Operator
Hello, this is the Chorus Call conference operator. Welcome to the Kinross Gold Corporation third quarter 2009 results conference call and webcast. As a reminder, all participants are in listen-only mode. The conference is being recorded. (Operator Instructions) At this time, I'd like to turn the conference over to Erwyn Naidoo, Vice President of Investor Relations. Please go ahead, Mr. Naidoo.
- IR
Thank you. Good morning, ladies and gentlemen. I'd like to welcome you to the Kinross Gold Corporation conference call to discuss our third quarter 2009 financial results. With us this morning, we have Tye Burt, our President and CEO, Thom Boehlert, our Chief Financial Officer, and Tim Baker, our Chief Operating Officer. Please note that certain statements may contain forward-looking information and actual results could differ materially from the conclusions or projections in that forward-looking information. In addition, we caution you that certain material factors or assumptions may be applied in our conclusions or projections. Additional information about risk factors and assumptions are contained in our news release dated November 2, 2009 and our management discussion analysis for the same period as well as other regulatory filings in Canada and the United States. Now I'll turn the call to Tye Burt, President and CEO.
- CEO
Good morning and thank you for joining us today. I'll make some third quarter comments and give an overview on our growth projects. Both Thom and Tim will review financial results and operations. While revenues were up and we had strong margins in rising cash flows, overall our third quarter results were disappointing. This is primarily due to under performance at Paracatu, where we're seeing a slower than expected ramp up and optimization of the new processing plant. We're implementing solutions to improve operations there and more on that in a minute. For the third quarter, production was 537,440 ounces. Close to our Q2 record of 560,000 ounces despite Paracatu's under performance. And that was at a cost of sales of $464 an ounce on a (inaudible) basis.
On by-product accounting, our cost of sales was $421 an ounce. for 513,492 ounces of gold and 2.7 million ounces of silver. This gave us operating cash flow before changes in working capital of $203 million or $0.29 a share for the quarter. This is significantly higher than 2008 on a year-to-date basis at a total of $645 million up 64%. Adjusted net earnings were $1.7 million. That measure doesn't back out the $58.6 million future tax expense related to foreign exchange gains on US dollars that negatively impacted earnings. Thom will give more detail on that shortly.
So, putting those results into perspective, Q3 2009 operating cash flow was higher than Q3 2008. So flat on a per share basis. Operating cash flow for share before working capital for the nine months, ending September 30, rose by 45% versus that period last year of $0.93. Our cost of sales margin improved on both a three-month basis, of $492 an ounce, nine-month basis, of $487 per ounce when compared to 2008. During the quarter we achieved other milestones. Kupol mine produced one million pounds of gold and 10 million pounds of silver and achieved economic completion in September. This released a $25 million letter of credit, repaid $89 million in third party debt and allowed our Russian operating company CMGC to pay a $100 million dividend to our partnership in Russia.
The Fort Knox heap leach, which was first announced in February 2008, produced its first gold yesterday, and will began contributing in Q4 this year. We continue advancing each of our major products and finally we settled the Aurelian class action warrant litigation we inherited with that acquisition. I'll turn to Paracatu for a minute. We gave an update on that expansion on our press release last week, October 26th. Availability, efficiency, and recovery have all showed improvements there in the quarter. However, they were not at expected levels and resulted in lower Q3 production, with higher costs. Also causing us to adjust our Company, full year production guidance downward by approximately 6% with costs slightly higher. We continue to see some trade-offs at Paracatu while achieving concurrent recovery and through put at the planned levels.
For the month of October, we averaged a through put of 70% in the grinding circuit, and average recovery of 74%, compared to a target gold recovery of 80%. We push through put beyond those levels, but have found that results, (inaudible) from the mill reducing gold recoveries. We're currently testing several alternatives, such as including vocation to increase recovery of the larger grind size and (inaudible) We're also accelerating our evaluation of increasing grind capacity. And Tim will give more detail on that initiative. I do know that the team at Paracatu is extremely committed to working very hard to resolve these (inaudible) concerns. Given this expansion extends the mine life of this 18 million (inaudible) to over 30 years, it's important that we take the time get this plant operating as we hoped. The remainder of this year, we expect Paracatu to produce, on average, 35,000 ounces per month.
As a result of lower production of Paracatu, we revised our 2009 full year guidance last week. And now expect to produce 2.2 million ounces at a cost of sales of $435 to $450 per equivalent ounce. We're currently completing our 2010 budgeting process. In our financial path, our Company, 2010 productions expected to be similar to 2009. We'll give more detail to 2010 production and cost guidance as we usually do in January of next year.
Our underlying assumptions to drive those costs remain unchanged from our January release. Also, unchanged, the 2009 guidance from our operations in the US, Chile and Russia.
At our Fort Knox expansion in Alaska, as I mentioned, we producted our first ounce of gold from the heap leach yesterday. So production has begun in the fourth quarter as planned. Each (inaudible) are currently being loaded onto the new heap leach pad, so far some 2.7 million tons have been stacked and processed solution is now being applied. We're also continuing to have drilling success on and around the property of Fort Knox. We're looking forward to improving mine (inaudible) potential at that mine.
I'll give an update on our portfolio projects now for future growth, beginning with organic opportunities at existing lines. At Maricunga in Chile, the analysis completed as part of the pre-feasibility study has defined an expansion option that involves increasing the capacity of the existing crush plant and construction of a new primary crusher. The target is increase in throughput of approximately 50%, bringing ounces in the end of mine life forward. Now is accelerating this project and a target completion of the full feasibility study in the first half of 2010. With a current reserve base there of 6.5 million ounces. resources of 2.3 million ounces, plus further exploration potential. This expansion could bring forth meaningful volume for the shareholders. Stay tuned for the feasibility of results including construction and permitting timelines for that project.
We're also making good progress at Round Mountain, Nevada with plans to expand the existing pit and heap leach facilities. A draft Environmental Impact Statement has been issued and is expected to that this (inaudible) to be finalized in the first half of 2010. This would allow us to deepen the pit, fill the necessary heap leach pads, evaluate the option of further pushbacks.
We're also proceeding with a feasibility study for Gold Hill, which would be expected to be completed in the second quarter of 2010. To give more context (inaudible) brief comment in the press release, all of these activities are aimed at enabling further six to seven years of mining, beyond the current plan for mining activities which end in 2011 with current permits.
Turning now to our future projects, the next round of large scale growth for the Company, Bruce had mentioned last quarter, we're working on completion of the prefeasibility study for the local marketing department in Chile by year-end. The $3 million, three-month drilling program planned for this year was started in July and is about 80% complete today. That drilling is to facilitate the metallurgical testing necessary to advance the prefeasibility study, and preliminary results on our first goal on matching (inaudible) predicted in our models.
In Ecuador, in Fruta del Norte, we continue with field work at the site and focused on environmental studies, infrastructure and training programs for the workforce. We also continue with engineering and metallurgical studies. We're continuing to work with the Ministry of Non-renewable Natural Resources to contain the final optimization to recommence the infill drilling and (inaudible) drilling campaign at FDM. The Ministry has indicated that regulations to the new Ecuadorian mining laws will be issued early this month which may facilitate the restart of large scale mining activities in the country soon.
At Cerro Casale in Chile, the draft feasibility study was completed in the quarter and is now being reviewed and optimized with our partner and the technical committee that oversaw that work. We expect to release details of the study, including project economics, assumptions and recommendations early in 2010. At the same time, permitted and engineering development work are taking place as we speak and we expect to spend about $50 million in 2010 as our share of the funding to advance this project.
So in summary, our quarterly results were impacted by the issues at Paracatu, which I expect will be largely resolved to initiatives already started there. Our financial results were also impacted by FX and tax adjustment. So overall operating cash flow was strong at $203 million. Remainder of this year will be focused on the optimization of the Paracatu expansion. The continued start up of the Fort Knox heap leach expansion, completion of the feasibility study at Lobo-Marte, advancement of the feasibility study from the Maricunga, evaluation of the Cerro Casale feasibility study, and potentially the restart of the infill drilling at Fruta del Norte. I'll now turn the call to Thom Boehlert and Tim Baker to provide financial and operational results and I'll make a few additional closing comments.
- CFO
Thanks very much Tye. The financial results for the quarter were clearly impacted by the operating results at Paracatu. They were also affected by foreign exchange losses related to net monetary liabilities, future income and mining taxes related to foreign exchange gains on Paracatu's US dollar debt and litigation reserve pick-up. Despite the lower production and increase in cost of sales, our cost of sales margin expanded. Our gross sales for the third quarter were approximately 609,000 gold equivalent ounces at an average price of $556 per ounce, sorry, $956 per ounce This generated revenue of $582.3 million which was 16% higher than the third quarter of 2008. This increase was driven by slight increases in the total ounces sold and the increase in gold price.
Third quarter attributable cost of sales per ounce was $464, an increase over the same period, same quarter last year. Which was largely driven by higher Paracatu costs. Compared to the same quarter last year, our cost of sales margin in the quarter increased to $492 per ounce or at 9%, while the average realized gold price increased by 12%. Third quarter adjusted net earnings were $1.7 million compared to $83.4 million or $0.13 a share in the third quarter of 2008. Both reported earnings and adjusted earnings were negatively impacted by the inclusion of the future income taxes spent of $58.6 million related to Paracatu's US dollar debt. Third quarter cash flow, before changes in working capital increases quarter-over-quarter to $203 million or $0.29 per share from $183.2 million also $0.29 per share last year.
On a year-to-date basis, cash flow before changes in working capital increased by 64%, $645 million. The income tax provision of $89.1 million includes future income taxes spent of $58.6 million on foreign exchange gains on US dollar debt on Paracatu. I just want to take a moment to give a little background on this particular item. So, we view Paracatu as essentially a US dollar business. All of its revenue are in US dollars, and once we implement our annual hedging program, about only a third of our operating costs are in local currency, two thirds in US dollars. We therefore, funded the Paracatu expansion with US dollar allowance. Because introducing foreign currency debt for this US dollar model would have introduced real foreign currency exposure.
However, using foreign currency, using US dollar debt, introduces a tax wrinkle. In that Brazil levees taxes on gains or losses generated by the revaluation of nonreal dominated debt owned by companies. On the US dollar debt, we have exposure to 34% of the changes in exchange rates over time. This is a tax exposure we managed actively on a go-forward basis. Since we began funding the expansion in 2006, the gains and losses have offset one another over time. But there's no real net tax cost, in exchange rate or economic costs of having funded our expansion project using US dollar loans.
The accounting and tax treatment is not quite as straightforward. From an accounting perspective, during the construction, gains or losses are added to the asset base. And therefore we get the benefit or the cost of those gains and losses as we depreciate the assets over the first five years of construction. So effectively the gains and losses are spread over the first five years, sorry, of operation. During the operating period, there is no spreading much the accounting tax. As you record the impact on a mark to market basis in the third quarter. From an economic perspective, we will have, in this case, tax savings over the first five years, as we record higher depreciation from the losses we recorded during construction and we'll have a tax bill on the gains that, we have recorded since we entered operation. Those tax bills will be paid when we repay the loans over the same period. So from a net cash perspective, over the next few years, we are neutral. But we will have, an accounting impact going forward because of the accounting tax treatment (inaudible).
Why did we record this amount all in one quarter? because for the first time when we did our, our tax calculation at the end of the third quarter, we actually showed, as a result of reduced production, a loss at Paracatu for the year and it therefore shifted this amount for the full year into earnings in one particular quarter. Why did we not include it on our adjusted earnings schedule?
Looking back we had, a fairly insignificant benefit from this item in past quarters of this year, about $11 million. Through the end of the second quarter. So we didn't think it would be appropriate, that we hadn't pointed out the past to include this item on the schedule this time. What's the impact going forward? There'll be a mark to market impact in our tax provision, unless we restructure the items going forward. And we will have a tax savings going forward from the higher depreciation and (inaudible) our tax provision. We've looked at a number of different ways to deal with the accounting and tax implications of this funding. We continue to do so, and we'll continue to report the impact of this going forward.
So excluding this tax expense on the foreign exchange gains, our effective tax rate for the quarter would have been 34.3%. We reduced our debt by $95.6 million taking our net debt position to $224.6 million by the end of the quarter. We expect to make $68 million of scheduled debt repayments during the last quarter of 2009. Our cash and short-term investments stood at $533.6 million at the end of the quarter, CapEx for the quarter was $140.5 million and $343.7 million year-to-date. We expect our full year CapEx to come in at approximately $500 million. As already mentioned our full year forecast for cost and production has been relied to reflect the change of our expectations in Brazil. Specifically Paracatu. We now expect to produce 2.2 million ounces this year at a cost of sales of $435 to $450 per ounce.
Our sensitivity to changes in gold and oil prices remain unchanged at $5 per ounce for a $100 movement in the price in gold and $2 per ounce for every $10 per barrel of change of oil price. However, as a result of lower production at Paracatu, sensitivity to foreign exchange has, increased slightly, so a 10% change in foreign currency Company-wide would result in a $7 change in our cost of sales per ounce.
These sensitivities continue to take our hedges into account and as I said before, we generally hedge approximately 50% of our foreign exchange exposure prior to the beginning of each of each operating year and we've made good progress on that year-to-date.
I will now turn the call over to our Chief Operating Officer, Tim Baker for a review of our operations.
- COO
Thanks, Thom. I'll take you through the highlights from our operating assets and then provide an update of our expansion project of Paracatu and Fort Knox. I'll ask you to look at the final page of our press release, which has our usually review of operations and mine by mine summary for each of the key metrics, production grade, cost and depreciation. I'll discuss the high level results on a country by country basis, consistent with how we give operational guidance. We experienced strong performance from our US operations, Fort Knox, Round Mountain, and Kettle River-Buckhorn. Attributable production was 169,490 ounces an increase of 11% was compared Q2 2009. Cost of sales was $480 per ounce in the quarter, down 3% from the previous quarter.
The Buckhorn mine is producing at capacity and is meeting expectations. Heap leaching began at Fort Knox during the quarter and initial production of gold started this week. Application of the process solutions started one month late due to later than anticipated due to weather conditions. It has planned to stop stacking ore during very low temperatures to prevent freezing of the pile. In Chile the Maricunga operations produced 100,915 gold equivalent ounces of cost of sales of $487 per ounce. Production was down by 19% and costs were up by 8%, but this is largely due to a loss of production caused by the temporary work stoppage at La Coipa.
In Brazil our operation of Paracatu and Crixas produced 106,155 ounces, at a cost of sales of $696 per ounce. When compared to Q2, 2009. Production decreased by 2%, and cost per ounce increased by 8%. Let me go into more details on Paracatu. Last week announced that we were reducing our operating expectations for the remainder of the year due to the grinding challenges of the newly constructed oil processing facility plant 2. Getting off on the Paracatu team has expanded a lot of access and energy moving plant 2 forward. The results are that we have a significant improvement in plant availability, which is key to driving overall mill performance. Much better understanding of the grinding recovery relationship of the B2 ore and we have increase grinding capacity by fine tuning the flows screens (inaudible).- control systems. In summary, our philosophy is to improve recoveries to acceptable levels and start pushing the tonnage up. We have backed throughput off through 70% of design mill throughput and for the month of October achieved recoveries of 74% which peaked over the designs of 80%. We're testing new reagents, improved floatation recovery and initial results are encouraging. We are now blending ore to mix high grade material was lower grade softer material to optimize throughput. We are currently completing a scoping analysis throughout additional grinding capacity at sites.
When we built the plant, it was designed and built to accommodate a third bore mill. The decision will be made by the end of the year. So the reduced throughput levels, we're forecasting production of 35,000 ounces per month. This should result in full year 2009 production, 340 to 360,000 ounces. We expect cost per ounce to be high for this calendar year at approximately $700 to $735 per ounce. We will keep you updated on the progress we're making at the site. The Kupol mine in Russia came out a share of third quarter production decreased by 8% for the second quarter 2009 to 160,880 gold equivalent ounces. At a cost of sales of $278 per ounce. Production of Kupol was impacted by manageable stability issues and lower grades. A geotechnical assessment on ground stability based on a year of experience resulted in re-evaluation of the mine plant avoiding future ground control issues. Starting late last year initially with good success. Warmer summer conditions, leading to flowing of frozen rock in the faces, combined with a problematic shears are in the hanging wall required us to redesign the mining methodology. We will continue to use the open stoping method in the main drifts. However, we will be extracted the ore in two phases allowing for greater stability within the stopes.
It is important to note that this will effect only 50% of the stoping phases and ultimately extraction remains unchanged. This plan is being developed at present and it's likely that will result in a slightly reduced production, approximately 30 to 38,000 ounces, our share and slight increases in costs for 2010. We will have further information and details regarding the plan once it is complete with our 2010 guidance in January of next year. We continue to focus considerable efforts on further organic growth, evaluating opportunities to lower costs increase throughput and extend mine life at current operations. We're excited of possibility to declining production at Maricunga and expect to have a feasibility study completed by Q2, 2010. During the quarter, our exploration teams were active on 25 mine sites in green field projects, drilling more than 61,000 meters and for the full year, we expect to spend $65 million on exploration. Drilling success continues at La Coipa. Drilling (inaudible) of La Coipa Norte (inaudible). At Kettle River-Buckhorn, drilling of targets continued and additional drilling is planned to fall on the (inaudible) property. We're also actively exploring at all our other operations. The programs (inaudible) from east and west will start in November. We expect to learn more about the mineralization there.
Overall results to date are encouraging. In Ecuador we have four drilling rigs on site awaiting authorization to start our infill program. With that, I'll now turn the call back to Tye for his concluding remarks.
- CEO
Thanks, Tim. To summarize the results, higher gold prices led to higher revenues and margins in Q3. Operating cash flow was the same from Q3 2008 in the three-month basis. Looking at the last nine months, it's a better picture on a year-over-year change. And from nine months until December 30th, operating cash flow per share was up 46%, and margins per ounce increased 9%. Paracatu, however, we are very disappointed in the noncash futures (inaudible) bottom line results. Looking forward, we're making progress on many fronts. Optimizing and improving the Paracatu expansion by adding grinding capacity as mentioned and potential improvements of the floatation service. Starting up the heap leach at Fort Knox with the first gold in circuit yesterday. And advancing scoping studies, feasibility studies in Maricunga, Lobo-Marte, and Cerro Casale. We look at the large picture, the last few years, Kinross has aggressively transformed itself to growing into the two million ounce producer we are today. Margins and cash flow are up substantially. Having built Kupol, Kettle River-Buckhorn, Paracatu and Fort Knox expansion. (inaudible). We own two of the best projects in the world, found in the last decade. Today we have in total, eight mines we expect to produce 2.2 million ounces at the cost of $435 and $450 at a co-product basis this year. We have a fleet of organic and large new projects in our pipeline advancing through engineering, permitting and construction to bring our next phase of growth. Until expiration we will focus on expanding in our resource basis. In closing, I'd say we'd continue to work hard on optimizing our existing assets and advancing our projects. We will not stop in our pursuit (inaudible). So thanks folks for listening this morning. I'd like to open up the lines for questions.
Operator
Thank you, we'll now begin the question-and-answer session. (Operator Instructions) The first question is from John Bridges of JP Morgan. Please go ahead, sir.
- Analyst
Good morning, everybody. Just wanted, the costs are up, at a lot of the operations which is counter to what some of the others have been achieving in the basis of reduced commodity inputs. Just wondered if there was any sort of overriding issue you've been facing?
- CEO
Overriding issue, I'd say not, John. We are, we think we had specific issues that were dealt with, that we're dealing with in Paracatu. Had a specific couple of issues at Fort Knox and Kupol which affected costs this quarter. If you look at our US operations overall, they were very strong and positive. We don't see there's any particular large scale issue. We did have a couple line up in the quarter. what will state the cost of 2010 will give guidance in January as we usually do. We were pretty specific saying we think current guidance in line with two, with the production results from this year. So no, to be very clear, no overall , overriding issue. Just the flip side, I would say of gross projects, is that they're gross projects. You can't always predict in streamline how they'll are going to perform until you build in years of experience.
- Analyst
Right and as a follow-up, the (inaudible) problems at Fort Knox, I seriously think those are? What do you think you'll get out of there in the fourth quarter?
- CEO
Tim?
- COO
Yes. They certainly have an impact on the short-term mine plan , because we push out and will initially leave behind oar, but we'll recoup that oar with the next push back. So in the longer term, we're not going to lose oar as it looks right now.
- CEO
Bottom line, John. We're thinking of a 5,000 ounce impact in Q4. Not material to the overall programs we're making in Fort Knox facility. This is still a terrific mine. We're not going to lose the ounces in the long-term.
- Analyst
Okay, guys, I'll get out the way. Many thanks and good luck. Thanks.
Operator
The next question is from Victor Flores of HSBC. Go ahead, sir.
- Analyst
Thank you, good morning. Just, I'm doing some back of the envelope numbers on Paracatu. It actually looks like in Q3, your cost per ton number dropped with respect to Q2 which is a positive thing Your cost of sales, went up because you actually sold fewer ounces during Q2. I'm just trying to see if you could unravel for us, what the currency impact might have been that led to that higher cost. If you could just comment overall, on the unit cost trend , that you expect, out of Paracatu. Because at 35,000 ounces a month, likes like that pushes you toward $600 an ounce. But I expect that you would like to do better than that.
- CEO
The second question is based is first on currency impact from Q3 in the (inaudible).
- COO
The currency impact in Brazil and around the company hasn't been that great this year. So, Q2 impact added a couple dollars on Q3. Couple dollars per ounce, but not a big impact.
- CEO
Big picture on the cost, overall costs, we are running the same overall dollar costs against a smaller production ounce base, so of course costs were higher than we hoped. But as we bring that production up, as we get to that average of 35,000 ounces per month and as we start refining and continue refining the recoveries in throughput, obviously we expect that to improve over what it's been this year. So we're looking, if you took that 35,000 ounce per month baseline, and projected that forward around the same cost as we have been delivering in the last few months, I think it's not an overly bad picture. We want to get our budget done and give proper guidance on that in January.
- Analyst
Okay, let me ask a follow-up or let me ask it in a different way. What scope do you see for next year to tweak that current cost structure at Paracatu, lower? Is it just going to come from more ounces? Or is there a means--
- COO
There's a lot of scope to improve the costs and the guys have done a lot of work and continue to work. And some rationalization we can do, we're moving less tons and so there'll be reductions in costs. As Tye said, we'll have a better sense of those for the budget which will be due in January.
- CEO
As an another example, we've got a pretty high component of contractors in on site as you'd typically have in start-up. Of course, those folks will be down (inaudible) quite significantly here. So, that expats moving out, there'll be significant reduction in labor costs, depending on how the reagents go. That will get that to a better place. There's a number of places where we can refine operating costs. Too early to give specifics.
- Analyst
Yes. No that's fine, just trying to get a directional sense. Thank you.
- CEO
Thank you
Operator
The next question is from Brian McCarder, UBS. Please go ahead, Sir.
- Analyst
Good morning. Not to belittle or be-labor the tax issue, but could you going forward go through the cash impacts here? It sounds like it's all known cash. But when I look at your deferred taxes, it doesn't appear it's coming through. So, maybe the easier way would have been if you just confirm guidance for the year, X this ongoing mark to market will be 28% to 32% tax rate. And then give me how much of that would be X this thing would be deferred? I'm just trying to get where the cash component comes out of this.
- CFO
Okay, the effective tax rate for the year , adjusting for this item will be in that range. Probably the high end. So take 32%. That's our forecast. In terms of the cash related to this, there are two pieces to it,. We will either we will make a cash payment on any gain on these loans when we repay the loans. And that's from now until 2016. And we will get a cash tax benefit going the other direction which will offset that amount, give you a timing difference. Because we have losses during construction which increased our tax basis, gives us higher depreciation for the first five years of operation. So, from a cash perspective, over the next five or six years, at the current exchange rate, we'll be neutral.
- Analyst
But in any given quarter, you made code of it at 34%. Does that mean we'll have some quarters, if you have a loss, the cash goes one way. You're actually exchanging cash back and forth continuously?
- CFO
Yes. It depends on the time of repayment of the loans versus depreciation deduction.
- CEO
But with short answer, we'll be marking, basically marking it to market each quarter.
- CFO
Right.
- CEO
On a non cash basis.
- Analyst
Sorry. On a non cash? On a cash basis or non cash basis?
- CFO
What we recorded this quarter is a future income tax expense. Relates to the future repayment of these loans. And we'll continue to do that going forward. So each quarter we will mark these loans to market and in our tax provision, record a future item related to it.
- CEO
Okay, and then clean it up on the repayment schedule basically.
- CFO
Yes, so, for an economic perspective at the current exchange rate, our cash over the next, (inaudible) 2016, net cash in and out, of tax is zero.
- CEO
Right.
- Analyst
Okay.
- CFO
Okay, thanks.
- Analyst
Yes. I may call offline to flush this out a little bit more.
- CFO
That will be great
- Analyst
Thanks very much, bye.
Operator
The next question is from Steven Butler from Canaccord Adams. Please go ahead, Sir.
- Analyst
I'll resist any further questions there. Guys, question for you. Tim, I guess for you on, you needed a bit more elaboration on changing of soaping methods to Kupol. We talked about blasting I think in two phases. No change in open soaping methods. What is then the change in the other method do you, going from open soaping to different method. And what's the impact. Or what is, just please describe it a bit more, just a bit more.
- COO
Okay, what we've been doing up until now is taking the soap out in one pass. And a long pass at that. And, two things happen. One is that, especially in the summer months with the warmer air coming in, we start to throw out the permafrost, which results in some instability. And that combined with sheer zone on the hanging wall side complicates issues. The new plan is to drive the soaps, shorter soaps in 2 rather than 1. So we'll take a narrower cut. The impact is slightly more mining costs. Slightly more ground control, but we produce the same amount of rock and oar at the end of the day. So we don't lose any oar. It just takes a little bit more effort to get that.
- Analyst
Okay, so shorter, not as much strike length on the soaps, is that what you're saying.
- COO
That's right. We'll take a short and then we'll come in ahead of the one and leave some ground behind. Take the next one and finish off the first one. That's idea.
- Analyst
Okay, and Tye you mentioned, I think your if I'm correct, interpreted your comments on guidance for next year, of course we await that January 2010 guidance, but you said broadly in line with 2009? Is that what I heard?
- CEO
In production terms, that's right.
- Analyst
In production terms. Near 2.2ish.
- CEO
Yes.
- Analyst
So, is Kupol expected to be broadly in line next year with this year's levels? Or are we going to see a slight decline in grade of Kupol, as we would next year in 2010?
- CEO
As we have said previously and as was in the mine plan, the Kupol grade will decline as we get deeper in the bid and deeper underground. That's as predicted. So later in 2010, we start getting down to 18, 17 grams per ton, as per gram. So another 20 gram approximately in Q3.They're in gradual decline to their full life of mine. So, that of course means lower production this year at Kupol in 2010.
- Analyst
Okay. Tim, what's your best sense of the, the plan for Paracatu? Either can you get access to used ball mill or you going to get a new ball mill? What are your current thoughts there?
- COO
There are new ball mills available that we're evaluating and there are reusable ball mills. Our preference is obviously new. And we're encouraged by what we see. And we will, as I said, we'll have something by the end of the year for sure.
- Analyst
Any sense of lead time on the new ball mill at size you need?
- CEO
Just to give you a wrap up on that. As Tim says, new and used ball mills, both available. Order of magnitude cost installed, $75 million. Time to find, refine, build foundations, install, probably 12 to 18 months. We're going to finish the scoping study in the next two months or month and a half rather by year-end to determine what the best ball mill, what the best approach is. But future grinding capacity will be up by that t ball mill. We think in order of magnitude that will get us back to our current plan. And that of course the 30 year mine life, there remains the opportunity to go further and increase grinding further (inaudible) later in mine life. I'd say we'll tackle the next round in two phases. Immediate ball mill grinding we need to get to targeted capacity and then further beyond that.
- Analyst
Okay. And I guess I couldn't resist, Thom, last question, for you. Why was the FX adjustment on the Paracatu debt, inter company debt, such a volumously large number in the quarter. I think you briefly mentioned, maybe you can elaborate on why it's such a large number.
- CFO
Yes, I'll do that. The method that we used up until this, this quarter had produced and actually a benefit through the end of the second quarter of $11 million as I mentioned. We got to this quarter and as a result of the change of production in Paracatu and the income tax calculation, with income showing a loss for the year. That methodology was no longer applicable. And so we took the entire mark to market on those loans this quarter. Including, , catch-up, of that $11 million benefit last quarter. So that's why it's so large this quarter. Not expected to continue like that.
- Analyst
Okay, okay, thank you.
- CFO
[Inaudible]
- Analyst
Thank you.
- CEO
Thanks, Steve
Operator
The next question comes from the David Haughton of BMO. Please go ahead, Sir.
- Analyst
Yes, good morning Tye, Thom, and Tim. Just going back to Kupol, just circling back to what Steve was asking questions on, the underground mining rate at Kupol, I have it around about 2,000 tons per day, is that correct? And would that be impacted adversely as a result of the change in methodology?
- COO
Yes the underground mining rates, building up to that. It's not going to, it shouldn't impact it. Don't forget, we've still got the open bid through mid-2011. We've now developed access to the north end. So that's going to complement our ability to mine underground.
- Analyst
When do you expect to get to that 2,000 ton per day rate?
- COO
I'll have to get back to you. I think it's early next year.
- Analyst
Okay, and are you still thinking sometime in the future for an expansion of that underground rate? As the open pit go through depletion, would you look to increase that rate? Or do these changes to the way that you're mining, impact the ultimate level to which you could mine underground?
- COO
We're always looking at possibilities. And one of the possibilities would be to open up an extension to the north which is under evaluation at the moment. The feasibility study had overall rate, mill rate at 2800 tons a day once the open bid comes to an end. So that's work in progress.
- CEO
Yes, bottom line, the oar body will stand. We just haven't finished the technical work yet on taking underground (inaudible) to that full level, David.
- Analyst
All right. Now just, circling back to Paracatu, the 35,000 ounces per month, are you comfortable with that as a sustainable rate through 2010, given the optimization plans that you've got and awaiting, obviously until you decide whether you go through a new mill or what else? Are you comfortable with that?
- CEO
What we know, after now, these last couple of quarters in particular, we can get the throughput out. And we can get the recoveries up. We can't make them happen concurrently. So, that led us to, what kind of baseline can we deliver on a sustainable basis that's conservative and we think achievable. That's where the 35,000 ounces per month comes from. I think that's a good baseline to look into the future. That doesn't include the upside from say reagents or significant blending that is work in progress right now. Nor of course, changing the grind capacity. So all of those things are for the future. The ounces, let me be really clear with this. The ounces are not lost. The tough quarter doesn't make or break a 30 year mine oar. The important thing is we get it right. It'll take us a while to get there. We think this is a sustainable baseline.
- Analyst
If you go ultimately for additional grinding capacity it sounds like that's the way you're thinking by whatever rigid is. 30 mill or additional oar mill, that would have a positive impact toward the tile end of the life as you get into harder and harder oar. Because previously wouldn't include that kind of additional grind in there. So, can you see benefits in the longer run as you are moving into harder material?
- COO
Yes. Obviously. And one of the things with long life mine is that you have a lot of time and opportunity to refine the through put. And there will be benefits.
- Analyst
Ok now back to time. Dragging out that horse so we can flog it again. When we're looking at, what's the quantum of this loan that we're looking at? What's repayment schedule for Paracatu?
- CFO
The total amount is both internal debt, internal debt and external debt. $625 million. It's basically funding of the project. And it will be repaid between now and 2016.
- Analyst
On a regular payment or one big lump sum as the end?
- CFO
It gets repaid overtime depending on the tranche and lender. So, (inaudible) over that period of time.
- Analyst
So, when I'm looking at your balance sheet, I don't see the full amount necessarily, because there's some internal loans as well that will get cancelled out on consolidation, is that right?
- CFO
That's exactly right.
- Analyst
Ok. All right, thank you very much.
- CEO
Thanks.
Operator
The next question is from Barry Cooper, of CIBC. Please go ahead, sir.
- Analyst
Good day everyone. Coming to your development stories in Chile, you talk about Maricunga and how there's a feasibility study going to be done on that with the release next year. How does that feasibility incorporate or does it incorporate anything with Lobo-Marte? And if it doesn't, are you not kind of somewhat putting the cart before the horse? As soon as you get that done, then you'll need to incorporate Lobo-Marte, or are they going to be two separate things that won't necessarily interfere with one another?
- CEO
No, let's be really clear on that. The Maricunga expansion is a stand alone, 50% target uptick in through put and production there. So, that's on the boards from a study perspective right now. This is a known quantity, known oar body, existing, defined ounces of reserve and resource and a proven production throughput (inaudible) facility, (inaudible) et cetera. The Lobo-Marte oar, that we are talking about and looking at the opportunity to truck the high grade oar, there's some 5 or 6 million tons exposed to surface. That'll be trucked to the La Coipa mill, where we thing we'll have a million capacity, depending on what the programs and future ounce profile is (inaudible) profiles at La Coipa. So, that's on a 2012 kind of time frame. That'd be the first stage of Lobo-Marte and different from what we're contemplating for the bigger project at Lobo-Marte which is another two or three stage crush with another large (inaudible). So kind of a mirror image, but the high grade piece, we wouldn't could not plate building a mill at Lobo-Marte. We are contemplating moving high grade. Should we get the permits and if makes economical sense, moving the high grades of the La Coipa mill.
- Analyst
Ok, so treating them as really two separate things. No overlap at all then?
- CEO
Yes, I'd say it's safe to say Maricunga expansions at Maricunga project, Lobo-Marte is a combined high grade at La Coipa and stand-alone.
- Analyst
Then you have almost, I guess, about a year's worth of experience under your belt at Buckhorn and obviously it's one of your better producers now, having reached full production levels there. In fact, I would say it's above full production levels in Q3. What is happening with respect to grade reconciliation? Because obviously that's a key component of that operation because of its high grade nature.
- COO
Yes, grade's coming in pretty well as expected. So no, no surprises there.
- Analyst
Okay, so right now you're about 20% above reserve grade and then we should anticipate that that's going to be coming down then, I guess, as well, correct?
- COO
Yes, That's right. We targeted high grade soaps to get started.
- Analyst
Okay, Tim while I have you there, if we are looking at things at Kupol, what kind of cost per ton should we be thinking about increases for next year? Is it like 10% or thereabouts or do you have a feel for that at this point in time?
- COO
Yes, it's going to be a little bit more than 10% with the reduction in. I mean, the overall costs don't change, total costs don't change significantly. The deviser changes.
- CEO
So order of magnitude, quick pass. $30, $35 an ounce. Maybe $40 an ounce.
- Analyst
Okay, and then I'm assuming there's going to be a corresponding bump up in your sustaining capital or development capital to keep those, get those soaps ready.
- COO
Not a bump up, no. I don't think it will change.
- Analyst
You don't think that will? Why not with, there's no extra sustaining capital associated with that, then?
- CEO
Pretty well, yes, the development continues at the same rate we're doing it.
- Analyst
Right, okay, thanks, that's my questions.
- CEO
Thanks
Operator
Next question is from Mark Menima from Morgan Stanley. Please go ahead, Sir.
- Analyst
Most of my questions have been answered, but just a little more detail on how you see events unfolding in Ecuador. Whether things are tracking such that you can perceive with your drilling plan as you'd like to? Thanks.
- CEO
Yes, and operator, we probably have time for one more question. But to answer the question on FDN, we are proceeding with all our preparatory work, feasibility, technical background work, environmental baseline studies, training of employees, employees staffing, all is proceeding. What we're waiting for at this point, is final go ahead from Ecuadorian government to restart on drilling, as are the other companies that are active in that country. So we have the Ecuadorian delegation here in Ottawa a few weeks ago. They announced that the regulations, that is the legal execution piece that attaches to the new law would be published in early November. We have no reason to believe that's not right. The restart for drilling would happen after that. So we're standing by. We have four rigs poised on site. This is one of the best oar bodies in a generation, so we're anxious to get drilling and proceed to move ounces and move our plans forward there. But bottom line, this is a country which is gingerly exploring its new mining framework. They have put in place new constitution, they have put in place a new mining law, a new mining minister and now new mining regulations. So, it is, keyword there, new. We're working with the government to move forward. We do have water permits for proceeding. We do have our drilling permits proceeding. We're just waiting for the final release from the minister.
- Analyst
That's expected in early November? Do you have any insights as the body language suggesting that it's going to be something amenable to what you would have measured?
- CEO
We think time from our social audit, but the governments are all very positive. We're learning not to give specific forecasts there. We want to leave those decisions to the government as it is their decision. I wouldn't want to forecast. All the signs are positive. And the results of our studies and the government studies on our work have been positive. I don't want to project a specific date.
- Analyst
Thank you.
- CEO
Thank you very much. Operator, one more question.
Operator
The last question is from David Christy of Scotia Capital. Please, go ahead, Sir.
- Analyst
Good morning guys. Just quickly, most of my questions have been answered. This year the DD&A rose quite a bit. We were in the low 200s, per ounce. What do you expect for next year? Will it stay in that sort of range?
- CFO
Yes, the DD&A of course is up because of our new, because of our new operations and the costs associated with those relative to our old operations. So, looking into next year, I don't have the number handy, but just considering that we are not putting a great deal of new operations into the portfolio for next year. Our existing operations and delivering on what we have. I wouldn't expect a big change into next year.
- Analyst
So sort of flattish with next year, okay. And looking at Paracatu, if you make a decision on crusher and some new equipment there to help because recoveries where you want them, how quickly do you think you can get that working?
- CEO
I think we mentioned earlier, David, we don't want to give a precise time. But in the order of magnitude, 12 to 18 months to source, design, build footings, install and start up a new ball mill. Much will depend on how fast we can get it to site. There are mills out there, and we're in hot pursuit at this point.
- Analyst
So 2010, we should sort of keep the 35,000 ounces a month kind of as sort of where you'll be be probably?
- CEO
We think that's a reasonable baseline. Of course, we won't settle for that. We'll be working hard, but I think it's a good starting place. Ok, Just one more question. A follow up on (unaudible) in Maricunga region and you have three projects there where you were talking about expansions or building, can you give me sort of a rank order of which ones you're thinking as top priority? Obviously, expanding existing operations comes first. So, working hard at Maricunga to deliver the 50% throughput project or uptick in throughput. Second is La Coipa where those are very high value ounces that we're finding around and below the current pits. So, That will provide, we hope, mill field. More to say about that at year-end. Next sequence then would be, as we mentioned to Barry, trucking, potentially trucking oar from the Lobo-Marte pits, to La Coipa for the high grade and in sequence after that would be constructing the (inaudible) and processing facilities for the lower grade, full scale, Lobo-Marte pits. And finally Casale at the back end of the time table would follow those in sequence. By the time you get to Casale, it's 2014. And it's a steady beat of projects between now and then.
- Analyst
So you're saying before you get to building service all year, 2014?
- CEO
No, we think we could potentially start construction at Casale as early as 2012, 2013. Which could mean early production, possibly 2014, 2015.
- Analyst
Okay, what's the permitting process in Chile? Year and a half?
- CEO
Depends on whether it's complete environmental impact study or summary of environmental impact study, but for the complete 18, 24 months, for the partial, for updates 12, 18 months.
- Analyst
That's great, thanks, a lot, Tye.
- CEO
Thank you, folks. Listen just a few commends I'd like to make in closing. We think we've executed a tremendous growth search in the last three years and our cash flow and cash flow per share are record levels. We haven't had a tail end of the globe price. So margins are up dramatically and our portfolio is strong and continues to grow. We have a 30 year mine life at Paracatu with 18 million ounces of reserves and working hard to optimize our new facility there. We had a tough quarter, but relative to successes in recent months and we believe we're still on track for growth in the future. So I think we have today a strong management team. 5500 extremely hard working employees and a complete dedication to delivering future production and future growth. So, thank you very much for listening to us today, folks, and we'll look forward to further results in the future. Thanks very much
Operator
Ladies and gentlemen, this concludes today's conference call. You may disconnect your lines. Thank you for participating. Have a pleasant day.