarter 2005 and down 16%, or $46 million, versus the first quarter '06. This was due to seasonal burn and the previously described exit of certain low margin contracts and MSA renewals with shorter than typical durations.

  • For telecommunications, our backlog of $221 million is up 17%, or $32 million, versus the second quarter '05 and down 5%, or $12 million, compared to the first quarter of this year. This is reflective of a year over year increase in dark fiber contracts and lesser amounts of master service agreement construction work.

  • An important component of our value building strategy has been and continues to be making acquisitions that complement our existing businesses and divesting those businesses that do not fit with our core strategy and can be monetized. We will continue to pursue select acquisitions that are immediately accretive and that contribute directly to our strategic objectives.

  • During the first -- the second quarter we announced the formation of the InfraSource Technology division with the hiring of three nationally renowned T&D consultants. We are very excited to add their capabilities to our portfolio of services and look forward to their growth and contribution to our customers and the company. On a divestiture front, we closed the sale of a small unit, Mechanical Specialties, that was non-core to our operation.

  • Before turning over the call to Terry, I'd like to spend a few minutes discussing the contract loss to which I alluded previously. While our second quarter operating results on balance were at the high end of our previously announced guidance, we are disappointed that they were diminished by the recognition and order of a project loss. As we approach the midpoint of completion on one of our transmission projects in the Southwest, we observed that our rates of production or productivity were proving to be less than anticipated during our normal project reviews.

  • Upon detection of these trends we immediately dispatched a team to assess the situation and identify appropriate mitigating actions. Our assessment has now been completed and we have taken the steps necessary to mitigate the extent of this loss. Our investigation revealed that the project loss was due primarily to less than anticipated field productivity attributable to ineffective supervision, difficult labor market conditions, supplier issues and extremely hot weather.

  • We booked a full loss of $5 million and reversed previously recorded profits of $1.6 million during this quarter, consistent with our revenue recognition policy for projects in a forecasted loss position. Steps are being taken to further mitigate this loss, including changes in project leadership, the addition of more experienced workers, replacement of a key supplier, changes to the staffing and sequencing of work, and of course pursuit of recoveries.

  • We've also completed reviews of our other major transmission projects to ensure that we do not have any additional situations at risk of significant deterioration. We continue to invest in the enhancement of our project management and execution capabilities and are in the process of hiring a number of additional personnel with significant experience in this area.

  • Now I'd like to turn the call over to Terry Montgomery, our CFO, who will discuss our financial results for the quarter in more detail and our outlook for the third quarter of 2006. Terry?

  • Terence Montgomery - CFO

  • Thank you, Dave.

  • Revenues for the second quarter of 2006 increased $26.3 million, or 11%, to $258 million as compared to $231.7 million for the second quarter of last year. This increase in revenues for the quarter was due to growth in our electric and telecommunications and market revenues, offset by an anticipated decline in natural gas market revenues. Net income for the second quarter was $5.3 million, or $0.13 per diluted share, versus a net loss of $1.4 million, or $0.04 per diluted share, for the second quarter of last year.

  • As indicated in the table accompanying our press release, income as adjusted was $8.5 million for the second quarter versus loss as adjusted at $0.3 million for the second quarter of last year. The primary reconciling items included $2.6 million after-tax charge for acceleration of amortization of previously capitalized debt financing costs associated with our recent refinancing and $0.06 -- I'm sorry, $0.6 million after-tax expenses related to the SFAS123R charge implemented on January 1st, 2006.

  • Net income for the second quarter of 2006 included the entire anticipated transmission project loss that Dave discussed of $5 million and reversal of previously recognized profits of $1.6 million. For comparative purposes, it should be noted the net loss for the second quarter of 2005 included a charge of $8.5 million for an underground utility construction project loss.

  • EBITDA from continuing operations for the second quarter was $17.3 million compared to $8.5 million for the second quarter of 2005, which is an increase of 104%. Excluding the items outlined in the table accompanying our press release, EBITDA as adjusted was $22.5 million for the second quarter versus $8.5 million for the second quarter a year ago, an increase of 165%.

  • As in the past, we've provided certain non-GAAP measures in order to enhance understanding of our operating performance. These non-GAAP measures demonstrate how we as management evaluate the results of operations exclusive of the effects of certain non-operational items. Reconciliation to net income for these various non-GAAP financial measures are included in the tables accompanying our press release.

  • Also included in this morning's press release is a table for reference which details our revenue and backlog by our three primary end markets, including a breakdown of our electric end market by transmission, substation and other electric work.

  • Our SG&A expense for the second quarter of 2006 was $23 million, or 8.9% of revenue, compared to $17.7 million, or 7.6% of revenue, for the same period last year. Our increase in SG&A expense is due to the hiring of additional personnel over the past year to manage current and projected growth as well as the addition of $1 million of expense for share-based compensation under SFAS123R.

  • At June 30th we had total backlog of $916 million, as Dave previously outlined. You'll recall that we classify contracts as backlog when we have been awarded the contract and we've received the notice to begin work. Our backlog includes an estimate of work to be completed under master service contracts.

  • At the end of the second quarter we had $20 million of cash on our balance sheet, $34 million in letters of credit outstanding, primarily to secure our insurance programs, and no drawings under our revolving credit facility.

  • As previously announced, we entered into a new credit agreement on June 30th with a syndicate led by Bank of America. The new $225 million senior secured revolving credit facility matures on June 30th, 2012 and replaces our previous $85 million revolving credit facility and $84 million term loan. With the consummation of the new facility, we've reduced our total senior debt to $75 million, increased our borrowing availability from $51 million to $116 million and reduced the rates on our borrowings by 150 basis points.

  • The new facility will provide us with considerable flexibility for future growth, including the right to seek additional commitments to increase the size of the facility to $350 million. Details on this facility can be found on our Form 8-K filed with the Securities and Exchange Commission on July 3rd, 2006. Our current cash balance is approximately $20 million and we believe we have sufficient liquidity to meet our expected operating and capital needs.

  • Days sales outstanding improved by 13 days during the quarter to 75 days at the end of the second quarter compared to 88 days at the end of the first quarter and 81 days at the end of the second quarter of 2005. We calculate DSO as accounts receivable plus cost and estimated earnings in excess of billings, less billings in excess of cost and estimated earnings, divided by the average revenues per day in the quarter.

  • Capital expenditures were $9.4 million for the second quarter as compared to $7.5 for the same quarter last year. Over one-half of capital expenditures were in our telecomm business segment focused on dark fiber growth.

  • Regarding our outlook for third quarter of 2006, we expect revenues of $260 to $275 million and earnings per share of $0.22 to $0.25 per diluted share, including pre-tax expenses of approximately $950,000 relating to SFAS 123R-based -- share-based compensation expense and $300,000 of amortization of intangible assets. Our gross margin percentage for the third quarter is expected to be in the range of 15% to 16% due to the current mix of work in our backlog. Our SG&A expenses for the third quarter will be approximately $24 to $25 million. Depreciation for the quarter is expected to be approximately $6.7 million and net interest expense will be approximately $1.5 million, reflecting the interest rates and fees associated with our new credit facility. Capital expenditures for the third quarter are expected to range from $9 to $11 million. Our effective tax rate will be approximately 41% and our expected weighted average diluted shares outstanding are approximately $40.3 million.

  • For the full year of 2006, our expectation is for revenues in the range of $940 to $960 million and GAAP net income of $0.55 to $0.60 per diluted share, which is within previously stated full year guidance when considering the $0.06 refinancing charges included in that range. Our full year earnings range also includes the project loss charge of $0.10 and SFAS123R and amortization expenses combined at approximately $0.07.

  • This concludes our formal presentation and we will now open up the lines for questions.

  • Operator

  • Thank you.

  • [OPERATOR INSTRUCTIONS]

  • Our first question comes from Alex Rygiel with Friedman, Billings and Ramsey. Please go ahead.

  • Alex Rygiel - Analyst

  • Thank you. Good morning, gentlemen.

  • David Helwig - CEO

  • Good morning, Alex.

  • Alex Rygiel - Analyst

  • A couple of quick questions, first with regards to the disappointing project in the quarter. What is the total revenue of that project that's anticipated over the time period?

  • David Helwig - CEO

  • Over which time period?

  • Alex Rygiel - Analyst

  • Well, the entire project, how large is the project?

  • Terence Montgomery - CFO

  • The entire project is about a $24 million contract, Alex.

  • Alex Rygiel - Analyst

  • Okay, and it's about half complete, so you've got about another 12 million that'll hit your P&L with no associated operating profit, is that correct?

  • Terence Montgomery - CFO

  • That's correct. So when we book the loss, as we've stated before, we book the entire amount of loss in the quarter for the expectation and given no change in profitability, would be revenues with zero profit for the balance of the contract.

  • Alex Rygiel - Analyst

  • And was this a project that had anything to do with the hurricanes last season or is this totally unrelated to that?

  • David Helwig - CEO

  • No, it's in the Southwest.

  • Alex Rygiel - Analyst

  • Thank you. And then with regards to the current quarter you mentioned that you booked a performance bonus. How large was that?

  • David Helwig - CEO

  • We actually, Alex, consider that extremely proprietary commercial information.

  • Alex Rygiel - Analyst

  • Fair enough. Was the size of that performance bonus abnormally larger than your typical performance bonus that you're booking throughout all the different quarters?

  • David Helwig - CEO

  • Yes, it represented exceptional performance.

  • Alex Rygiel - Analyst

  • Okay. And then with regards to the competitive marketplace out there, can you talk a little bit about new projects that you're winning, how many competitors you're seeing today on those new projects versus, say, 12 months or 24 months ago? Are you seeing the competitive nature improve?

  • David Helwig - CEO

  • I think we've indicated before that these days we're seeing fewer than we were certainly 24 months ago and probably fairly stable over the last year. Of course it depends what type of work and we do quite a variety of work, as you're aware.

  • Alex Rygiel - Analyst

  • Of course.

  • David Helwig - CEO

  • I don't think there's any one easy answer to that.

  • Alex Rygiel - Analyst

  • As it relates to electrical transmission project work that you're bidding on, is that -- ?

  • David Helwig - CEO

  • Again, it depends on the size and scale of the project.

  • Alex Rygiel - Analyst

  • Thank you.

  • Operator

  • Our next call comes from Sanjay Shrestha with First Albany. Please go ahead.

  • Sanjay Shrestha - Analyst

  • Great, thank you. A couple of quick question here, guys. First of all, good quarter. Number one, the transmission backlog is up nicely and it seems like there's a lot of work coming your way. So is it fair to say that looking forward the mix on the backlog as well revenue, natural gas portion of your business, unless you can really get it down on a much better margin than what you have right now, will continue to sort of show that decline?

  • David Helwig - CEO

  • Well, we -- yes, I think, Sanjay, I'll paraphrase back to you our perspective. We are concentrating on the profitability of our natural gas distribution work, as we've indicated before, and are driving productivity in the field to increase its profitability and being very selective about the contract terms under which we're doing that work. So yes, I think that adds up to what you said.

  • Sanjay Shrestha - Analyst

  • Okay. Okay, fair enough. Now, looking at essentially again this project in the quarter here, you guys said that you've evaluated other projects as well and feel pretty comfortable with what's in the backlog. I think, Dave, you mentioned that -- well, one of the issues was field productivity. And in this tight labor environment, I think you did mention hiring some more people. Can you go into some more details as it relates to, number one, your competitor advantage, number two, how many other transmission projects can you support at this point in time, and number three, maybe a level of comfort that will sort of address [inaudible], and there's always a chance in the EMC industry for a cost overrun every now and then, but the likelihood of that is minimal going forward?

  • David Helwig - CEO

  • That was a few questions all at once, Sanjay. I'll try.

  • Sanjay Shrestha - Analyst

  • Sure.

  • David Helwig - CEO

  • I guess first with regard to the labor market, as we've discussed before, the ability to attract and retain and employ on our work a workforce that is experienced and is skilled with the work that we're performing clearly is a factor. As there is more transmission work not only being performed by us but by others, that market for those particularly skilled and experienced individuals clearly becomes more competitive. So that's a factor that we need to consider in our bidding and in our planning. We've been very fortunate to have a substantial workforce with substantial experience that we've been able to move from project to project and that's a part of our success.

  • As we've discussed before, we do need to be cautious and not get ahead of ourselves in terms of expanding to take on work without the experienced resources to perform it effectively or else one has to account for that in the pricing. To say anything beyond kind of the general statements that I think you'd hear from everybody in the industry, I think those become competitively sensitive information.

  • As far as the reviews of other projects, we did undertake independent reviews of our other large projects that are underway, as I indicated, and received affirmative evaluations of each of them.

  • Sanjay Shrestha - Analyst

  • Okay, okay, terrific. And one last question if I could, Dave. I know you don't want to get into specific detail, but with now all this incremental positive news flow from the FERC side as well, when you look at the transmission portion of your prospects today versus, let's say, a quarter ago or maybe let's say a year ago, is there a way maybe you can sort of give us a sense in terms of how much or what is an uptick in that and sort of what the profit opportunity look like?

  • David Helwig - CEO

  • I can give you some color on that, Sanjay. Actually, just evidenced by the kind of continuous stream of announcements by utilities and regional planning organizations of additional projects is indicative of more work than ever on the horizon. I mean every study, every announcement, they all line up that way, as you're well aware.

  • Sanjay Shrestha - Analyst

  • Yes.

  • David Helwig - CEO

  • The challenge, of course, that we face is that specificity of theirtiming. It'd be really great if everybody got together and lined them up beginning to end ideally for us. Of course it never quite works that way with large project work.

  • Sanjay Shrestha - Analyst

  • Sure.

  • David Helwig - CEO

  • So the constant challenge is tracking schedule slippages and changing proposed timelines for the project and focusing on those in the right time frames that we can best perform. Right now we're really, really busy right now, as you can tell and as we've indicated before. But those existing projects come to an end and the exact timing of the replacement of those remains subject to change and not all that clear and certain right now. It's kind of the bane of this kind of work.

  • Sanjay Shrestha - Analyst

  • Terrific. That's great. And if I could, one last one actually. With your transmission portion of the backlog up as much as it is, utility CapEx going up, doesn't look like there's been any sort of an impact for the T&D spending despite the fuel charges maybe or emission control related work, do you see that dynamic changing at all as we move forward going to the latter part of this year or maybe even in early '07 and maybe sort of like the self-correcting phenomenon for lack of labor pool and maybe a competitive advantage like you to win the right kind of the projects?

  • David Helwig - CEO

  • It's an excellent question and I wish I had a great crystal ball about that. So really, I'll kind of paraphrase your question about will the aggregate CapEx requirements that the utilities are facing require them to temper any one of these markets?

  • It's an interesting question. There's actually a couple of articles that have been written in professional journals recently on that subject that are speculating in that regard. As I read those articles, one of the conclusions is it's impossible to generalize, that in each case it's a customer-by-customer specific situational analysis that's required.

  • Sanjay Shrestha - Analyst

  • Okay.

  • David Helwig - CEO

  • It is something that we're looking at but can't make sense out of the macro trends there and it'll remain to be seen. Interesting thesis that there could be a self-equilibrating dynamic here and in fact we have seen some of our customers with large amounts of transmission work to be performed working very diligently to space it out and time its sequence to kind of work relative to the availability of qualified companies and resources. So we do see balancing and re-jiggering the timing, if you will, of projects to comply at least with workforce. And I guess it would be fair to say in some other situations with regard to budget constraints.

  • Sanjay Shrestha - Analyst

  • Yes.

  • David Helwig - CEO

  • Now, to the extent there's rebalancing of course, between, let's say, power plant work and scrubber work and T&D work, of course we're on both sides of that equation, if you will.

  • Sanjay Shrestha - Analyst

  • Sure. Okay, that's very helpful. Thanks a lot, guys.

  • Operator

  • We'll now go to Jamie Cook with Credit Suisse. Please go ahead.

  • Jamie Cook - Analyst

  • Hi, good morning.

  • David Helwig - CEO

  • Morning, Jamie.

  • Jamie Cook - Analyst

  • Dave, I guess my first question related to the problem project we had in the quarter, it sounds like you feel comfortable that there's not another shoe here to drop. But I guess could you just go into a little more detail in terms of the changes that you've made, has there been any changes in management or the processes, just so we could get more comfortable?

  • David Helwig - CEO

  • Sure. First of all, Jamie, with regard to its detection, we do have a system of project measurements and controls and formal reviews of each project on a monthly basis and it was during the course of those reviews that we detected some developing trends that were of concern and that's what triggered a full-blown response and investigation and evaluation. So we have, in fact, changed the project manager on this job.

  • And as far as the conduct of the work, with the new project manager and our -- some independent experts that we brought in to assist, we have re-sequenced the methodology to conduct a number of the field activities that are proving to make a significant difference in the flow of the work and its efficiency. And additionally we were able to recruit a sizeable number of people that became available that are specifically experienced with certain aspects of this work. So we think -- probably I'd site those three factors as the most significant mitigating measures that have been taken.

  • Jamie Cook - Analyst

  • And just to be clear, you have -- you do feel very comfortable that there are no other projects here in the near term that you know of right now that could be problematic?

  • David Helwig - CEO

  • The confidence that we're expressing on that is based on independent reviews that were performed at those other major projects that are going.

  • Jamie Cook - Analyst

  • Great.

  • David Helwig - CEO

  • [inaudible-microphone inaccessible]

  • Jamie Cook - Analyst

  • And then -- sorry.

  • David Helwig - CEO

  • No, I was going to say there always in the E&C business can be developments that you can't foresee right now, but we've been very deliberate about our reviews and measurements at the ongoing projects and the conduct of independent reviews, especially after this -- the development of this situation, to make sure that we can have confidence in those ongoing indications.

  • Jamie Cook - Analyst

  • Okay. And then I guess the flip side -- the flip side to this is if you back out the problem project, you had a phenomenal quarter.

  • David Helwig - CEO

  • You could add the numbers up that way.

  • Jamie Cook - Analyst

  • Yes. So then it brings me back to your guidance for the third quarter and I always thought -- what are you at, $0.22 to $0.25? I mean if you back out the third quarter -- well, first of all, if you back out the charge in the second quarter, you earned what, $0.29 or so, excluding the refinancing. And then I look at your guidance for the third quarter and you're saying $0.22 to $0.25. It looks like your implied margins, gross profit margins in the third quarter are lower sequentially than the second quarter and I guess I'm just trying to understand. I always thought the third quarter seasonally was the strongest quarter of the year where it looks like we're seeing a decline in the third quarter. So I'm just trying to understand why we're lower sequentially.

  • David Helwig - CEO

  • A fair question. I think in large measure the answer to that would be related to the performance bonuses that void up profitability in the second quarter. And we do see the third quarter as continuing strong quarter.

  • Jamie Cook - Analyst

  • Okay.

  • Terence Montgomery - CFO

  • We also had some gains on sale of equipment in the second quarter that were higher than we normally have. And when compared to the third quarter of last year, we had $0.15 EPS, so it's still strong year over year growth.

  • David Helwig - CEO

  • We consider it very strong.

  • Jamie Cook - Analyst

  • Well, no, I'm not complaining. But the gain on the sale of equipment, how big was that, Terry, or much more -- versus your expectations?

  • Terence Montgomery - CFO

  • If you look at other income, we had about 1.4 million of other income that flows through that line and it's the majority of the income in there.

  • Jamie Cook - Analyst

  • Okay. And then, Dave, I guess just my last. To get back into the favorable performance awards, I'm assuming there's a lot more opportunities out there for you guys to receive these performance awards, which could help earnings going forward?

  • David Helwig - CEO

  • That's hard to say. That depends on the contract terms and form. There's quite a variety of contracts. Most typically our higher margins come from earning up on fixed price projects, if you will, not using contingency and performing the work more productively. So by and large our contracts typically do not include the opportunity for large performance bonuses per se, but rather the opportunity to earn up. So that depends on the mix of contracts and how customers choose the contract for the work.

  • So that's -- well, that's a hard one to answer in aggregate. We do have other projects with performance bonus opportunities in their contract form, but it's not the dominant form of contract. Sometimes those bonus opportunities are based on schedule, sometimes they're based on beating budget estimates, frequently when they exist they have safety performance as a factor in them. That would be most consistently applied opportunity.

  • Jamie Cook - Analyst

  • Okay, great. Thanks a lot.

  • Operator

  • Our next question comes from Rich Wesolowski with Sidoti & Co. Please go ahead.

  • Rich Wesolowski - Analyst

  • Thanks a lot. Good morning.

  • David Helwig - CEO

  • Morning, Rich.

  • Rich Wesolowski - Analyst

  • Hey, Dave, you booked about $300 million in transmission work over the past year. About how many projects does that represent? What's the average size of the jobs, just on a ballpark basis?

  • David Helwig - CEO

  • I'll bet the average, 10 million?

  • Terence Montgomery - CFO

  • 10 to 15 million probably on average. The largest was about 50.

  • David Helwig - CEO

  • But appreciate that's quite a mix of 1 to 50, if you will. Probably averages out in that 10 to 15 range.

  • Rich Wesolowski - Analyst

  • Okay. On the problem job, was there any claim revenue put on the balance sheet?

  • Terence Montgomery - CFO

  • Yes, there is a small amount; it's about $1.4 million.

  • Rich Wesolowski - Analyst

  • Okay. Looking at the SG&A growth in relation to sales, it's accelerated significantly over the past three quarters or so. I know you have some charges in there now that you haven't had previously, but do you guys target a dollar growth for SG&A looking out toward the second half '06 and even into '07 or is it keeping it under a certain proportion of sales?

  • Terence Montgomery - CFO

  • We do look at it both ways, Rich. The guidance we gave actually at the beginning of the year was 9 to 9.5% of revenue for the year. With the current guidance we'll be somewhere around that 9.5% level. Our original guidance was exclusive of ERP, which we are now starting the implementation of during the second half of the year, so there's some additional expense related to that.

  • Also, as Dave mentioned, personnel that we recruited to enhance management, included in there are some recruiting fees and severance costs and we also have the new technology group that for the balance of this year is building up their book of business.

  • Rich Wesolowski - Analyst

  • Okay. You might have mentioned, you usually do, I'm not sure if I missed it, what proportion of the backlog is going to come second half of this year versus next year?

  • Terence Montgomery - CFO

  • Let me look that up. I'll come back to you on the answer on that.

  • Rich Wesolowski - Analyst

  • Okay. That's all I got. Thanks.

  • David Helwig - CEO

  • Rich, one additional thought on the SG&A. We -- in conjunction with our ERP implementation, we are also evaluating SG&A improvement opportunities that are quite frankly for us locked up quite a bit because we do not have an efficient ERP system.

  • Terence Montgomery - CFO

  • The answer on the backlog is about -- between 420 to 440 would be in the balance of the year.

  • Rich Wesolowski - Analyst

  • Thanks a lot.

  • Operator

  • We'll now go to John Rogers with D.A. Davidson. Your line is open.

  • John Rogers - Analyst

  • Hi, good morning.

  • David Helwig - CEO

  • Good morning, John.

  • John Rogers - Analyst

  • A couple of things. First of all, just to be clear, Dave, when you talked about the buildup in electrical work, the shortages of people out there, are you now seeing higher pricing in that market and fewer competitors?

  • David Helwig - CEO

  • Again, it depends what kind of work it is. But as I mentioned in response to Sanjay, depending on the type of work, we're seeing fewer competitors for example for large project work than for small project work. So as far as pricing, it's always a dynamic in competitive market.

  • John Rogers - Analyst

  • Sure, but presumably then some of that is being reflected in bidding out?

  • David Helwig - CEO

  • Sure, but we all face the same challenges with regard to labor.

  • John Rogers - Analyst

  • Okay.

  • David Helwig - CEO

  • And if we're all smart and we're having less experienced labor, that's going to be reflected in pricing.

  • John Rogers - Analyst

  • Okay. And then just following up on Jamie's question earlier about the third quarter, I'm curious also looking into the fourth quarter. Based upon your guidance, it looks like revenue levels are going to fall off quite a bit, profitability comparable to a year ago. Is that just seasonal factors and last year we had unusually good or is it project timing?

  • Terence Montgomery - CFO

  • Primarily seasonal factors and there is some project timing in there. It's also always uncertainty in the fourth quarter of what some utilities will do in advance of closing out their year and how much budget they have left over to spend. Sometimes we'll see an acceleration, sometimes we don't.

  • David Helwig - CEO

  • With regard to the project timing, there are a number of projects that we have been tracking that we were hopeful would actually be working in the fourth quarter that have slipped out into the first quarter or earlier next year. So there's some degree of that as well. But overall, I'd characterize that we believe this year's performance, as we've reflected in guidance, is quite strong.

  • John Rogers - Analyst

  • Yes.

  • Terence Montgomery - CFO

  • Final piece, John, would be we mentioned in the first quarter that we had excess revenues because of the good weather and some of that is a pull-through from later in the year because -- especially on the natural gas side. The utilities have somewhat static budgets and if they spend it in the early part of the year, they're not going to spend it in the fourth quarter.

  • David Helwig - CEO

  • Good point, Terry, and we have begun to see the effect of that in some number -- some select number of customers.

  • John Rogers - Analyst

  • Okay. And on the natural gas work, some of those larger multiyear contracts that you were awarded over a year ago, when do those start coming up for renewal or extension?

  • Terence Montgomery - CFO

  • There is a two to three year cycle, so each year we've got some portion of them coming up. I don't have a current tally of what is coming up for renewal in the first quarter of next year. But as we've said, we're going to take it on pricing terms that meets our return on capital requirements and if we don't get it at that level, we'll continue to reduce. At this point, we feel like we've somewhat plateaued in that reduction.

  • John Rogers - Analyst

  • Okay, but that -- the soonest that would be would be first quarter?

  • Terence Montgomery - CFO

  • Yes.

  • John Rogers - Analyst

  • Okay. Thanks, Dave. Thanks, Terry.

  • Operator

  • We'll now go to Barry Haimes from Sage Asset Management. Please go ahead.

  • Barry Haimes - Analyst

  • Hi, good morning. I just wanted to be clear on the status of the review of the major projects that resulted from the one loss project that you had in the quarter. Did you say that review is completed and you don't see any more problems or the review is still ongoing and at some future time we'll know for sure that you still feel comfortable? Thanks.

  • David Helwig - CEO

  • Thanks for the clarifying question. Yes, those reviews have been completed.

  • Barry Haimes - Analyst

  • Okay, wonderful. Thanks so much.

  • Terence Montgomery - CFO

  • Though we continue to evaluate all of our projects each month and quarter as we do our closing processes and our normal project management processes. But that [inaudible] check was completed.

  • Barry Haimes - Analyst

  • Great. Thanks so much.

  • Operator

  • We'll now go to Eric Beaumont from Copia Capital. Please go ahead.

  • Eric Beaumont - Analyst

  • Hi, guys.

  • David Helwig - CEO

  • Morning, Eric.

  • Eric Beaumont - Analyst

  • Most everything I had was asked, but a couple of quick questions. One is when you're talking about guidance for next quarter and the rest of the year, given the performance bonus we saw this quarter is it safe to assume that you would assume no performance bonuses in your guidance and that would all be kind of excess?

  • David Helwig - CEO

  • That's correct.

  • Eric Beaumont - Analyst

  • Okay. And secondly, just thinking about obviously transmission buildout, Connecticut has a lot of work going on, and then substation work between Con Ed and then with the heat we're seeing, a lot of people having transformer issues, thinking more substations, just give a little bit of a state of the market kind of in northeast in particular?

  • David Helwig - CEO

  • Yes, great question. You must be in New York or Connecticut.

  • Eric Beaumont - Analyst

  • Actually Chicago.

  • David Helwig - CEO

  • Well, that's -- in the northeast I guess the most newsworthy and noteworthy at the moment problems have been in New York City with the outages that have occurred there. The kind of problems that are at least publicly known that I'm aware of are what we would consider to be distribution type level. In other words, it's not the major transmission lines or substations but rather appears to be problems at the distribution level.

  • Now, there also have been a number of articles written and actually comments by government officials on the fact that there have not been major transmission level problems but that things have been very, very tight and precarious.

  • So I think regardless, if we just blend that altogether, the very high electric loads and the reliability problems that have manifest themselves do bode well for continued increases and emphasis in transmission and distribution expenditures. It is of course very regional. Connecticut, New York, they continue to be hot spots, as does California and a few other major metropolitan areas.

  • Eric Beaumont - Analyst

  • One last quick question. With respect to the project you were just talking about, difficult labor markets in particular and [inaudible], I'm just curious, are you really seeing a much more regionalized basis? I mean if you think about the mix of your projects, do you see more difficult labor markets in any portion of the country and are you taking any specific steps to alleviate or to limit exposure to those areas?

  • David Helwig - CEO

  • That's a good question and the -- yes, there in general are differences in regional markets in our experience. We take an approach to much of our major project work that uses a substantial amount of portability of our experienced workforce as one means of overcoming that.

  • And we, as I indicated, we very deliberately consider the availability of resource, labor specifically, but leadership as well in our pursuit of project opportunities both in terms of the number of projects and their locations in the country that we choose to pursue. So, definitely not an easy answer but a significant consideration, I guess, is the best short answer to your question.

  • Eric Beaumont - Analyst

  • Great. I appreciate the time. Thank you.

  • Operator

  • Now for a follow-up question we'll go to Alex Rygiel from Friedman, Billing and Ramsey. Please go ahead.

  • Alex Rygiel - Analyst

  • Thank you. Just to sort of confirm the math, if you used the high end of your full year guidance and the high end of your third quarter guidance, that would imply that your fourth quarter guidance is something like 210 million in revenue. That compares to about 223 last year. It would sound like the year over year decline is mostly due to the one-time revenue in last year's fourth quarter associated with the hurricanes. Is that correct such that your guidance for the fourth quarter this year is really kind of, worst case scenario, flattish year over year?

  • Terence Montgomery - CFO

  • It's a couple of pieces, Alex. Yes, the hurricane impact in the fourth quarter, there was hurricane revenues there. It wasn't significant. I think it might be in the range of $10 million. But the other components are, as we discussed, the kind of the pull forward of some work, especially on the natural gas side because the weather in the first quarter was so good, and then also some uncertainty around other utility spend and just timing of completion of some projects. So it's a combination of those things.

  • David Helwig - CEO

  • But you do touch on a subject that we do not have anything in the forecast for storm related activities. We do not budget and forecast for that.

  • Alex Rygiel - Analyst

  • Great. Thank you.

  • Operator

  • There appears to be no further questions at this time. I would like to turn the call back over to our moderator, Mr. David Helwig. Please go ahead, sir.

  • David Helwig - CEO

  • Great. Thank you, ladies and gentlemen, for participating today. As you've heard, we're very pleased with our results for the second quarter and we believe that we are well positioned for the remainder of 2006 and future growth. We do look forward to speaking with you on our next call.

  • Operator

  • That does conclude today's teleconference. Thank you for your participation and have a lovely day.