    Operator

  • Greetings and welcome to the Nano Nuclear first quarter 2026 financial results and business update call.(Operator Instructions) It is now my pleasure to introduce your host.

    歡迎參加Nano Nuclear 2026年第一季財務表現及業務更新電話會議。 (操作說明)現在,我很榮幸地向大家介紹主持人。

  • Matthew Barry - Director of Investor Relations and Capital Markets

    Matthew Barry - Director of Investor Relations and Capital Markets

  • Thank you and good afternoon, everyone. Joining me on the call today are Jay Yu, Nano Nuclear's founder, Chairman and President; James Walker, our CEO; and Jaisun Garcha, our CFO.

    謝謝大家,下午好。今天與我一起參加電話會議的有 Nano Nuclear 的創始人、董事長兼總裁 Jay Yu;我們的執行長 James Walker;以及我們的財務長 Jaisun Garcha。

  • Please note that today's press release and slide presentation to accompany this webcast are available on our website. Before moving ahead, I'll quickly address forward-looking statements made on this call. As reflected in more detail on slide 2, today's presentation contains forward-looking statements about Nano's future that are made under the safe harbor provisions of the applicable federal securities laws.

    請注意,今天的新聞稿和與本次網路直播配套的幻燈片簡報已發佈在我們的網站上。在繼續討論之前,我將快速回應本次電話會議中所做的前瞻性陳述。如投影片 2 更詳細反映的那樣,今天的簡報包含有關 Nano 未來的前瞻性聲明,這些聲明是根據適用的聯邦證券法的安全港條款作出的。

  • You are cautioned that actual results, including without limitation, the results of Nano's microreactor development activities, strategies, timelines, and other operational plans may differ materially and adversely from those expressed or implied by the forward-looking statements.

    請注意,實際結果(包括但不限於 Nano 的微反應器開發活動、策略、時間表和其他營運計劃的結果)可能與前瞻性聲明中明示或暗示的結果有重大不利差異。

  • Important risk and other factors that could cause actual results to differ from those in our forward-looking statements are contained in our filings with the SEC. Including our annual report on Form 10-K filed this past December, which you are encouraged to review.

    可能導致實際結果與我們的前瞻性聲明中的結果存在差異的重要風險和其他因素,均已列入我們向美國證券交易委員會提交的文件中。其中包括我們去年 12 月提交的 10-K 表格年度報告,我們鼓勵您查閱。

  • The forward-looking information provided today is accurate only as of today, and Nano disclaims any obligation to update any information provided except as required by law. With that, I'll turn the call over to Jay Yu, Nano's founder, Chairman, and President.

    今天提供的前瞻性資訊僅截至今天有效,除法律要求外,Nano 不承擔更新任何資訊的義務。接下來,我將把電話交給 Nano 的創辦人、董事長兼總裁 Jay Yu。

  • Jiang Yu - Chairman of the Board of Director, President, Treasurer, Secretary

    Jiang Yu - Chairman of the Board of Director, President, Treasurer, Secretary

  • Thank you, Matt, and thank you everyone for joining the call today. Nano Nuclear continues to differentiate itself as a microreactor developer with a focus on vertical integration across the nuclear fuel supply chain. We are advancing our hronos MMR, a high TRL, high temperature gas cooled reactor design backed by decades of operating history and meaningful prior capital investment.

    謝謝馬特,也謝謝今天參加電話會議的各位。Nano Nuclear 繼續保持其作為微型反應器開發商的獨特優勢,專注於核燃料供應鏈的垂直整合。我們正在推進我們的 Hronos MMR,這是一款高技術成熟度、高溫氣冷反應器設計,擁有數十年的運行歷史和大量的先前資本投資。

  • Which we believe can significantly de-risk future construction, licensing, and deployment. We expect the compact modular design of our Kronos MMR system to support factory fabrication, repeatable construction, and learnings that can accelerate deployment timelines and drive cost efficiencies over time.

    我們認為這可以顯著降低未來建設、授權和部署的風險。我們期望 Kronos MMR 系統的緊湊模組化設計能夠支援工廠製造、可重複建造,並能透過學習加快部署進度,並隨著時間的推移提高成本效益。

  • Importantly, we believe the inherent safety profile of our Kronos MMR can enable a smaller footprint, co-location, and off-grid deployment. Unlocking high value applications previously unavailable to traditional nuclear reactors.

    重要的是,我們相信 Kronos MMR 固有的安全特性可以實現較小的佔地面積、共址部署和離網部署。解鎖傳統核反應器以前無法實現的高價值應用。

  • We paired this foundation with a focus on vertical integration across critical aspects of the nuclear fuel supply chain which we believe will give us an advantage over our competitors, uniquely positioning us to expedite reactor deployment, benefit from growing nuclear renaissance, and enhance long-term economics of our reactors.

    我們將這一基礎與對核燃料供應鏈關鍵環節的垂直整合相結合,我們相信這將使我們比競爭對手更具優勢,使我們能夠以獨特的方式加快反應器部署,從日益增長的核能復興中受益,並提高反應器的長期經濟效益。

  • Turning to our Q1 highlights, we continue to make meaningful progress across business during this quarter. Our Chronos MMR continues to advance towards licensing and construction. We completed site characterization and drilling at the University of Illinois and are incorporating those results into our planned construction permit application to the US Nuclear Regulatory Commission. We also signed a formal MOU with the board of trustees at the University of Illinois detailing the next steps as we advance the project.

    回顧第一季的亮點,本季我們在各項業務方面繼續取得實質進展。我們的 Chronos MMR 計畫正朝著許可和建設方向持續推進。我們在伊利諾大學完成了場地特徵分析和鑽探工作,並將這些結果納入我們向美國核管理委員會提交的施工許可證申請中。我們也與伊利諾大學董事會簽署了一份正式的諒解備忘錄,詳細說明了我們在推進該計畫時需要採取的後續步驟。

  • The state of Illinois announced that we will receive $6.8 million in incentive awards, underscoring growing support for advanced nuclear technology. In Canada, we continue to make progress towards initiating formal licensing following our acquisition of Global First Power, now rebranded as True North Nuclear.

    伊利諾伊州宣布我們將獲得 680 萬美元的獎勵,這凸顯了對先進核技術日益增長的支持。在加拿大,我們收購了 Global First Power(現已更名為 True North Nuclear),並繼續朝著正式頒發許可證的方向努力。

  • And lastly, we're advancing discussions with numerous supply chain partners for key components and la le items. As well as discussions with commercial enrichment provider and trio manufacturers to procure fuel for our first Chronos MMR prototypes.

    最後,我們正在與眾多供應鏈合作夥伴進行關鍵零件和相關產品的討論。此外,我們還與商業濃縮供應商和三重燃料製造商進行了討論,以採購我們第一批 Chronos MMR 原型機的燃料。

  • On the commercial side, we signed a feasibility study agreement with Bob Rupo to evaluate the potential deployment of many Chronos MMR systems to provide up to 1 gigawatt of power for their AI data center and manufacturing campus under development.

    在商業方面,我們與 Bob Rupo 簽署了一項可行性研究協議,以評估部署多個 Chronos MMR 系統為其正在開發的 AI 資料中心和製造園區提供高達 1 吉瓦電力的潛在可能性。

  • We believe this announcement highlights the potential scalability of our platform for customers with significant energy needs. Nano is also expanding its pipeline of potential data center, industrial and military customers interested in Kronos for a range of power needs.

    我們相信,此次公告凸顯了我們平台對於能源需求量大的客戶而言具有潛在的可擴展性。Nano 也在擴大其潛在的資料中心、工業和軍事客戶群,這些客戶對 Kronos 的各種電源需求感興趣。

  • Nano saw growing interest for potential strategic partners highlighted by a recent MOU with DS Dansuk to explore localization, manufacturing, and deployment opportunities for Kronos's reactors in South Korea and the broader Asian region.

    Nano 發現,潛在的策略合作夥伴越來越感興趣,最近與 DS Dansuk 簽署了一份諒解備忘錄,旨在探索 Kronos 反應器在韓國和更廣泛的亞洲地區的在地化、製造和部署機會。

  • DS Dansuk is a leading South Korean industrial enterprise with extensive capabilities in energy, chemical processing, and advanced manufacturing, providing a strong platform to support commercialization of our technology.

    DS Dansuk 是一家領先的韓國工業企業,在能源、化學加工和先進製造方面擁有強大的實力,為我們技術的商業化提供了強大的平台。

  • We also signed an MOU with MRSco to explore integration of their EPC capabilities for deployments for our Kronos MMR systems on federal and commercial sites. These announcements reflect a broader trend of interest from strategic partners, including established companies with decades of experience with large scale energy and industrial infrastructure projects, who recognize the value proposition of Kronos.

    我們也與 MRSco 簽署了一份諒解備忘錄,探討如何整合他們的 EPC 能力,以便在聯邦和商業場所部署我們的 Kronos MMR 系統。這些公告反映了戰略合作夥伴的廣泛興趣趨勢,其中包括在大型能源和工業基礎設施項目方面擁有數十年經驗的成熟公司,他們認識到 Kronos 的價值主張。

  • As it relates to our strategic focus on vertical integration, we also made progress towards expanding our conversion and transportation capabilities through active exploration partnerships and acquisitions. In addition, our strategic affiliate List Technologies received a key radioactive material license for Tennessee's demonstration facility.

    就我們對垂直整合的策略重點而言,我們也透過積極的勘探合作和收購,在擴大轉化和運輸能力方面取得了進展。此外,我們的策略夥伴 List Technologies 獲得了田納西州示範設施的關鍵放射性材料許可證。

  • While also announcing plans to invest $1.38 billion over time to build a commercial enrichment facility in Oak Ridge, Tennessee. Supported by its patented laser enrichment technology each of these announcements reinforce our progress in securing our nuclear fuel supply chain.

    同時宣布計畫分階段投資 13.8 億美元,在田納西州橡樹嶺建造一座商業濃縮設施。憑藉其專利雷射濃縮技術,這些公告都進一步鞏固了我們在保障核燃料供應鏈方面的進展。

  • From a financial perspective, we raised gross proceeds of [$400 million]. And October private placement significantly strengthening our balance sheet and ex extending our operational runway. This capital raise included participation from a growing base of institutional investors, reflecting increased confidence in our strategy and execution. We were also added to the Morgan Stanley National Security Index, further expanding our visibility among institutional investors.

    從財務角度來看,我們籌集了總收益[4億美元]10 月的私募配售顯著增強了我們的資產負債表,並延長了我們的營運資金。此次融資吸引了越來越多的機構投資者參與,這反映出他們對我們的策略和執行力越來越有信心。我們也被納入摩根士丹利國家證券指數,進一步提高了我們在機構投資者中的知名度。

  • Our Q1 progress reflects our continued execution, advancing Kronos towards licensing, construction, expanding commercial traction, working to expand our vertical integration across the nuclear fuel supply chain, and maintaining our strong financial position to support execution of our long-term strategy.

    第一季的進展反映了我們持續的執行力,推動 Kronos 向許可、建設、擴大商業吸引力邁進,努力擴大我們在核燃料供應鏈中的垂直整合,並保持我們強勁的財務狀況以支持我們長期戰略的執行。

  • We believe our progress to date differentiates technology and strategy have positioned us to be a key benefactor of the global nuclear renaissance driven by several durable secular growth trends. These include growth in demand and reliable baseload energy for AI data centers, industrial reshoring, and a broader electrification, energy sustainability, independence, and climate mandates. And unprecedented policy support.

    我們相信,迄今為止我們在技術和戰略方面取得的進展,使我們成為全球核能復興的主要受益者,而全球核能復興是由幾個持久的長期成長趨勢所驅動的。這些因素包括人工智慧資料中心對可靠基荷能源的需求成長、工業回流以及更廣泛的電氣化、能源永續性、獨立性和氣候要求。以及前所未有的政策支持。

  • Recent developments in the US power markets are bringing increased focus on each of these trends. Electricity demand tied to AI data centers and other power intensive applications is expanding faster than the new generation and transmission can be delivered, creating rising concerns around power availability, grid expansion, and energy affordability. In January, the administration supported an emergency auction organized by the largest regional grid operator.

    美國電力市場的最新發展使得人們更加關注這些趨勢。與人工智慧資料中心和其他高耗能應用相關的電力需求成長速度超過了新發電和輸電能力的提升速度,引發了人們對電力供應、電網擴容和能源價格承受能力的日益擔憂。今年1月,政府支持了由最大的區域電網營運商組織的緊急拍賣。

  • Aimed at driving 15-year power purchase agreements to fund an estimated [15 billion] of new generation. The same grid operator is also considering co-location generation policies to help large energy users bring supply closer to demand. While these actions are important and reflect a growing recognition of current power bottlenecks, they alone are unlikely to close the structural GAAP between demand growth, and reliable supply.

    旨在推動簽訂 15 年的購電協議,為預計 [150 億] 的新發電項目提供資金。該電網營運商也考慮採用共址發電政策,以幫助大型能源用戶將供應更靠近需求。雖然這些措施很重要,也反映出人們越來越認識到當前的電力瓶頸,但僅靠這些措施不太可能彌合需求成長與可靠供應之間的結構性差距。

  • Against that backdrop, we believe assets capable of delivering high uptime, long-term cost, certainty, and operational resilience independent of constrained grid infrastructure are likely to command a meaningful premium in the future.

    在此背景下,我們認為,能夠提供高正常運作時間、長期成本、確定性和獨立於受限電網基礎設施的營運彈性的資產,未來可能會獲得可觀的溢價。

  • We view our Kronos MMR as an ideal future solution to address. These challenges, which are expected to intensify in the years ahead. By offering the potential to provide behind the meter or off-grid base load power directly to the end users and customers, we can help meet expected demand growth without driving higher costs for everyday Americans.

    我們認為 Kronos MMR 是解決未來問題的理想解決方案。這些挑戰預計在未來幾年會加劇。透過向最終用戶和客戶提供表後或離網基本負載電力,我們可以幫助滿足預期的需求成長,而不會增加美國一般民眾的成本。

  • In short, the recent actions across the country are reinforcing the need for global nuclear renaissance and highlighting what we have long believed reliable, clean base load energy is a strategic necessity, and we are building our Kronos MMR as a next generation solution aligned with national priorities, customer needs, and long-term economics of the AI-driven energy future.

    簡而言之,全國各地最近的行動正在強化全球核能復興的必要性,並凸顯了我們長期以來所認為的可靠、清潔的基礎負荷能源是一種戰略必需品,我們正在將 Kronos MMR 建設成為符合國家優先事項、客戶需求和人工智能驅動的能源未來長期經濟效益的下一代解決方案。

  • Before handing the call over to our CEO James, I'll briefly highlight why we view 2026 as an important year with multiple potential catalysts offering the opportunity to create shareholder value.

    在將電話交給我們的執行長詹姆斯之前,我將簡要介紹為什麼我們認為 2026 年是一個重要的年份,因為有多個潛在的催化劑為創造股東價值提供了機會。

  • First, we expect progress towards regulatory licensing of Kronos in the US and Canada. We are targeting submission of a construction permit application to the NRC in the coming months to formally begin the US licensing process. This submission will represent a key milestone that could set the stage for initial construction at the University of Illinois in mid to late 2027.

    首先,我們期待 Kronos 在美國和加拿大獲得監管許可方面取得進展。我們計劃在未來幾個月內向美國核能管理委員會提交施工許可證申請,正式啟動美國許可程序。這項提交將是一個重要的里程碑,預計將為伊利諾大學在 2027 年中後期開始的初步建設奠定基礎。

  • Second, we see potential for several commercial announcements this year reflecting growing interest in our Kronos MMR from customers in several markets.

    其次,我們看到今年可能會有幾項商業公告發布,這反映出多個市場的客戶對我們的 Kronos MMR 越來越感興趣。

  • Third, we're advancing discussions on commercial partnerships and acquisition opportunities across nuclear fuel supply chain, providing the potential to address key bottlenecks in areas like conversion and field transportation.

    第三,我們正在推進關於核燃料供應鏈中商業合作和收購機會的討論,這有可能解決轉換和現場運輸等領域的關鍵瓶頸。

  • And lastly, we expect additional progress towards strategic partnerships that could accelerate and de-risk large scale deployment of our reactors while also significantly expanding commercial opportunities globally.

    最後,我們期待在策略夥伴關係方面取得更多進展,這將加速並降低我們反應器大規模部署的風險,同時顯著擴大全球商業機會。

  • With that, I'll turn the call over to James.

    接下來,我將把電話交給詹姆斯。

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • Thank you Jay. Let me start with a brief update of our University of Illinois prototype project, which will be essential to advancing our Kronos MMR towards commercial deployment. As Jay mentioned, we've completed site characterization and drilling and also signed an MOU with UFI's board of trustees to outline the next steps for the design, construction, ownership and operation of our Kronos MMR system on campus.

    謝謝你,傑伊。首先,讓我簡要介紹我們在伊利諾大學的原型項目,這對於推進我們的 Kronos MMR 實現商業部署至關重要。正如 Jay 所提到的,我們已經完成了場地特徵描述和鑽探工作,並且與 UFI 的董事會簽署了一份諒解備忘錄,概述了我們在校園內 Kronos MMR 系統的設計、建造、所有權和運營的下一步措施。

  • We remain on track to submit our construction permit application to the NRC in the coming months under the Part 50 licensing pathway. Our team is working on the application closely with AEcom and other partners and have begun engaging with the NRC for several months to ensure alignment on scope and technical requirements.

    我們仍按計劃在未來幾個月內根據第 50 部分許可途徑向美國核管理委員會提交施工許可證申請。我們的團隊正與 AEcom 和其他合作夥伴密切合作開發該應用程序,並且已經與 NRC 進行了幾個月的溝通,以確保在範圍和技術要求方面達成一致。

  • In parallel, we are advancing discussions to procure key long lead components including discussions around reactor pressure vessel capacity, fuel enrichment and fabrication, graphite supply, and other key components.

    同時,我們正在推進有關採購關鍵長週期部件的討論,包括反應器壓力容器容量、燃料濃縮和製造、石墨供應以及其他關鍵部件的討論。

  • Based on our progress to date, we aim to begin construction in mid to late 2027 and see a realizable roadmap to a full-scale prototype online in or around 2030. Our team is also evaluating opportunities to accelerate this schedule and secure additional project funding to reduce overall capital costs. Turning to our growing pipeline of commercial opportunities, we believe growing commercial interest has been driven by Chronos's compelling value proposition.

    根據我們目前的進展情況,我們的目標是在 2027 年中後期開始建設,並製定一個可行的路線圖,在 2030 年左右實現全尺寸原型機的上線。我們的團隊也在評估加快專案進度和爭取額外專案資金以降低整體資本成本的機會。展望我們不斷成長的商業機會,我們認為,Chronos 極具吸引力的價值主張推動了商業興趣的成長。

  • Chronos has a strong safety profile that we expect to enable co-location directly at the customer site and provides the option for off-grid power. Chronos is also particularly well suited for large scale multi-unit deployments where reactors can be connected and scaled over time to match customer demand. It's modular architecture and compatibility with factory fabrication and standardized production.

    Chronos 具有強大的安全性能,我們預計它能夠直接在客戶現場進行共址部署,並提供離網供電選項。Chronos 也特別適合大規模多單元部署,反應器可以連接起來,並隨著時間的推移進行擴展,以滿足客戶需求。它採用模組化架構,相容於工廠製造和標準化生產。

  • Create the opportunity to capture meaningful economies of scale as we deploy at larger scales. We believe manufacturing efficiencies combined with operational learning curves can position us to achieve highly competitive economics over time while still delivering the 24/7 reliability and uptime that data centers, industrial customers, and other mission critical users require.

    創造機會,在大​​規模部署的過程中獲得有意義的規模經濟效益。我們相信,製造效率的提升加上營運學習曲線的提升,能夠使我們在長期保持極具競爭力的經濟效益的同時,還能滿足資料中心、產業客戶和其他關鍵任務使用者對全天候可靠性和正常運作時間的需求。

  • Moreover, Kronos' patented flexible design also provides the ability to serve projects with smaller power needs requiring only one or several units, expanding our served available market to new applications previously unavailable to nuclear energy.

    此外,Kronos 的專利靈活設計也使其能夠服務於電力需求較小的項目,這些項目只需要一台或幾台設備,從而將我們服務的市場擴展到以前核能無法觸及的新應用領域。

  • During the quarter, we announced a feasibility study with Barupon to evaluate the potential deployment of up to 1 gigawatt of power to support their AI data center and manufacturing campus. We are actively advancing the study, which includes the site evaluation, project scoping and timeline development.

    本季度,我們宣布與 Barupon 進行可行性研究,以評估部署高達 1 吉瓦電力來支援其人工智慧資料中心和製造園區的潛在可能性。我們正在積極推進這項研究,其中包括場地評估、專案範圍界定和時間表制定。

  • Following completion, we will aim to perform EPC cost estimates, begin early project development activities and work towards finalizing a formal agreement to sell our reactors. Beyond Barupon, we continue to build a growing pipeline of prospective customers across data center, industrial and military applications.

    完成後,我們將著手進行EPC成本估算,開始早期專案開發活動,並努力最終達成正式協議以出售我們的反應器。除了 Barupon 之外,我們還在資料中心、工業和軍事應用領域不斷拓展潛在客戶群。

  • A consistent theme across these discussions is the need for reliable baseload power, particularly solutions with favorable footprints that can be deployed behind the meter to reduce grid dependence and accelerate deployment timelines. Notably, power requirements for these projects range from below 50 megawatts up to one gigawatt plus.

    這些討論中反覆出現的主題是需要可靠的基礎負載電力,特別是佔地面積小、可以部署在用戶側的解決方案,以減少對電網的依賴並加快部署進度。值得注意的是,這些項目的電力需求從 50 兆瓦以下到 1 吉瓦以上不等。

  • We also see meaningful opportunities in additional markets where Kronos is well suited, including remote communities, mining operations, and other energy intensive applications requiring reliable off-grid solutions. And as Jay highlighted, we're making progress towards several strategic partnerships we believe can further expand our commercial reach and accelerate deployment, beginning with our recent MOU with DS Danz.

    我們也看到了 Kronos 在其他市場的巨大潛力,包括偏遠社區、採礦作業以及其他需要可靠離網解決方案的能源密集應用。正如 Jay 所強調的那樣,我們正在朝著幾個戰略合作夥伴關係邁進,我們相信這些合作夥伴關係可以進一步擴大我們的商業範圍並加速部署,首先是我們最近與 DS Danz 簽署的諒解備忘錄。

  • We recently announced a collaboration with DS Dansuk, a leading South Korean industrial company, to accelerate deployment of our Kronos MMR in South Korea. DS Dansuk brings deep capabilities and operational experience across energy, chemical processing and advanced manufacturing, along with long-standing relationships across key industrial and government stakeholders in South Korea.

    我們最近宣布與韓國領先的工業公司 DS Dansuk 合作,以加速 Kronos MMR 在韓國的部署。DS Dansuk 在能源、化學加工和先進製造領域擁有深厚的實力和營運經驗,並與韓國的主要工業和政府利益相關者建立了長期合作關係。

  • We're confident their credibility within the Korean industrial ecosystem can facilitate engagement with state-owned entities as well as potential Korean industrial customers seeking reliable, carbon-free base load energy.

    我們相信,他們在韓國工業生態系統中的信譽可以促進與國有企業以及尋求可靠、無碳基礎負載能源的潛在韓國工業客戶的合作。

  • As such, our collaboration with DS Dansuk has the potential to meaningfully de-risk regulatory licensing, as well as accelerate site identification and project development, facilitate introductions to prospective customers, and support localization of manufacturing and component production within South Korea.

    因此,我們與 DS Dansuk 的合作有可能大幅降低監管許可的風險,加快選址和專案開發,促進與潛在客戶的接觸,並支持在韓國境內實現製造和零件生產的本地化。

  • Moreover, we also see this collaboration as a pathway to strengthen project financing opportunities and establish broader strategic partnerships that can accelerate commercialization and deployment in South Korea, one of the world's most sophisticated nuclear and industrial markets, as well as the broader Asia region.

    此外,我們也將此次合作視為加強專案融資機會、建立更廣泛的策略夥伴關係的途徑,從而加速在韓國(世界上最成熟的核能和工業市場之一)以及更廣泛的亞洲地區的商業化和部署。

  • Now that we've touched upon Kronos's growing commercial momentum and value proposition, I'd now like to elaborate on Kronos's technical differentiation. Kronos is supported by a proven and well understood foundation with nearly a decade of development and an estimated $120 million invested into its design by its prior owner.

    既然我們已經談到了 Kronos 不斷增長的商業動能和價值主張,我現在想詳細說明 Kronos 的技術差異化優勢。Kronos 擁有成熟且易於理解的基礎,經過近十年的發展,其前所有者估計已投入 1.2 億美元用於其設計。

  • We believe this materially de-risk the platform and provide a strong technical basis as we advance towards licensing and deployment.

    我們相信這將大大降低平台的風險,並為我們推進許可和部署提供強大的技術基礎。

  • Kronos' 15-megawatt electric design builds on high temperature gas cooled reactor technology that has been deployed and validated across multiple countries for more than five decades. Core elements of the design, including triso fuel, helium coolant, and graphite moderation, are mature technologies supported by extensive real-world operating data.

    Kronos 的 15 兆瓦電力設計基於高溫氣冷反應器技術,該技術已在多個國家部署和驗證了五十多年。該設計的核心要素,包括三元燃料、氦冷卻劑和石墨​​慢化劑,都是成熟的技術,並有大量的實際運行數據支援。

  • Beyond the reactor itself, our balance of plant strategy prioritizes commercially proven systems, including steam generators, turbines, and thermal energy storage technologies already in use in today's concentrated solar plants.

    除了反應器本身之外,我們的輔助設備策略優先考慮商業上已驗證的系統,包括蒸汽發生器、渦輪機和熱能儲存技術,這些技術目前已在聚光太陽能發電廠中使用。

  • We also expect to operate within conservative temperature and pressure parameters that align with successful deployments. As a result, our focus is not on developing new or experimental reactor technology, but on integrating well understood components into a compact modular microreactor platform that can be licensed, manufactured, and deployed efficiently.

    我們也希望在符合成功部署要求的保守溫度和壓力參數範圍內進行操作。因此,我們的重點不是開發新的或實驗性的反應器技術,而是將成熟的組件整合到一個緊湊的模組化微反應器平台中,該平台可以有效地進行授權、製造和部署。

  • With that operating history in mind, I'll now outline the key advantages of Kronos as a prismatic, high temperature gas cooled reactor. First, on technology readiness, prismatic high temperature gas cooled reactors utilize well characterized materials with established commercial supply chains, and the performance data from prior deployments provides a high TR level foundation for our design.

    考慮到其運行歷史,我現在將概述 Kronos 作為棱柱形高溫氣冷反應器的主要優勢。首先,就技術成熟度而言,稜柱形高溫氣冷反應器採用特性明確的材料,並擁​​有成熟的商業供應鏈,先前部署的性能數據為我們的設計提供了高技術成熟度的基礎。

  • Second, the safety profile is fundamentally different from other reactor types. Trisso fuel retains fission products at extreme temperatures. Helium is an inert coolant, and the design relies on passive heat removal. As such, we don't expect a credible meltdown pathway, and the core can shut itself down without reliance on active safety systems. Third, prismatic high temperature gas cooled reactors are inherently simple. There are few active systems and high stress components, and many elements can be commercially off the shelf rather than safety grade.

    其次,其安全特性與其他反應器類型有著根本的不同。Trisso燃料能夠在極端溫度下保留裂變產物。氦氣是一種惰性冷卻劑,該設計依靠被動散熱。因此,我們預計不會出現可信的熔毀路徑,堆芯可以在不依賴主動安全系統的情況下自行關閉。第三,棱柱形高溫氣冷反應器本質上結構簡單。主動系統和高應力零件很少,而且許多元件可以採用市售現成產品,而不是安全級產品。

  • The core configuration itself has no moving part other than the control rods, and the materials are inert and well understood, contrasting with the complexity of certain other advanced designs.

    核心結構本身除了控制桿之外沒有其他活動部件,而且材料惰性且易於理解,這與其他一些先進設計的複雜性形成了鮮明對比。

  • Fourth, prismatic high temperature gas reactors like Kronos are especially well suited for export. The use of riso fuel presents minimal proliferation risk compared with other fuel technologies, and the superior safety case potentially offers streamlined licensing with international regulators.

    第四,像 Kronos 這樣的稜柱形高溫氣體反應器特別適合出口。與其他燃料技術相比,使用riso燃料的擴散風險最小,而且其卓越的安全性有望簡化與國際監管機構的授權流程。

  • Fifth, we believe this architecture is uniquely flexible. In particular, the standard design can be deployed for smaller capacities by simply decreasing operating pressure. This flexibility allows Chronos' output to be scaled without redesign to meet the needs of a wide array of customers.

    第五,我們認為這種架構具有獨特的靈活性。具體來說,只需降低工作壓力,即可將標準設計應用於較小容量的場合。這種靈活性使得 Chronos 的產量無需重新設計即可擴展,以滿足各種客戶的需求。

  • And lastly, we believe these characteristics could enable lower long-term maintenance and stronger economies of scale. An inert coolant, passive safety and advanced fuel reduce the need for complex chemistry controls and high maintenance systems.

    最後,我們認為這些特性可以降低長期維護成本,並實現更強的規模經濟效益。惰性冷卻劑、被動安全措施和先進燃料減少了對複雜化學控制和高維護系統的需求。

  • Combined with a simpler design and greater use of non-specialized commercial components, we see opportunity for reduced operating costs, lower maintenance costs, and favorable cost scaling over time.

    結合更簡單的設計和更多使用非專用商用組件,我們看到了降低營運成本、減少維護成本以及隨著時間的推移實現有利的成本擴展的機會。

  • Our focus on vertical integration stems from our belief that one of the largest constraints to deploying advanced reactors at scale isn't the reactor technology, but fuel availability. We're working to gain exposure to several critical stages of the fuel cycle, starting with enrichment through our collaboration with our affiliate LIST Technologies.

    我們之所以專注於垂直整合,是因為我們相信,大規模部署先進反應器的最大限制因素之一不是反應器技術,而是燃料供應。我們正在努力了解燃料循環的幾個關鍵階段,首先是透過與我們的附屬公司 LIST Technologies 的合作來了解濃縮過程。

  • List owns the only US origin patented laser enrichment technology, and our relationship with List has the potential to provide Nano with a differentiated uranium enrichment solution. In parallel, we're exploring opportunities to build our capabilities in conversion and fuel transportation through strategic commercial partnerships and acquisitions.

    List 擁有美國唯一獲得專利的雷射濃縮技術,我們與 List 的合作關係有可能為 Nano 提供差異化的鈾濃縮解決方案。同時,我們正在探索透過策略性商業合作和收購來提升我們在轉換和燃料運輸方面的能力的機會。

  • Further progress in each of these areas can not only de-risk future reactor deployments but also positions Nano to generate revenue across the nuclear fuel cycle while remaining aligned with federal funding opportunities and national energy security needs.

    在這些領域取得進一步進展,不僅可以降低未來反應爐部署的風險,還可以使 Nano 在整個核燃料循環中創造收入,同時與聯邦資金機會和國家能源安全需求保持一致。

  • With that, I'll turn the call over to our CFO Jaisun to provide financial highlights.

    接下來,我將把電話交給我們的財務長 Jaisun,由他來介紹財務方面的要點。

  • Jaisun Garcha - Chief Financial Officer

    Jaisun Garcha - Chief Financial Officer

  • Thank you, James. I'll now provide a summary of our Q1 financial performance. Our overall cash position increased significantly during the quarter, ending the period with cash and cash equivalents of $577.5 million. This was an approximate $374 million increase during the quarter ended December 31, driven by the net proceeds of our successful October 2025 private placement.

    謝謝你,詹姆斯。接下來我將概述我們第一季的財務表現。本季我們的整體現金狀況顯著增加,期末現金及現金等價物達到 5.775 億美元。截至 12 月 31 日的季度,該季度增長了約 3.74 億美元,這主要得益於我們 2025 年 10 月成功完成的私募配售的淨收益。

  • We're confident our substantial cash balance and proven ability to raise capital at scale position us well to accelerate development and commercialization of the Kronos MMR. Our strong financial position also provides flexibility to pursue value of creative opportunities via M&A and strategic partnerships to enhance our vertical integration.

    我們相信,我們雄厚的現金儲備和大規模籌集資金的成熟能力,使我們能夠加速 Kronos MMR 的開發和商業化。我們雄厚的財務實力也使我們能夠靈活地透過併購和策略合作來尋求創造價值的機會,從而加強我們的垂直整​​合。

  • Turning to the income statement, Q1 loss from operations was $11.6 million. The higher year over year loss resulted from an approximate $8 million increase in operating expenses. A substantial majority of these expenses focused on advancement of our Kronos MMR and other strategic growth opportunities.

    從損益表來看,第一季營業虧損為 1,160 萬美元。年比虧損增加是由於營運費用增加了約 800 萬美元。這些支出中的絕大部分都集中在推動我們的 Kronos MMR 和其他策略成長機會。

  • Q1 net loss totaled $6.5 million up approximately $3 million from the comparable prior year period. The net loss was lower than the loss from operations as we earned approximately $5 million of interest income on our larger cash balance. Net cash used in operating activities increased by approximately $1 million from the prior year period to $4 million.

    第一季淨虧損總計 650 萬美元,比去年同期增加約 300 萬美元。由於我們較大的現金餘額帶來了約 500 萬美元的利息收入,淨虧損低於營運虧損。經營活動所用現金淨額較上年同期增加約 100 萬美元,達到 400 萬美元。

  • This resulted from the aforementioned increase in G&A and R&D expenses. Net cash used in investing activities totaled $3.1 million and included payments for our Oak Brook, Illinois engineering facility. Before turning the call over to the operator for Q&A, I'd like to reiterate that our strong balance sheet places us in a great position to execute our strategy of advancing our Kronos MMR and enhancing our vertical integration.

    這是由於前述的行政管理費用和研發費用增加所致。投資活動使用的淨現金總額為 310 萬美元,其中包括支付給位於伊利諾州奧克布魯克的工程設施的款項。在將電話轉交給接線員進行問答之前,我想重申,我們強勁的資產負債表使我們處於非常有利的地位,可以執行我們的策略,推進 Kronos MMR 並加強我們的垂直整​​合。

  • As we look ahead, we will continue to generate value for shareholders by allocating our time and capital prudently toward opportunities offering compelling return on investment. With that, I'll now turn the call over to the operator to open up the call for Q&A.

    展望未來,我們將繼續謹慎地分配時間和資金,抓住能帶來可觀投資回報的機會,進而為股東創造價值。接下來,我將把電話交給接線員,開始問答環節。

  • Operator

    Operator

  • (Operator Instructions)

    (操作說明)

  • Sameer Joshi, H C Wainwright.

    Sameer Joshi,H C Wainwright。

  • Sameer Joshi - Analyst

    Sameer Joshi - Analyst

  • Hey, good afternoon, guys, and thanks for taking my questions. So, the one strategic alliance you announced, with the DS Dansuk Group, are there any sort of milestones or catalysts over the next, 12 to 18 months that we should be watching out for?

    嘿,下午好,各位,感謝你們回答我的問題。那麼,您宣布與 DS Dansuk 集團達成的這項策略聯盟,在接下來的 12 到 18 個月內,有哪些里程碑或催化劑值得我們關注?

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • Hi, Sameer. So, yes, I, I'm quite pleased to answer a question about this actually, because the plan with DS Dansuk is actually a pretty large one. So, what they actually wanted was that they envisioned massive bottlenecks with regard to power for their industry.

    你好,薩米爾。所以,是的,我非常樂意回答這個問題,因為與 DS Dansuk 的合作計劃實際上相當龐大。所以,他們真正想要的是,他們設想他們的產業在電力方面出現巨大的瓶頸。

  • And so, when we went over there, me and the technical team, we were talking to them about how we actually create a manufacturing facility there. And we've been working with them in the interim months to break down the reactor into sections and how we would manufacture those sections, what can be done in Korea, what cannot be.

    所以,我和我的技術團隊去了那裡,和他們討論了我們如何在那裡建立一個製造工廠。在過去的幾個月裡,我們一直與他們合作,將反應爐分解成各個部分,以及我們將如何製造這些部分,哪些可以在韓國完成,哪些不能完成。

  • So, what's been happening over the last few months is we've been looking at what can be fabricated in Korea, what can be sourced there, where materials were going to come from, because one major thing that companies aren't looking at is that great, you build a reactor and it gets licensed. How are you going to mass manufacture that reactor? So, we're obviously turning our attention to that in the US, but the stanzuk wants to do the same thing with our reactor in North Korea.

    所以,過去幾個月發生的事情是,我們一直在研究哪些東西可以在韓國製造,哪些東西可以在韓國採購,材料將從哪裡來,因為公司沒有考慮到的一件重要事情是,太好了,你建造了一個反應堆,然後它就獲得了許可。你們打算如何大規模生產這種反應爐?所以,我們顯然正在美國關注這個問題,但史丹祖克也想對我們在北韓的反應爐做同樣的事情。

  • So, what we're likely going to see over the coming year is just more development in that direction. We were all going to put together a plan about how we arrive at a centralized local core manufacturing facility. To take, to keep the southern market initially, but it's really the whole, East Asia region where there's a huge demand for the product.

    因此,未來一年我們很可能會看到這方面有更多發展。我們原本打算共同製定一個計劃,探討如何建立一個集中化的本地核心製造工廠。首先要佔領南方市場,但實際上整個東亞地區對該產品的需求龐大。

  • So, I, in terms of what you are going to see, you're going to see more engagement with us in DS Dansuk. You're going to see that, MOU advancing into more critical planning stages. At some point you're going to start seeing, it's difficult to say exactly the timelines now. You're going to see industrial factories that are going to be built for the purposes of mass manufacturing reactor, and you're going to see additional, partnerships between us and them, regarding certain street, key strategic things like, partnerships on graphite acquisitions and fuel supply and things like that to get things into place.

    所以,就你們將會看到的而言,你們將會看到我們在 DS Dansuk 中更多的參與。你會看到,諒解備忘錄將進入更關鍵的規劃階段。在某個時候你會開始看到,但現在很難確切地說出時間表。你會看到為大規模生產反應器而建造的工業工廠,你還會看到我們與他們之間就某些關鍵戰略事項(例如石墨採購和燃料供應等方面的合作)建立更多夥伴關係,以使一切就緒。

  • The other part as well you're going to see is that. There's a big demand for this, so you're probably going to see some, related, news about our interaction with the government, with KHNP, with big vendors in South, and ultimately, over the years you'll see increasing contracts between ourselves and customers in the region, regarding, offtake agreements for power, PPA agreements, those kind of things as we look to actually.

    你還會看到另一部分。這方面的需求很大,所以你可能會看到一些相關的新聞,內容涉及我們與政府、KHNP、南方的大型供應商的互動,最終,在未來的幾年裡,你會看到我們與該地區的客戶之間簽訂越來越多的合同,包括電力購買協議、購電協議等等,正如我們實際所期待的那樣。

  • So that when we hit that period when we have the reactor fully constructed and licensed, we're then readily able to start manufacturing the reactor immediately, achieve economies of scale, and then start installing those reactors masse.

    這樣,當我們完成反應爐的建造和許可後,就可以立即開始製造反應堆,實現規模經濟,然後開始大規模安裝這些反應器。

  • Sameer Joshi - Analyst

    Sameer Joshi - Analyst

  • Understood. Thanks for that, teller, James. So, should we, I mean, we also talk about strategic partnerships worldwide but also within the US and North America. Should we also include, like a EPC kind of a, strong partnership, signed in this region?

    明白了。謝謝你,出納員詹姆斯。所以,我的意思是,我們不僅要談論全球戰略夥伴關係,還要談論美國和北美內部的戰略夥伴關係。我們是否也應該包括像EPC一樣,在該地區簽署的強有力的合作夥伴關係?

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • Yeah, so this is a very good point actually, because now is that we are on the verge of submitting our construction permit. We, we're very close to finishing that submission now. When that goes in, that means that we can pivot the technical team to be able to refocus on what the next big stages are. And one of the big next stages is going to have to be how we mass manufacture these things.

    是的,這一點確實非常重要,因為我們現在正處於提交施工許可證的邊緣。我們,我們離完成那份提交文件已經非常接近了。如果這項技術得以實施,那就意味著我們可以調整技術團隊,重新專注於下一個重要階段的工作。接下來的一大挑戰是如何大規模生產這些東西。

  • Now, beyond that, there becomes a larger question. Say we have 10 sites, 12 sites, whatever it is that we need to service. Now that is a lot of local construction crews that need to be coordinated and so the EPC element to this becomes quite important, because when you are doing that kind of, digging that well for the reactor to go into because it's fields all that concrete, that's all stuff that Nano doesn't have to be involved in it can locally contract out, but that's still a huge amount of coordination.

    現在,除此之外,還存在一個更大的問題。假設我們有 10 個站點、12 個站點,或我們需要服務的任何數量。現在需要協調許多當地的施工隊伍,因此EPC(工程、採購、施工)環節就顯得非常重要,因為當你進行那種挖掘反應堆井的工作時,由於需要澆築大量的混凝土,Nano公司不必親自參與,它可以將工作外包給當地承包商,但這仍然需要大量的協調工作。

  • So, you might have seen, partnerships between ourselves and Amoresco and hatch and previously actually even And, Hyundai, I think, we were involved in looking at how, we deploy this reactor, around the world. So, the EPCM, part of this is going to be a fairly large, component of how we deploy here. So, we have made a few announcements as we begin to look at how we deploy these things, how it gets coordinated.

    所以,您可能已經看到,我們與 Amoresco 和 Hatch 建立了合作關係,而且之前實際上還與現代汽車合作過,我認為,我們參與了研究如何在世界各地部署這種反應器。因此,EPCM(工程、採購、施工和管理)將是我們部署方式中相當重要的一環。因此,隨著我們開始研究如何部署這些設施以及如何協調這些設施,我們發布了一些公告。

  • That is obviously a very separate thing to DS Dansuk where they are where they are going to be an industrial factory partner, so they wouldn't be doing EPC, but those EPC contractors in the US are going to be very important. In South Korea, they're going to be just as important as well.

    這顯然與 DS Dansuk 的情況截然不同,DS Dansuk 將成為工業工廠合作夥伴,因此他們不會從事 EPC 業務,但美國的 EPC 承包商將會非常重要。在韓國,它們也將同樣重要。

  • Sameer Joshi - Analyst

    Sameer Joshi - Analyst

  • Understood. Thanks for that clarification. And then just one last one, the construction permit, should we see any, like news prior to your, like submitting the application which, also is it on track for, like first half of this year.

    明白了。謝謝你的解釋。最後還有一個問題,關於施工許可證,在我們收到任何消息之前,例如您提交申請之前,是否有任何消息,以及申請是否按計劃在今年上半年獲得批准。

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • It is on track for the first half this year. It's actually going very well at the moment. We've been quite aggressive about it, so we've worked, we, we've worked the team pretty hard on this one because it is a very big differentiator. There's actually not many companies.

    今年上半年一切進展順利。目前一切進展非常順利。我們在這方面採取了相當積極的策略,我們為此付出了很多努力,我們讓團隊在這方面下了很多功夫,因為這是一個非常重要的差異化因素。實際上,這類公司並不多。

  • There might be a lot of reactor companies that are sprouting up because it's a hot market. But there's nobody putting in for a construction permit because it is a big difference between a paper reactor that you can make in your bedroom and an application to actually build. There's a lot of technical data that need to go into it.

    由於市場火爆,可能會湧現許多反應器公司。但是沒有人申請施工許可證,因為在臥室裡製作紙質反應器和實際建造的申請之間存在很大的區別。這裡面要輸入很多技術資料。

  • I wouldn't say we're going to announce anything prior to the submission specifically on this, but we will announce when it gets submitted because it is important to let industry know where we are, and it is as well a very good indicator for the market that this is a very credible thing that's being taken forward at a time when, there's not a lot of reactors being constructed. And if we stick to our timelines, we should still be the first company in the US to build a full scale licensed microreactor system.

    我不會說我們會在提交之前就此事發布任何公告,但我們會在提交時發佈公告,因為讓業界了解我們的進展很重要,而且對於市場來說,這也是一個非常好的信號,表明這是一個非常可靠的項目,在目前反應堆建設不多的情況下,我們正在推進這個項目。如果我們按計劃進行,我們仍然會成為美國第一家建造全尺寸授權微型反應器系統的公司。

  • Sameer Joshi - Analyst

    Sameer Joshi - Analyst

  • Understood. Thanks, James. Congrats on the progress and good luck.

    明白了。謝謝你,詹姆斯。恭喜你取得進展,祝你好運。

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • Thank you.

    謝謝。

  • Operator

    Operator

  • Nate Pendleton, Texas Capital Bank.

    內特·彭德爾頓,德克薩斯資本銀行。

  • Nate Pendleton - Analyst

    Nate Pendleton - Analyst

  • Good afternoon and congrats on the continued progress. Staying on the same topic, James, in your prepared remarks, you mentioned looking at ways to accelerate the 2030 timeline for the UIUC project. Can you elaborate on the potential pathways there?

    下午好,祝賀你們持續進展。詹姆斯,繼續討論這個主題,你在事先準備好的演講稿中提到,正在研究如何加快伊利諾大學厄巴納-香檳分校計畫2030年時間表的實施。您能詳細說明一下可能的途徑嗎?

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • Sure. So, it's a very good question. So, obviously, there's, what's happened very recently is that there's been a huge amount of government pressure that has come onto the NRC to try and expedite timelines, and you've seen that manifest in things like the formal licensing period where it being firstly reduced to 18 months and then subsequently 12 months. So, there's a possibility that that the licensing process is expedited for us now. I would say with our 2030 timeline.

    當然。所以,這是一個很好的問題。所以,很顯然,最近發生的事情是,政府對核管委員會施加了巨大的壓力,試圖加快審批流程,這一點已經體現在正式許可期限上,先是縮短到 18 個月,然後又縮短到 12 個月。因此,我們的許可證辦理流程有可能加快。我認為按照我們2030年的時間表來看。

  • We've not factored into consideration these adjustments because We want to be as conservative as possible, but there's also a reality to the assessment of a reactor system for any regulator anywhere in the world, and their principal focus is safety. And to do to interrogate that property for any design, it is still very difficult to expedite that even if you throw people at the problem.

    我們沒有考慮這些調整,因為我們想盡可能保守,但對於世界各地的任何監管機構來說,評估反應器系統也存在現實問題,他們的主要關注點是安全。即使投入大量人力,要對任何設計進行效能評估,仍然非常困難。

  • So, the 2030 timeline could be expedited. It's certainly possible, but it's prudent, I think, for us to stick to that because there is a, there's been a tendency in recent years of companies to make very ambitious date targets, and I think all of those are going to be missed now or they're just going to keep evaluating and moving things right. We don't really want to be in that, that situation.

    因此,2030 年的時間表可以加快推進。這當然有可能,但我認為,我們堅持這樣做是明智的,因為近年來,很多公司都傾向於設定非常雄心勃勃的日期目標,我認為現在所有這些目標要么都會落空,要么他們只會不斷評估並調整方向。我們真的不想陷入那種境地。

  • If we say 20,130 and if it gets delivered earlier, great. If there are expedited timelines that benefit us as well, fantastic, I would say that aside from those sort of things, obviously we will work on the construction, get all that expedited, we've got a lot of resources already that we can pay for the construction of this. A lot of it will depend on industry and supply chains and those kind of things, but those things we're already identifying now and working on, so it's a lot of it is already de-risked.

    如果我們說數量是 20130,而且能提前交付,那就太好了。如果加快進度對我們也有好處,那就太好了。除了這些事情之外,我們顯然會努力推進建設,加快所有相關工作。我們已經有很多資源可以支付這項建設費用。很多因素取決於行業、供應鏈等等,但這些因素我們現在已經在識別和著手解決,所以很多風險已經降低。

  • The other thing I would say too is that what's missed a bit in industry is that a lot of companies might be focused very in the near term on getting their first reactor constructed and licensed. And obviously, that's a very important milestone. But when you hit that period and you have a reactor that can be commercially sold, how do you actually get economies of scale? You need to be able to mass manufacture it.

    我還要補充一點,業界有點忽略的一點是,很多公司可能在短期內非常專注於建造和獲得第一個反應爐的許可。顯然,這是一個非常重要的里程碑。但是,當發展到那個階段,並且擁有了可以商業銷售的反應器時,如何才能真正實現規模經濟?你需要具備大規模生產的能力。

  • So, when we talk about expediting the timelines, It would be very nice to hit 2030 and be in a position where we are actually able to start mass selling the reactor, and that's going to mean that over the next few years while the reactor is being constructed, we do actually refocus a lot of our attention on reactor core manufacturing facilities, how these things are going to be mass produced, how the EPCM contractors are going to get into place for coordinating localization.

    所以,當我們談到加快進度時,如果能在 2030 年實現反應爐的大規模銷售,那就太好了。這意味著在接下來的幾年裡,在反應爐建造的同時,我們將把很多注意力重新集中到反應爐核心製造設施上,研究如何大規模生產這些設施,以及如何讓 EPCM 承包商到位以協調本地化工作。

  • So, there's two answers to the question. One, there's a lot of initiatives that can benefit us and can move our timeline forward. And the other part is that if we really want to expedite ourselves as a business, we need to attack this problem now.

    所以,這個問題有兩個答案。第一,有許多措施可以讓我們受益,並能推進我們的時間表。另一方面,如果我們真的想加快業務發展,就必須立即著手解決這個問題。

  • So, once the construction permit goes in, we really want to focus people's energy on getting these, what can actually be manufactured in the US? How much can we centralize them? All of these different considerations will come into it. Which partners do we need to bring in to make certain components? Let's centralize their production capacities within this facility as well.

    所以,一旦施工許可證辦妥,我們就真的希望大家把精力集中在如何才能真正在美國生產這些東西?我們能將它們集中化到什麼程度?所有這些因素都會被考慮在內。我們需要引入哪些合作夥伴來生產某些零件?讓我們把他們的生產能力也集中在這個工廠。

  • All of this is going to be very important so that we hit the ground running when it gets to 2030, hopefully earlier, but again, the reason why we haven't adjusted those timelines is that we, myself and a lot of others in Nano, we've done a lot of licensing before, and we're very familiar with what's typically involved and even though there are pressures on the NRC to expedite things, it still seems prudent to us to keep the longer timelines because the evaluation process, it is difficult to see how it could be shortened substantially from what it currently is.

    所有這些都非常重要,這樣我們才能在 2030 年(希望更早)到來時迅速進入狀態。但是,我們之所以沒有調整這些時間表,是因為我和 Nano 的許多其他人之前做過很多許可工作,我們非常熟悉通常涉及的流程。儘管美國核管會 (NRC) 面臨著加快審批速度的壓力,但我們仍然認為保持較長的時間表是謹慎的,因為評估過程目前很難大幅縮短。

  • Nate Pendleton - Analyst

    Nate Pendleton - Analyst

  • Got it. That makes complete sense. So thanks for that detail. And then shifting gears a little bit for my follow-up, can you talk a bit about your decision, to announce the request for information for low-key MMR? Specifically, what options are your team looking at for that reactor design and have you received any notable feedback?

    知道了。完全合情合理。謝謝你提供這個細節。接下來,我想稍微轉換一下主題,您能否談談您決定低調宣布 MMR 資訊徵詢的決定?具體來說,您的團隊正在研究哪些反應器設計方案?您是否收到任何值得注意的回饋?

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • So we did. So, the interesting part about this was that the low-key design can be sort of a bit like a scaled-down Kronos reactor. So, as we work on Kronos, it has immediate benefits for the advancement of the low-key reactor. But the low-key reactor was originally envisaged as being a solution for space power. Now, when we began looking at actually, attributing more resources towards lowkey.

    於是我們就這麼做了。所以,有趣的是,這個低調的設計有點像是縮小版的克洛諾斯反應器。因此,在我們開發 Kronos 的過程中,它對推進低調反應器的發展有直接的好處。但這種低調的反應器最初被設想為太空能源的解決方案。現在,當我們開始真正審視這個問題時,我們決定將更多資源投入低調的策略中。

  • The, we looked at who the previous interests came from, and that was predominantly things like Blue Origin, NASA. These kinds of groups were interested in it because it was a very advanced space reactor type, and there was, this kind of examination of additional resources being allocated into Loki was coming at the same time when there was an emerging bigger push into space.

    然後,我們研究了先前的投資意圖來自哪些方面,發現主要來自像藍色起源、NASA 這樣的公司。這些團體對它感興趣,因為它是一種非常先進的太空反應器類型,而且,對分配給洛基的額外資源的這種研究,恰逢太空探索的浪潮興起。

  • And we realized actually we were in a very advantageous position to produce a working system that could actually supply power for a lot of these initiatives. So whether it was zero gravity or low gravity because it was a base, and this could be for, a variety of different applications in the space program. But we are not a space industry either.

    我們意識到,我們實際上處於非常有利的地位,可以開發出一個能夠為許多此類專案提供動力的可運行系統。所以,無論是零重力還是低重力,因為它是一個基地,而這可能用於太空計畫中的各種不同應用。但我們也不是航太工業公司。

  • We're not, we don't have space engineers, people who are involved in that space. So if we're going to pursue this, it needs to be done in partnership with groups that are involved in that space and know what they're doing.

    我們沒有,我們沒有航太工程師,也沒有從事航太領域的人員。所以如果我們打算推進這項工作,就需要與參與該領域並了解其運作方式的團體合作。

  • So when we put out the RFI, effectively, we were looking for partners already involved in that and they were looking for power. So, what we can say is that there were a number of companies that were looking for power that were not involved in that space, launch companies, people like that. So, we did receive a large number of RFIs, and I say I believe we just completed a submission with one at the moment.

    所以,當我們發出資訊徵詢書時,實際上,我們是在尋找已經參與其中的合作夥伴,而他們則在尋求權力。所以我們可以說,有很多公司在尋找能源,但它們並沒有涉足這個領域,例如發射公司等等。所以,我們確實收到了大量的 RFI(資訊徵詢書),而且我認為我們目前剛剛完成了一份提交。

  • Obviously, it's these are very early days and we're just putting our toe in the water of space of the space industry. It's not to say that Loki couldn't be applied in terrestrial environments either, but certainly we want to take advantage of the interest in the space industry. Loki had a big head start on a lot of other space reactor types, years and years and millions and millions of investment, and so that's what precipitated our interest to partner with people in the existing space industry because nuclear we know very well. Space industry a little bit foreign to us.

    顯然,現在還處於非常早期的階段,我們只是在太空工業領域試水。這並不是說 Loki 不能應用於地球環境,但我們當然希望利用人們對太空產業的興趣。Loki 比許多其他類型的太空反應器都領先一步,投入了數年時間和數百萬美元,因此,這促使我們有興趣與現有太空產業的人們合作,因為我們非常了解核能。航太工業對我們來說有點陌生。

  • Nate Pendleton - Analyst

    Nate Pendleton - Analyst

  • Got it. Well, thanks for taking my questions and congrats again.

    知道了。謝謝你回答我的問題,再次恭喜你。

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • Thank you.

    謝謝。

  • Operator

    Operator

  • Jeff Grampp, Northland Capital Markets.

    Jeff Grampp,北地資本市場。

  • Jeff Grampp - Analyst

    Jeff Grampp - Analyst

  • Evening guys, thanks for the time. James, I'm curious with respect to the supply chain and some of the work you guys are doing to engage, various partners and strategics there, what's your kind of assessment on the longest lead times or most challenging parts of that puzzle that need to get solved sooner rather than later? And is there any imminent need from your standpoint to solve any of these, say, in calendar 26, or would you say you have a little bit of time? Given the timing with engaging with the NRC, getting the permit, that sort of thing. Thanks.

    晚上好各位,感謝你們抽出時間。James,我對供應鏈以及你們為與各種合作夥伴和策略家合作所做的一些工作很感興趣,你認為最長的交付週期或最具挑戰性的部分是什麼?這些部分需要盡快解決嗎?從您的角度來看,是否有迫切需要解決這些問題,例如在 26 號日曆年內解決?或者您認為您還有一些時間?考慮到與美國核子管理委員會接洽、獲得許可等事宜的時間安排。謝謝。

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • So this is actually a very good question. I think it's pertinent to anybody involved in the nuclear space at the moment. So what I would say the advantage we have with Kronos is the vast majority of components are not that specialized. So, the complete adjacent plant that converts the thermal output of the reactor into electricity is an example basic turbine system.

    所以這確實是個非常好的問題。我認為這與目前任何從事核能領域的人息息相關。所以我認為 Kronos 的優點在於,絕大多數元件都不是那麼專業化。因此,將反應器的熱輸出轉化為電能的整個相鄰裝置就是一個基本的渦輪系統範例。

  • Even things like heat exchanges, control rod mechanisms, the citadel thing, these are all things that can be built independently of any NRC involvement. Obviously they need to be up to a certain standard which we can ensure, but the vast majority of components we don't need to worry about the long lead times. These are things that can be readily manufactured now or there are immediate solutions that are very obvious that can be put together in short order.

    即使是像熱交換器、控制棒機構、堡壘之類的東西,這些都是可以獨立於美國核管會(NRC)參與而建造的。顯然,它們需要達到一定的標準,我們可以確保這一點,但絕大多數零件我們不必擔心交貨週期過長的問題。這些東西現在就可以很容易地生產出來,或者有一些非常明顯的即時解決方案,可以很快地組裝起來。

  • Now there are actually components though that are Mologa lead items, so there's a number like our reactor and a number of other reactors use like nuclear grade graphite. And I would say that's a that's an item that needs special consideration because There's only, as far as I know, three nuclear grade graphite producers in the world. I think two are in China and one is in Japan.

    現在確實有一些零件是 Mologa 鉛製品,例如我們的反應器和其他一些反應器使用的核級石墨。我認為這是一個需要特別考慮的項目,因為據我所知,世界上只有三個核級石墨生產商。我認為其中兩輛在中國,一輛在日本。

  • Now what that means is that Obviously there's going to be a lot of demand for these things, but it's also, it's too much to expect more nuclear grade graphite to come online anytime soon. The reason why is that principally a lot of these manufacturers of this substance are located at the mine site. So first of all, you need, the graphite mine, and then to get yourself to a point where you reach that sort of certification level where you're where you're at an acceptable level of quality.

    這意味著,顯然這些東西會有很多需求,但同時,指望更多的核級石墨很快就會投入生產也是不切實際的。原因在於,這類物質的生產商大多位於礦區附近。首先,你需要石墨礦,然後讓自己達到那種認證水平,達到可接受的品質水平。

  • That can take a substantial amount of time. So, the time to bring a mine online to get producing and then get it certified, you could be looking at more than 10 years. So I expect at some point in the future North America will bring on some nuclear grade graphite line, but for the next few years, What we expect to do is just buy or even maybe even co-build production lines to make our graphite blocks with these manufacturers, so that's probably going to take us some investment that goes into that.

    這可能需要相當長的時間。因此,從礦山投產到獲得認證,可能需要超過 10 年的時間。所以我預計,未來某個時候,北美將會引進一些核級石墨生產線,但在接下來的幾年裡,我們打算購買,甚至可能與這些製造商合作建造生產線來生產我們的石墨塊,所以這可能需要我們進行一些投資。

  • We're obviously talking with them. We know what their prices are, and we're arranging for the first of a kind and second of a kind cause with these with these suppliers now. So that's obviously an important part of it. The other major part for the US is the fuel supply. Now the US is obviously throwing money back at the problem. The DOE has put billions of dollars back into things like enrichment.

    我們顯然在和他們溝通。我們知道他們的價格,現在我們正在與這些供應商洽談一項史無前例和一項史無前例的合作項目。所以這顯然是其中很重要的一部分。對美國而言,另一個重要部分是燃料供應。現在美國顯然正在投入資金來解決這個問題。美國能源部已將數十億美元重新投入濃縮鈾等領域。

  • But there's bigger bottlenecks beyond that. There's conversion considerations to provide the feed grade. Nano is actually investing a substantial amount of labor and. Involve itself in that she can have its own uranium hexafluoride, that it can then provide to enrichment companies, so it keeps ownership of that fuel.

    但除此之外,還有更大的瓶頸。需要考慮轉換因素才能達到飼料等級。Nano 實際上投入了大量的人力和物力。它參與其中,這樣它就可以擁有自己的六氟化鈾,然後將其提供給濃縮公司,從而保持對該燃料的所有權。

  • But the, but for everybody involved in this, that enrichment capacity to come online, whether it's Centris or Orrano or Liss Technologies or General Nator or even Eureko increasing their capacity, the timelines on that are a little bit uncertain. So, that's principally also why, Nano has opted to use, to make a reactor that can utilize LEU because that's fuel that can be manufactured today. Now, there's going to be.

    但是,對於所有參與其中的人來說,無論是 Centris、Orrano、Liss Technologies、General Nator 還是 Eureko 提高其產能,這些濃縮能力上線的時間表都有些不確定。所以,這主要也是 Nano 選擇製造能夠利用低濃縮鈾的反應器的原因,因為低濃縮鈾是現在可以生產的燃料。現在,一定會有的。

  • That's fine because most of ours use Halu fuel, so that means that even they might even have much longer wait times to get towards that fuel than we do because one, they're going to need a several things. If they're going to need a Category 3 site to be upgraded to a CAT 2 site that could take some time by the facility be licensed up to a level so it can handle CAT 2 material, so 10% to 20% material.

    那沒關係,因為我們大多數都使用Halu燃料​​,這意味著即使是他們,獲得這種燃料的等待時間也可能比我們長得多,因為首先,他們需要一些東西。如果他們需要一個 3 類場地升級到 2 類場地,那麼該設施可能需要一些時間才能獲得許可,使其能夠處理 2 類材料,也就是 10% 到 20% 的材料。

  • That that could be a long lead time too. We don't have to wait for that, which is fortunate. We could benefit from Halu fuel and the reactor will have the ability to switch out the LEU for Halu in the future, but we want to get going as soon as possible. But the fuel supply thing needs a lot of consideration and then related to that also is the fabrication of the Trio.

    那也可能需要很長的準備時間。我們不必等待那一天,這真是太好了。我們可以從 Halu 燃料中受益,而且反應器將來有能力用 Halu 取代 LEU,但我們希望盡快開始。但燃料供應問題需要仔細考慮,而與此相關的還有 Trio 的製造。

  • Now there are several companies that are really leading in this space. I would say, Standard Nuclear in partnership with Framatome. Framatome obviously has a huge experience with fuel and BWEXT, again, very experienced company, very competent, so there's no, there's, I don't think there's any risk that these big companies don't know how to do this kind of thing.

    現在,有好幾家公司在這個領域處於領先地位。我認為是 Standard Nuclear 與 Framatome 合作。Framatome 顯然在燃料和 BWEXT 方面擁有豐富的經驗,同樣是一家經驗豐富、能力很強的公司,所以我認為,這些大公司完全有能力做好這類事情,不存在任何風險。

  • What could happen with them is that there could be a bit of a bottleneck on fuel supply just because of the demand, so getting in now and putting in the orders is going to be very important. And then 2, what we're weighing up at the moment is the right contracts because even though we understand the first of a kind reactor might be expensive, we need to have a sustainable fabrication toll fee applied to the material that we supply the fabricators. So they can make the trio.

    可能出現的情況是,由於需求旺盛,燃料供應可能會出現一些瓶頸,所以現在下訂單非常重要。其次,我們目前正在權衡的是合適的合同,因為即使我們理解首個此類反應器可能很昂貴,我們也需要對我們提供給製造商的材料收取可持續的製造費用。這樣他們就能組成三人組了。

  • Well, and this is principally our strategy too. We're going to invest very heavily into the fuel supply so we can own our own fuel and supply it to the fabricators so we don't get stuck, but they will still have to increase their capacity probably to meet the market expectations. And I would say those are principally the main.

    嗯,這基本上也是我們的策略。我們將大力投資燃料供應,以便擁有自己的燃料並供應給製造商,這樣我們就不會陷入困境,但他們可能仍然需要提高產能以滿足市場預期。我認為這些都是主要原因。

  • The main issues, not issues exactly, but longer lead items that need consideration. But beyond those, even the reactor vessel that, the capability exists to do that in North America, it's those longer lead items, the fuel and the graphite, I think, which need more consideration and earlier engagement to de-risk.

    主要問題,或嚴格意義上的問題,是需要考慮的、需要長期關注的事項。但除此之外,即使是反應爐壓力容器(北美有能力做到這一點),我認為,那些耗時更長的零件,如燃料和石墨,需要更多的考慮和更早的參與來降低風險。

  • Jeff Grampp - Analyst

    Jeff Grampp - Analyst

  • Great, I really appreciate that answer, James. You kind of hit on the follow-up that I was hoping to ask, on the fuel side of things, and you guys have been, seemingly increasingly vocal about some acquisition or or strategic opportunities to. To put some capital to work there so I was just hoping to get a little bit of an update on I guess level of maturity or intensity of conversations with different companies in in that endeavor or just any kind of yeah I guess update on what we could see from you guys in in that avenue of the cycle.

    太好了,詹姆斯,非常感謝你的解答。你算是說到了我想問的後續問題,關於燃料方面的問題,而且你們似乎也越來越頻繁地公開談論一些收購或戰略機會。為了投入一些資金,我只是希望能夠了解與不同公司進行對話的成熟度或強度,或任何關於你們在這個週期中能取得什麼進展的最新情況。

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • Thanks. Sure, so I'm going to be a little bit careful because obviously it's not public information at the moment, but I don't think it's any great secret that we've been very concerned about the fuel supply chain and because. We're obviously very focused now as the, as we get on in advancement about mass manufacturing reactor. We want to make sure the fuel supply is in place.

    謝謝。當然,所以我會稍微謹慎一些,因為顯然目前這還不是公開訊息,但我認為我們一直非常關注燃料供應鏈也不是什麼秘密。顯然,我們現在非常關注的是反應爐的大規模製造,因為我們正在推進反應爐的大規模生產。我們要確保燃料供應充足。

  • And part of that over the last few years has involved us looking at fuel supply options, and that involves, obviously, we had a related party transaction called List Technologies that we were behind the creation of, and that was obviously, that is a separate entity that we have a partnership with for enrichment. It's Oldcamico tech. It had very good results in the 90s, so that has reasonable levels of confidence that we'll get that to a place where it can eventually enrich.

    過去幾年,我們一直在研究燃料供應方案,這包括我們參與創建的關聯方交易—List Technologies。顯然,List Technologies 是一個獨立的實體,我們與其建立了合作關係,共同進行濃縮業務。這是 Oldcamico 的技術。它在 90 年代取得了非常好的成果,因此我們有相當大的信心,最終能夠使它變得富有。

  • But the lead time on that is still going to be after when we want to get going with the mass manufactured reactors. So that means that we need to be working with companies like EUR that are enriching now. They can enrich your LEU, which is the fuel that we need for our reactor. But even then, if you look at enrichment and you look at all the buildback of enrichment. Or that actually creates the next bottleneck, which is the uranium hexafluoride.

    但即便如此,大規模生產反應器的啟動時間仍會晚於此。所以這意味著我們需要與像EUR這樣正在創造財富的公司合作。它們可以濃縮低濃縮鈾,這是我們反應器所需的燃料。但即便如此,如果你看看財富積累,看看財富累積的所有重建過程。或者說,這實際上造成了下一個瓶頸,即六氟化鈾。

  • So, we identified this, I think, back as early as 2023, and for a while we were in discussions with countries like Namibia, which are large uranium producers about potentially building facilities in country to take yellow cake and make it into that uranium hexafluoride product for export.

    所以,我認為我們早在 2023 年就發現了這一點,並且有一段時間我們一直在與納米比亞等鈾生產大國討論在該國建設設施的可能性,以便將黃餅加工成六氟化鈾產品進行出口。

  • I don't mind saying that we have found better options than that, and we've made substantial progress with the with the governments, the national governments on the acquisition of some of these facilities. I can't give a lot more details at the moment, but I would expect you will see sometime this year some big announcements in that space as we complete some of those discussions and acquisitions.

    我不介意說,我們已經找到了比這更好的選擇,並且在與各國政府,特別是各國政府的合作下,我們在收購其中一些設施方面取得了實質進展。目前我無法透露更多細節,但我預計今年晚些時候,隨著我們完成一些討論和收購,你們將在該領域看到一些重大公告。

  • Jeff Grampp - Analyst

    Jeff Grampp - Analyst

  • All right, we'll stay tuned. Best of luck. Thank you, guys.

    好的,我們會繼續關注。祝你好運。謝謝大家。

  • Operator

    Operator

  • Sherif Elmaghrabi, BTIG.

    謝里夫·埃爾馬格拉比,BTIG。

  • Sherif Elmaghrabi - Analyst

    Sherif Elmaghrabi - Analyst

  • Hey, thanks for taking my questions. I missed a little bit of your, response on LU versus Haleu fuel, but I thought it was pretty interesting, so a couple more on that. From a regulatory point of view, are we talking about a separate regulatory process at NRC or CNSC to use one versus the other, or is it kind of one approval to run at any enrichment level?

    嘿,謝謝你回答我的問題。我錯過了你關於 LU 與 Haleu 燃料的回复,但我認為它很有趣,所以再補充幾點。從監管角度來看,我們是在討論美國核管理委員會 (NRC) 還是加拿大核安委員會 (CNSC) 制定單獨的監管流程來決定使用哪種濃縮水平,還是只需要一次批准就可以在任何濃縮水平下運行?

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • It's a good question because when we do get the reactor licensed, we'll almost certainly get it licensed so so we can demonstrate that it could operate with Haleu fuel. We're in a nice position to be able to do that, and the reason why is the operating parameters that we use for our reactors are enormous. So for instance, if we're operating at like [600 °C], the melting temperature is 1800.

    這是一個很好的問題,因為當我們獲得反應器許可證時,我們幾乎肯定會獲得許可證,以便證明它可以用Haleu燃料運行。我們有能力做到這一點,原因是我們的反應器運作參數非常龐大。例如,如果我們在 [600 °C] 下運行,熔點就是 1800。

  • Now when you've got that kind of margin. Then the safety case that you submit to the NRC for a higher enriched fuel is fairly straightforward. I don't think a lot of companies are in that kind of advantaged position. So, when they are licensing their reactors, they will do it at Haleu level directly, whereas our safety parameters basically allow us to do it simultaneously. The main challenge, I think with the Halo is that it's not.

    現在你有了這樣的利潤空間。那麼,你向美國核子管理委員會提交的關於使用高濃縮燃料的安全論證就相當簡單明了。我認為很多公司都沒有這種優勢地位。所以,當他們頒發許可證給反應器時,他們會直接在 Haleu 層級進行,而我們的安全參數基本上允許我們同時進行。我認為《光環》面臨的主要挑戰在於它並非如此。

  • That it can't be done. Like it's, we've been enriched much higher up to Haleu levels for decades. It's really the fact that in the US at the moment there's no commercial cap2 site. I think BWXT does have a CAT 1 site, but obviously that's very centered towards military and would make everything very expensive if you've manufactured through there.

    這不可能做到。事實上,幾十年來,我們的富營養化程度一直遠高於海溝族的水平。真正的原因是,目前美國還沒有商業化的Cap2網站。我認為 BWXT 確實有一個 CAT 1 站點,但顯然它非常側重於軍事領域,如果你通過那裡進行生產,所有東西都會非常昂貴。

  • So, it's a question of the ARC will need to upgrade sites to CAT 2. They will need to upgrade fuel facilities to be able to handle Haleu fuel and the proliferation, the increased proliferation concerns that attribute to that fuel. None of those proliferation concerns go away once it's fabricated, but it's still a process the NRC will need to go through for that enrichment of fuel.

    所以,問題在於 ARC 是否需要將網站升級到 CAT 2。他們需要升級燃料設施,以便能夠處理哈雷烏燃料及其擴散,以及由此產生的日益嚴重的擴散擔憂。即使燃料製造完成,擴散的擔憂也不會消失,但美國核子管理委員會仍需要經歷一個過程才能完成燃料濃縮。

  • So, it's an interesting thing. We want to take advantage of Haleu fuel as much as everybody else, but like having that option to license the reactor immediately so it can be deployed with [LEU] and then once the Haleu is available, immediately switch it out without further licensing engagement is going to be a very important part of the strategy here.

    所以,這是一件很有趣的事。我們和其他人一樣,都想利用低濃鈾燃料,但能夠立即獲得反應器許可證以便使用低濃鈾進行部署,然後在低濃鈾可用時,立即進行替換而無需進一步的許可證辦理,這將是該戰略中非常重要的一部分。

  • Sherif Elmaghrabi - Analyst

    Sherif Elmaghrabi - Analyst

  • Yeah, that's interesting. It sounds like it's not as binary as for other. Operators, so just one more on, University of Illinois, you guys signed that MOU kind of lengthening your relationship. It looks like Illinois will lend a hand designing the reactor. Do they retain a commercial stake when you look to commercialize your design down the road?

    是啊,這很有意思。聽起來它不像其他情況那樣非黑即白。各位營運商,還有一件事,伊利諾大學,你們簽署了諒解備忘錄,延長了你們的合作關係。看來伊利諾州將參與反應爐的設計工作。當您將來打算將您的設計商業化時,他們是否仍保留商業權益?

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • No, so they will be the owners and operators of the first of a kind reactor system, and they will, they will supply a huge amount of labor and resources into this project to make sure the first of a kind reactor is built. But beyond that, we own and operate the design of this reactor, and the commercial venture UIUC will be Nanos, exclusively.

    不,所以他們將成為首個此類反應器系統的所有者和運營者,他們將為該項目投入大量勞動力和資源,以確保首個此類反應器的建成。但除此之外,我們擁有並經營該反應爐的設計,而商業合資企業 UIUC 將完全由 Nanos 負責。

  • Now, the University of Illinois, the big benefit to them is obviously a reactor system that provides them clean energy for their campus system and also, it's obviously they have got a big nuclear engineering department that they will benefit from involved in this. So, it's obviously a big draw, if you're training nuclear engineers to say we're building this next generation gen four reactor system, so they get immediate benefits from this first of a kind, but beyond this, once we have a commercial venture, that will be a strictly Nano endeavor.

    現在,伊利諾大學顯然將從中獲得最大的好處是,它將獲得一個反應器系統,為他們的校園系統提供清潔能源;此外,他們還有一個龐大的核工程系,參與其中也將使他們受益匪淺。所以,這顯然很有吸引力,如果你正在培訓核工程師,告訴他們我們正在建造下一代第四代反應器系統,那麼他們就能從這個首創項目中立即受益,但除此之外,一旦我們有了商業項目,那將是一項純粹的納米技術事業。

  • Sherif Elmaghrabi - Analyst

    Sherif Elmaghrabi - Analyst

  • Great, hey, thanks for taking my questions.

    太好了,謝謝你回答我的問題。

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • No problem. Thank you.

    沒問題。謝謝。

  • Operator

    Operator

  • Subash Chandra, StoneX.

    Subash Chandra,StoneX。

  • Subash Chandra - Analyst

    Subash Chandra - Analyst

  • Yeah, hey, James, a couple of, I guess NRC questions. So, first, I, the licensing, so you got on the reactor, to what degree is the balance of plant, in that process, and as you sort of, address these various use cases, does that. Again, go to the NRC, so just sort of confused there on where that distinction is between the reactor and balance the plant?

    嘿,詹姆斯,我有幾個關於美國核管會(NRC)的問題。首先,關於許可證,也就是反應器的許可,在這個過程中,電廠的輔助設備在多大程度上發揮了作用,以及當你處理這些不同的用例時,它是如何運作的。再說一遍,去美國核能管理委員會(NRC)看看,我有點困惑,反應爐和電廠平衡裝置之間的差異到底在哪裡?

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • No, it's actually a very good question because for instance, ironically, most of the Kronos MMR system is not a nuclear system. So, for instance, even though, your reactor vessel is, it needs to be nuclear qualified up to a certain level so it can house the reactor itself, it can still be manufactured.

    不,這其實是個非常好的問題,因為例如,諷刺的是,克洛諾斯MMR系統的大部分並不是核子系統。例如,即使你的反應器容器需要達到一定的核能認證標準才能容納反應器本身,它仍然可以被製造出來。

  • In a facility that the NRC does not need to oversee that facility. So if you're fabricating that reactor vessel, that facility does not need inspection. Now the component does need to meet a certain standard. So there's still, when you even get to those sorts of parts that are instrumentally important in a reactor deployment.

    在一個美國核子管理委員會無需監管的設施中。所以,如果你是反應爐壓力容器的製造者,那麼該設施就不需要接受檢查。現在,該組件確實需要符合一定的標準。所以,即便到了反應器部署中那些至關重要的零件,仍然存在一些問題。

  • There's still that that nuance, I think when the NRC mostly care about safety systems, how safe a reactor is, and so their assessment only becomes relevant when it is a nuclear device. So, okay, the balance of plants, so you could say things like the entire adjacent plant. So you've got the secondary coolant loop that stores power that creates essentially a battery, so you could ramp up and ramp down very quickly. It's a non-nuclear device that is a heat sink device that sits outside the NRC.

    我覺得仍然存在這種細微差別,因為美國核能管理委員會主要關心的是安全系統,也就是反應器的安全性,所以他們的評估只有在涉及核裝置時才具有相關性。好的,植物的平衡,你可以說像整個相鄰植物這樣的東西。這樣一來,你就有了可以儲存能量的輔助冷卻迴路,它本質上就是一個電池,因此你可以非常快速地提升和降低溫度。這是一個非核子裝置,它是一個位於核子管理委員會外部的散熱裝置。

  • The adjacent plant where you have the turbine systems that convert heat to electric, again, that would be roughly the same sort of contraption you would find for a gas operation as you would for a nuclear operation. Again, that sits outside of the NRC.

    相鄰的工廠裡有將熱能轉換為電能的渦輪系統,同樣,它在燃氣發電廠和核電廠中使用的裝置大致相同。再說一遍,這不屬於美國核管會的管轄範圍。

  • Now as you get closer to the reactor, then it becomes a bit more blurry because say for instance the citadel, which is the cavity that the reactor sits in, so you dig that into the ground. Now obviously that can be built by local contractors, that can be concreted, and the steel can be put in.

    現在,當你靠近反應爐時,它就會變得有點模糊,因為比如說堡壘,也就是反應爐所在的空腔,所以你要把它挖到地下。顯然,這可以由當地承包商建造,可以澆築混凝土,然後安裝鋼筋。

  • Now the standard has to be up to scratch, and you need to be able to demonstrate that it has met those requirements. But the construction itself is not as relevant as the operation of the reactor system, because what's likely going to happen here is that I think it's part [52 subpart F]. It allows for the, once the reactor is licensed at the NRC, like Kronos will be in say 2030.

    現在,標準必須達到要求,你需要能夠證明它已經滿足這些要求。但建造本身並不像反應器系統的運作那麼重要,因為這裡很可能發生的事情是,我認為這是部分[52 子部分 F]。一旦反應器獲得美國核管理委員會的許可,例如 Kronos 反應器將在 2030 年獲得許可,就可以進行後續操作。

  • All the subsequent reactors that will inherently be licensed to be deployed, so you wouldn't need much more regulatory engagement and you're going to have a big cost saving as a result of that. Now there's some nuance to that because you still need to be able to supply the NRC with information that they would need at any one time if they wanted to inspect your reactor.

    所有後續反應器都將自動獲得部署許可,因此無需更多監管參與,從而節省大量成本。這其中還有一些細微差別,因為你仍然需要能夠向美國核管會提供他們在任何時候想要檢查你的反應爐時所需的資訊。

  • So, you're still going to have to do the geotechnical drilling, make sure you have all that data, you can demonstrate the ground meets the criteria the NRC allocated. The there might have to be inspections of the cores that are being mass produced. Those might need to be inspected to make sure they're up to grade, but provided you are meeting all of those criteria, you could still deploy dozens of those reactors, across the country without further regulatory engagement. But yeah, the majority of the system could be.

    所以,你仍然需要進行地質鑽探,確保你擁有所有數據,並且能夠證明地質條件符合美國核管會(NRC)所製定的標準。可能需要對大量生產的鋼芯進行檢查。這些反應器可能需要進行檢查以確保其符合標準,但只要滿足所有這些標準,你仍然可以在全國範圍內部署數十個這樣的反應堆,而無需進一步的監管幹預。但是,是的,系統的大部分可能都是如此。

  • What we anticipate doing is a centralized manufacturing facility where we do a lot of things like the reactor protection control mechanism, the helium service systems, the modern salt loops, the instrumentation, the electrical systems, operator training, those kind of aspects, those are still mostly mechanical engineering items, and the majority of the reactor comes under that, and that, a lot of that stuff can be done under, say, ISO standards rather than NQA1, nuclear grade standards, it does break down, but it gets a lot easier after that first reactor is licensed because then you have your template and your standards that you need to meet and provided you meet those, the actual the actual necessity for further regulatory engagement drops off quite dramatically.

    我們計劃建立一個集中式製造工廠,在那裡完成許多工作,例如反應器保護控制機制、氦氣服務系統、現代化的鹽迴路、儀表、電氣系統、操作員培訓等等。這些仍然主要屬於機械工程範疇,反應器的大部分都屬於這個範疇。很多工作都可以按照 ISO 標準而不是 NQA1 核級標準來完成,雖然這方面存在一些問題,但在第一個反應器獲得許可後,情況會變得容易得多,因為那時你就有了模板和需要滿足的標準。只要滿足這些標準,進一步監管的必要性就會大幅下降。

  • Subash Chandra - Analyst

    Subash Chandra - Analyst

  • Thank you. Then I guess, to the AI question, I think initially, AI was about looking through the vast trove of documents and perhaps making it a little bit easier and less repetitive and things like that, but I think lately in the last, few weeks or so they're talking about, bringing in digital twins for simulation of these. Do you see, I mean, we see that, having a real-time effect in other sectors, of course, and.

    謝謝。那麼,關於人工智慧的問題,我認為最初人工智慧是為了瀏覽大量的文檔,並使其更容易、更少重複等等,但我認為最近幾週,他們正在討論引入數位孿生來模擬這些操作。你看,我的意思是,我們看到,這當然會對其他領域產生即時影響。

  • And given how lengthy the licensing process is, do you see some of this, having a very material effect on the licensing process? I sort of, yeah, sorry, go ahead. Thank you.

    鑑於許可流程非常漫長,您認為其中哪些因素會對許可流程產生非常實質的影響?我有點……嗯,抱歉,請繼續。謝謝。

  • James Walker - Chief Executive Officer, Director

    James Walker - Chief Executive Officer, Director

  • No, I was going to say like that is my actual big hope because I've been involved in licensing before and it is an enormously complicated thing. So just to, just, I'm not trying to throw Vogel under the bus, but as for instance, Vogel is being built, being built very competently, but say for instance the regulator suddenly says, well, what about this component. Of this reactor that was installed two years ago, well, that's already buried in concrete.

    不,我本來想說,這正是我最大的希望,因為我以前參與過授權許可的工作,那是一件極其複雜的事情。所以,我並不是想把 Vogel 推下水道,但舉個例子來說,Vogel 的製造過程非常順利,但假設調節器突然說,那麼這個組件呢?至於兩年前安裝的這座反應堆,它現在已經被混凝土掩埋了。

  • Well, how do we know it's safe? Did it meet, where's the checklist with regard, the inspection of this component before it was installed and it was encased in concrete? Well, we don't have that. Well, that means we need to dig it up. That means there's going to be a delay to the reactor. That means there's going to be an additional cost component that's going to.

    我們怎麼知道它是安全的呢?該部件在安裝並被混凝土包裹之前是否經過了檢查?檢查清單在哪裡?我們沒有那個。那我們就得把它挖出來了。這意味著反應爐的建造將會延期。這意味著將會產生額外的成本。

  • That's why Vogel is so expensive because you get these things. Now ultimately that that example there is human error. Either someone missed that component, needed to be qualified, or it got installed without anyone realizing that they had to submit it for qualification or something like that.

    這就是 Vogel 產品價格昂貴的原因,因為你可以獲得這些東西。歸根結底,這個例子中存在人為錯誤。要嘛是有人漏裝了那個零件,要嘛是需要進行資格認證,要嘛是安裝的時候沒人意識到需要提交資格認證之類的。

  • If you have an AI system, my hope here is that It would actually be able to identify very quickly what needs to be qualified, what needs to be identified, and you actually will reduce the human error of it down substantially because it will creep into it if you're thinking just, it's difficult to even put into, to explain how complicated a licensing process can be, but if you think about a warehouse and you were to fill it with A4 sheets of paper.

    如果你有一個人工智慧系統,我希望它能夠非常迅速地識別出哪些內容需要認證,哪些內容需要識別,從而大幅減少人為錯誤,因為如果你仔細想想,許可流程有多麼複雜,這很難解釋,但你可以想像一下一個倉庫,裡面堆滿了A4紙。

  • That contain the licensing documentation, you would fill a warehouse. It would be that much paper, millions and millions of documents. It's a crazy process. Now for a human, that's, it's, even if you are 99.99% perfect, that still means thousands and thousands of errors just because of the size of the undertaking that you're going through.

    如果把所有許可證文件都裝進去,足以裝滿一個倉庫。那將是多麼龐大的紙張數量,數以百萬計的文件。這是一個瘋狂的過程。對人類來說,即使你完美無缺(99.99%),也仍然意味著會犯下成千上萬個錯誤,只是因為你正在經歷的事情規模龐大。

  • So, my hope here is that AI can substantially reduce the risk of things being missed, and there's no reason why a computer that's operating like that, that's very familiar with the process that's been exposed to recent licensing data documentation.

    所以,我希望人工智慧能夠大幅降低遺漏的風險,而且沒有理由認為一台像這樣運行的計算機,一台非常熟悉流程並接觸過最新許可數據文檔的計算機,不會出現這種情況。

  • Couldn't immediately identify what needs to be focused on, what does need to be done at certain stages. I think that could be a big step forward for nuclear to reduce tons of licensing errors in terms of, components get missed, they get buried in concrete like the example I gave.

    無法立即確定需要重點關注什麼,以及在特定階段需要做什麼。我認為這可能是核能發展向前邁出的一大步,可以減少大量的許可證錯誤,例如零件遺漏、零件被埋在混凝土中(就像我舉的例子一樣)。

  • Definitely, that will definitely help us enormously. It would help the whole industry, and I can't see why that won't happen. And that's my big hope for AI. It's not so much, reading through all of our submissions and making sure things. It's what needs to be done and when, what has been missed, what could potentially be missed, and that kind of thing. I think that looks very plausible. And if that is plausible, then that makes our life a lot easier and it'll make reactors a lot cheaper in the long run.

    那肯定會對我們有很大的幫助。這將對整個行業都有好處,我不明白為什麼這不會發生。這就是我對人工智慧的最大期望。其實也沒那麼複雜,就是把我們提交的所有資料都仔細閱讀一遍,確保萬無一失。它包括需要做什麼、何時做、已經遺漏了什麼、可能遺漏什麼等等。我覺得很有道理。如果這是可行的,那麼我們的生活就會輕鬆很多,從長遠來看,反應爐的成本也會大大降低。

  • Subash Chandra - Analyst

    Subash Chandra - Analyst

  • Yeah, fingers crossed here as well. Thank you.

    是啊,我也希望如此。謝謝。

  • Operator

    Operator

  • No problem. I for closing (inaudible).

    沒問題。我關閉(聽不清楚)

  • Jiang Yu - Chairman of the Board of Director, President, Treasurer, Secretary

    Jiang Yu - Chairman of the Board of Director, President, Treasurer, Secretary

  • I want to thank everyone again for joining us on today's call. The interest and enthusiasm of our investors and market participants is important to us, and we're very grateful for your support. We look forward to providing additional updates in the future. Have a great evening.

    我再次感謝大家參加今天的電話會議。投資者和市場參與者的興趣和熱情對我們非常重要,我們非常感謝你們的支持。我們期待在未來提供更多更新資訊。祝你有個美好的夜晚。

  • Operator

    Operator

  • Thank you. (Operator Instructions)

    謝謝。 (操作說明)