Operator
Good morning, ladies and gentlemen. Thank you for standing by. Welcome to the Red Back Mining third quarter results conference call. At this time, all participants are in a listen-only mode. Following the presentation, we will conduct a question-and-answer session. Instructions will be provided at that time for you to queue up for questions. (OPERATOR INSTRUCTIONS) I would like to remind everyone that this conference call is being recorded on Tuesday, November 4th, 2008, at 9:30 AM Eastern time.
I will now turn the conference over to Mr. Richard P. Clark, President and CEO. Please go ahead, sir.
- President & CEO
Thank you very much, operator. Good morning, ladies and gentlemen. Welcome to the third quarter conference call in respect of the results of Red Back's operations. What I propose to do is, as usual in this presentation, is just a few brief opening comments, and then I'll pass over the discussion to Alessandro Bitelli, our CFO, to go through the numbers that we released yesterday. And following that, I will go back on the call and go through operations in a bit more detail, and also in terms of our corporate plans. And then we will turn it over to a Q&A period, where you have the opportunity to pretty much ask us anything you would like. Also on the call from Red Back's side is Simon Jackson, our VP Corporate Development. So between the three of us, I think we can satisfy all of your inquiries.
To start off, I can tell you that we're -- in the current market reality that we have, we're very pleased with the third quarter results. In terms of a subjective review, we have had some challenging issues that [ran] over and above the general market conditions, and we're working our way through those. Some of those were anticipated, and I'll go through those in more detail. All of those issues will be resolved in 2009 with the completion of the expansion.
In terms of capital and where we're sitting with gold price and budgeting, I'll touch upon that after Alessandro has had an opportunity to review the numbers with you, and at that time I'll give you an update as well on exploration. But as I said, we continue to, I think, outperform our forecast, certainly in terms of production, predominantly from Tasiast, which has turned out to be an exceptional acquisition and project for us, and we see that trend continuing in the fourth quarter and into 2009. With that sort of introduction, I'll pass this off to Alessandro, go through the numbers in some detail, and then I'll be back to explain in more detail on the operation side after that. Thank you.
- CFO
Thank you very much, Richard. The third quarter, when compared to the same period of 2007, once again, clearly indicates the much higher profitability of the results of two operating mines, Tasiast becoming -- going into production at the beginning of this year, as well as the higher gold price we have enjoyed at Chirano throughout the year once the hedge book was bought out November of last year. With respect to the specifics of the performance for the third quarter in comparison with the second and the first quarter of this year, our production is very much on target, and indeed, we expect company-wide to slightly exceed our targets for the year, and we expect to have 255,000 ounces for use by the end of the year. This will come from approximately 120,000 ounces at Chirano and 135,000 ounces from Tasiast. The average gold price realized has dropped as a result in the gold price in the third quarter, and we have seen a continued drop in the gold price in the fourth quarter today, and that has had a direct impact on our revenues, and as a result of the operating profits for the third quarter compared to the first two quarters of the year.
The challenges, Richard alluded to with respect to cash costs were certainly in part anticipated at the end of the second quarter at Chirano with the doubling of the power costs as a result of the decision by the government of Ghana to do so as of July 1st. In addition, we have incurred additional costs with respect to the change in the mining schedule, and with respect to additional crushing that we had to have on board because of the hardness of the ore. We expect these issues to continue for the fourth quarter and to then be a result in the new year. At Tasiast, we had anticipated a decrease in cost in the third quarter, and indeed that has occurred, and we expect that to continue to occur in the fourth quarter. And overall for the year, we are now forecasting cash costs of $450 per ounce.
With respect to capital expenditures, we are very much in the middle of the capital expansions of both Chirano and Tasiast, and our costs in the third quarter were very much an indication of that. We spent approximately $9 million in the third quarter at Chirano, proceeding with the capital expansion, and well over $12 million at Tasiast. At the same time, the underground development continued at Chirano, where we spent over $7 million on that front. We expect to incur costs slightly higher at Chirano and Tasiast for the plant expansion during the fourth quarter, and then completing the majority of those costs in the first quarter of 2009. Capitalized exploration costs for the third quarter were in the neighborhood of $10 million, and we expect to incur between $4 million and $6 million in the fourth quarter. At this point in time, we do not see significant capital cost arising as a result of our dump leach operations or beginning of our dump leach operation, and those are not going to be significant for 2008, and we don't expect them to be significant in 2009 either. Certainly I want to point out our acquisition of 13% interest in the Mineral Deposits Limited for approximately $27 million -- that acquisition was financed by way of a bank loan, and -- Rick Clark will talk to it a little bit more in the next few minutes. Overall again, strong performance, the profitability still very strong and cash flow is still very strong. Richard?
- President & CEO
Thanks, Alessandro. Okay. Expanding on some of the points, first of all, a question that's coming up as the result of the current gold price, is how have we budgeted for these capital expansions. I can tell you that we obviously use the higher gold price. I don't think anyone anticipated that gold at this time in 2008 would be at these levels for any sustained time. Now, I think that people will recognize that from a management perspective, and from a board perspective, we at Red Back have taken a very conservative approach to how we do our budgeting and our forecasting. That is the same, certainly with how we have gone about these capital expansions.
What has impacted that in terms of available funds this year, is unanticipated, we made the decision to go owner mining. The opportunity arose, we took it, and so that was a significant, unexpected capital cost this year that cut into our reserves. At the same time we made the decision, this year, to buy back-up generator gen sets for Chirano, to give us more flexibility terms of our power situation and cost situation. That turned out to be fortuitous, in that we are now in a position with the Canadian government to look to a significant decrease in what they are charging right now for power, because we're in a position with falling diesel prices to be able to turn those gen sets on unless we can negotiate a better hydro deal. So that worked out very well, but those are what we'll call unanticipated costs on our reserve position.
So where -- where we sit at this point in time, is we are close to finalizing a revolving line with our bankers, and we expect to be able to draw down on that by the end of November, and that will carry us through, obviously into the new year in terms of our capital expenditures. We have looked at all sorts of alternatives. I know there are a lot of companies that are shelving capital projects, or slowing down capital projects. We certainly looked at that. But we are very well advanced on ours, looking to commission in first quarter of 2009, and we made the decision we're not going to slow down. We're certainly not going to put them on the shelf. We're going full speed ahead to complete those projects. We are looking at -- if gold stays at this levels into first quarter of next year, we're basically looking at around a $15 million shortfall. So in the grand scheme of things, that's not a substantial or material amount for Red Back.
It's also a very short-term situation as with the completion of our expansions at Chirano and Tasiast, by midyear 2009, we start producing a significant amount of free cash. So we are looking at a very short timeframe here, and we are in advance discussions, again, with our bankers on that issue, and I expect a positive resolution of that, certainly before year end, carrying us into the first quarter. Let me emphasize and make clear, our projects are full-speed ahead, we are aggressively growing the company. We are focused on gold production, and it makes a significant impact on Red Back, because it is effectively going in to 2010 going to double our production profile once we completed these projects.
As I stated, the impact on cash flow is predominantly gold price, and we're now being very conservative on that going forward. We have adjusted gold price in our models, but I can tell you we have not adjusted downwards our costs. We're staying very conservative on that. However, we do expect a significant reduction in costs at both Tasiast and Chirano in terms of fuel, power, and consumables going forward into 2009. But, again, let me emphasize in terms of how we're budgeting our capital, we have not lowered our cost productions. For example, I think we'll still using about $120 a barrel for diesel in our projections.
Okay. In terms of specifically on the expansions, as I have said, both projects are on track for commissioning still in first quarter 2009. All of the major long lead items have been purchased. We're well into it. We're waiting on the delivery of the mill at Tasiast as the only major capital item outstanding. We expect to complete the full crushing facility at Chirano in the first of the new year, and that's going to make a significant difference on Chirano's cost profile. Right now, we have four portable crushers going at Chirano. We needed that many, just for security of through-put. One of the things that's impacted Chirano's production in the last three to four months has been a pit wall failure at the Tano pit, which is one of our highest grade pits. That necessitated a rescheduling of the mine plan to lower-grade material, requiring more through-put which resulted in higher costs and obviously lower production of ounces. Again, that's a one-off event. We're back in the Tano pit now, and we're going to be continuing to clean up that failure as we do a pit wall pushback and optimization of the shell going in to the new year.
So, you know, that's the impact on this quarter. As I said, we'll still feel at it bit in the fourth quarter at Chirano, but that should all be taken care of going in to 2009 and going forward. In terms of -- staying with Chirano for the moment. As I said, the underground is on schedule. It's on budget. We're down about 450 meters right now on the decline, and we expect to be producing the first higher grade ore to the Chirano mill in the first part of December and continuing into 2009. By the middle of 2009, we start to get significantly higher grade from the underground, and that continues to increase in grade profile going in to 2010.
Jumping to Tasiast, as we said at the outset, Tasiast continues to surprise us on the positive side. We have been fortunate in a number of ways. We are driving the Tasiast plant well above name plate. We have been doing that now for many months. It's operating extremely well, and we have also been fortunate to hit some high-grade pods in our mining, and that's one of the reasons we're going to exceed our production targets at Tasiast this year. We expect to continue to see geological surprises like that going forward over the next year or so, as we continue to try to fully understand the geological model at Tasiast and expand it. But so far, I can tell you lots of pleasant surprises at Tasiast. Where we sit there is on an exploration basis, as we told the market, we are looking to come out with a new resource statement reserve in January. Exploration at Tasiast right now is focused on that, and again, we're looking for a significant increase in -- to be able to report in January.
Jumping back very quickly to Chirano, just touching upon exploration, as a result of our cash-flow concerns, we have reduced significantly exploration for the time being at Chirano. Right now we are focused on a new discovery. We are -- and our drilling efforts are pretty much streamlined for that for the next couple of months, and again, hopefully coming in to the new year, we expect to be able to come out with some form of resource statement on that discovery.
As I said when I was talking about the capital projects, we do expect to realize the benefit of reduced costs, commodity prices right across the board going into 2009. Exactly what that impact is going to be, we're not sure yet. Obviously it will be reported on a quarter-by-quarter basis. Not only when you comply that with the efficiencies of the expansions, we certainly expect to see much more favorable cost per ounce numbers, certainly from Chirano and continuing to decrease from Tasiast.
Looking at -- jumping quickly to corporate activity that Alessandro touched upon, and as everyone knows we recently acquired 13% of Mineral Deposits Limited of Australia. Our mergers and acquisitions effort has been focused on West Africa. We have been following Mineral Deposits for couple of years, and their progress. What I can tell you about this acquisition, it was opportune. Given market conditions and what was going particularly in regards to the hedge funds a month or so ago, we recognized the opportunity to buy this interest from Osprey out of New York. We went in there, there was a number of bidders, and we were able to put forward the best deal in the shortest amount of time, and we got that position and we're very happy with it.
Strategically, in the past, we have taken small positions or strategic positions in companies we have been interested in before. It's part of -- I would say, our modus operandi. This is no different. We are not long-term holders, by any stretch of the imagination. We are looking at Mineral Deposits primarily for its Sabodala Project in Senegal, and we're looking to do a deal on that. If that is not possible to the mutual benefit of both companies, then we will be looking to realize on our investment in Mineral Deposits in the near future.
We are focused on production growth corporately, especially in this market. We are very much believers in cash flow going forward, and we are looking at projects that are near-term production, or advance feasibility, or just in production -- we're looking at new projects with exploration upside, growth upside, and I think that you can see that that has worked extremely well for us with both Chirano and Tasiast. Chirano and Tasiast are new mines. Sabodala is another example of a new mine. As metallurgic standards go, these are very simple projects -- the process, certainly the case with Chirano and Tasiast, the only issue is Chirano being crushing, and that will be resolved in the new year. Sabodala is similar, again -- a very good metallurgical and recovery profile, and it fits our -- the type of the type of company that we're trying to target going forward.
So we'll leave that. We are looking at other companies as well. This is not a mutually -- this is not an exclusive review, and we see this market as a real opportunity. We think we are very strong financially going forward to be able to do a deal. As I indicated the working capital cash crunch that we're feeling right at this point in time is small. As I said, we predict somewhere in the range of $15 million to $20 million only. And certainly by midyear next year, we're in a very strong position cashwise to realize deals, whether they are consummated now or in the future. So that's the business plan for the company. That's certainly the current state of affairs of both Tasiast and Chirano.
I would like to leave you with one other aspect of our operations going into 2009, and that's dump leach operation at Tasiast. Where that sits right now, is it's going to -- the first pile will be irrigated in January. We are continuing to load the first pile now, and we are in the process of constructing the liners for the second pad as we speak. The timing for the irrigation of the first pad is the completion of the construction of the second pipeline to our aquifer, and that's well underway and on target, as I said, for January. All of the test work up to this point in time has confirmed our initial numbers. We're looking at approximately 75% recovery from dump leach, very low-grade material. That's going to have a very positive impact on production and unexpected impact on production from Tasiast. We will as obviously at the end of the first quarter, will able to give you much more accurate numbers, as to what we think is going to be happening from the dump leach going forward, 2009 and onward. So that's the end of the presentation from our perspective. I would now like to throw it out to questions and answers, and as I said -- as well as myself, Alessandro is here, and Simon Jackson. Thank you, operator.
Operator
Thank you. Ladies and gentlemen, we will now conduct the question-and-answer session. (OPERATOR INSTRUCTIONS) Your first question comes from Andrew Mikitchook from Thomas Weisel Partners. Please go ahead.
- Analyst
Good morning, gentlemen. I just wanted to touch on a few things. You talked about power costs. How quickly are you -- at your operations and maybe in West Africa in general, are you guys seeing fuel costs come down to the point where you guys can talk about turning on those gen sets?
- President & CEO
That's a good question. I always love the oil business. I mean, I think we can all appreciate that, when oil price was rocketing upwards, you would wake up in the morning and look at your corner gas station and found out it had risen overnight. What's amazing to me is that when oil falls, there is not a corresponding decrease in prices at the pump, and that's no different on a commercial basis. We are seeing some relief on diesel prices in Ghana for the moment in particular, but it is a slow process, and I don't think you are going to see it fully realized probably until the new year.
- Analyst
Okay.
- VP, Corporate Development
This is Simon Jackson, just to add to that and make sure that everybody is on the same page. Both in Ghana and Mauritania, we are buying out fuel supply just on the regular spot market from international oil companies, so there's no special deals or hedges or government intervention in -- of oil products.
- Analyst
Okay. That was going to be the second part of that question. And then just the ramp-up schedules for commissions of these expansions -- in terms of commissioning these expansions, you guys talk about improvements as of mid-'09. Should we be thinking that that's Q2 '09 will show improvements or this is more of a Q3 thing?
- President & CEO
Well, the commissioning is going to take place towards the end of Q1 into Q2. I mean, we expect to be in the, call it commercial production by the end of Q2 with the full benefits being realized at the end of Q4.
- Analyst
Just lastly, because maybe I'm not as familiar with this, can you give me a summary on the CapEx outstanding, say, as of the beginning of Q4 here? On the three individual projects?
- CFO
Certainly. At Chirano the plant expansion, we expect a balance of cost for Q4 of between $8 million to $10 million, and then in 2009 to complete the project it will be an additional $20 million to $23 million. At Tasiast the plant expansion we expect $10 million to $12 million in Q4, and another $10 million to $14 million in 2009. And with respect to the underground development of Akwaaba Deeps at Chirano, we expect to incur approximately $4 million to $5 million in Q4, and then in 2009 it's $14 million to $80 million, and you are likely going to see that type of capital development cost in 2010 to 2011 as well.
- Analyst
Great. Well that -- that runs me out of questions, and I'll let someone else go. Thank you.
- President & CEO
Thank you.
Operator
Your next question comes from Jacques Wortman from JMP Securities. Please go ahead.
- Analyst
A quick question -- can you just let me know, has the CapEx changed materially from where the original guidance would have been? Alessandro, did you say Chirano in 2009 -- what did you say for a CapEx number?
- CFO
Between $20 million to $23 million.
- Analyst
$20 million to $23 million. Okay. Has there been any CapEx creep? These numbers -- there still seems to be a lot outstanding relative to where we originally work.
- CFO
The majority of the work -- we expect it to take place in Q3, Q4, and then Q1 '09, and that is still the case. The overall capital cost expected for these three projects has not changed. It is still sitting at around $155 million as it was first budgeted in late 2007.
- Analyst
Okay.
- CFO
The balance of the cost -- between the three projects has indeed changed somewhat, in that the plant expansion at Chirano in particular have increased slightly, but on the other hand, the underground development which is going to take place over the course of four years has decreased instead. So one balances the other.
- Analyst
Thank you. What size revolver, Rick, are you guys seeking to lock in? How big a facility will this probably end up being?
- President & CEO
The revolver that we're looking at right now that, that we have been negotiating is approximately $30 million.
- Analyst
$30 million, okay. Can you provide a bit more color on the Tano pit wall failure, and the impact on the mine sequencing and how it is going to be dealt with? I guess you said with a normal pushback, but I guess can you just give us a sense of what the cause of that wall failure was?
- President & CEO
It wasn't an unexpected failure, Jacques.
- Analyst
Okay.
- President & CEO
There was nobody injured. We knew it was going to come down. What happened was it ended up being bigger than we thought it was going to be. That has now been stable for a number of months, which is why we haven't been in the pit. We wanted to see if anything more was going to come down, and we had the geologist take a look at it, the tech guys. And we think it's ready to go into again with machinery and start pushing back the walls, but even before that, we have now gone in and started mining down near where the pit wall failure is. So we're getting a lot better grade now going through the mill as of the last couple of weeks.
- Analyst
Okay. My last question, then I'll pass it on to someone else -- how many tons are on the dump leach pad right now, and what's the average grade, and what's the retention time?
- President & CEO
I have given you a guess, the last time I looked at it -- it's probably up to about 200,000 tons right now.
- Analyst
Okay.
- President & CEO
And the cut-off grade, I can tell you is 0.3. It's basically -- the grade is ranging between 0.3 and 1 gram.
- Analyst
Okay. And what is -- what kind of retention is -- are you looking at here for recovering?
- President & CEO
And Jacques, we don't have reserve numbers on that, right.
- Analyst
No, understood. Sorry, there was some beeping there. I don't know if you guys could hear that. But what kind of retention time do you need there?
- President & CEO
Well, we'll see when you get the commercial pad, but certainly the test work is showing 75% in 60 days.
- Analyst
In 60 days. That's what I wanted to know. Okay. Thanks very much.
- President & CEO
Okay.
Operator
Your next question comes from Anita Soni from Credit Suisse, please go ahead.
- Analyst
Good morning, gentlemen. Just a follow-up question on the dump leach, what is the -- how much of the mining -- I guess the mining capacity is going to be used for the dump leach? Basically how many thousand tons per quarter are we going to be expecting to go in the dump leach?
- President & CEO
We don't have those numbers yet, Anita, and part of that is because a lot of the stuff that we're putting on, or all of the stuff that we're putting on the pads right now, is either waste or low-grade stockpile material, so it's not mining specifically for the dump leach.
- Analyst
It's just basically what winds up meeting the cutoff requirement in the quarter?
- President & CEO
That's correct. Until we come out with our new reserve in January, we won't have a mine plan that goes forward with targeting that material over and above low grade stockpile or waste.
- Analyst
As I recall there was about 800,000 ounces of material that is what, around the 0.3 grams or around cutoff grade; is that correct?
- President & CEO
That's approximately correct.
- Analyst
The question about the pit wall failure was already answered. And just in terms of the cash cost in Q4 and going forward, you said they are going to remain high at both -- or remain at those levels at both Tasiast and Chirano. Are you expecting any kind of reduction there at all? It seems if you take the weighted average of what you're forecasting, it seem there is some improvement at both operations.
- President & CEO
Tasiast is going to continue to go down and decline.
- Analyst
Okay.
- President & CEO
Particularly because this quarter we'll have -- most of this quarter we'll have access to full heavy fuel generation, which we haven't had up until now. In other -- if -- on the heavy fuel gen sets, we have only been using one. This quarter we get two. So there's a big cost savings there.
- Analyst
And about how many dollars per ounce?
- President & CEO
I don't have the answer to that off the top of my head.
- CFO
We expect Tasiast to be at $400 or slightly below $400 for the year. So a decrease from the first three quarters.
- Analyst
Okay. At or below. Okay.
- President & CEO
And Chirano --
- CFO
Chirano we expect a margin of decrease possibly, but still high costs as you indicated, and that is why we have conservatively estimated $450 for the company as a whole for the year.
- Analyst
And also the (inaudible) -- The royalty rates at Chirano were a little bit low -- like lower -- half of what your run rate was. Is there -- could you walk me through that idea of where that is coming from?
- CFO
The royalties are calculated at 3%, in Mauritania and in Chirano. In addition in Chirano, there are sometimes royalties in excess of that, but some of the ups and downs are also dictated by the timing of shipments, and the receipt of gold, and the proceeds from gold, and that may give rise to some variations from month-to-month and quarter-to-quarter.
- Analyst
I think that's it for my questions.
- President & CEO
Thanks, Anita.
Operator
Your next question comes from Stuart McDougall from [Dunnings Capital]. Please go ahead.
- Analyst
Hi, guys. Most of my questions have been answered, but I did want to get some color, if you would, just on what through-put levels we might see at Q4 at the two mines? Are we going to see similar through-put to Q3 or is it going to go a little higher back to the Q2 levels?
- CFO
I expect that Chirano to be in the neighborhood of 30,000 ounces, but Tasiast, we are anticipating over 40,000 ounces.
- Analyst
I guess -- no, I was more look about the actual ore through-put, if you could.
- President & CEO
Stuart, what we expect is -- you are going to see the same type of through-put levels at Chirano but higher grade.
- Analyst
Okay.
- President & CEO
And at Tasiast you are going to see through-put levels around the same grading plus 3 grams.
- Analyst
Thank you very much. That's perfect.
Operator
Your next question comes from Don McLean from Paradigm Capital. Please go ahead.
- Analyst
Just a couple of follow-ups -- if you look at the power costs in Ghana, Rick, is there any flexibility in the price they're charging you per kilowatt hour that's driven by the fuel price, or is that a set rate?
- President & CEO
It is basically -- it is a set rate, but it is being affected by exchange rate. So when you are talking about $0.22, which was the original number, that's been affected by the US dollar. So I can't -- I don't have the answer right now exactly what we're paying today. But it's somewhere, probably between $0.15 and $0.20 per kilowatt hour. And what is interesting about this is that as diesel prices go down, obviously as you know all of the gold producers in Ghana, now have generator capacity. And the Ghanaian government was I think very careful where they pegged the number, and that was just below where it was cost effective for us all to turn on our generators. Well, that situation is going to change dramatically over the next six months, so I would -- we expect to see a significant reconduction in hydro costs.
- Analyst
If you look at Chirano in terms of the power cost, plus the diesel costs for the pit, any sense of roughly what proportion of total cash costs that would represent, or just cash costs? Would it be 20% or -- ?
- President & CEO
Alessandro will answer that for you, Don.
- CFO
You are probably looking at 25% to 30% of the total cost. We had put out an estimate of the impact of the increase in the electricity charges in June, and we had anticipated the life of mine that would increase our overall costs by $30 to $40, so that makes it $60 to $80 for power cost on all in business.
- Analyst
Just to be clear 25% to 30% for combined diesel, plus hydro power.
- CFO
Right.
- President & CEO
Yes,
- Analyst
Same kind of number for Tasiast?
- CFO
With the heavy fuel, we are looking at Q4 as a good indication of the extent of the savings on power for Tasiast, because obviously there is a big difference and we expect to see a big difference potentially in the $10 or $15 per ounce, at least in terms of the increase in power costs there. But we don't know yet, because we haven't been able to fully utilize the (inaudible) plant, so we'll have a much better gauge later on this quarter.
- President & CEO
And on the mining fleet, Don, it's a lot -- Tasiast is a lot more cost effective on the mining side, because the distances are very short, and you don't have the hills.
- Analyst
Right. Well, maybe the easiest way you can get back to me and the others, would be just to ask how many liters per year you would expect for the HFO, and then liters for the diesel going forward. Then we can all play around with our models however we feel like, sticky or otherwise, as far as those pricing assumptions. Just a couple of clarifying points. The -- on the Chirano Tano pit failure, there any incremental costs to that over and above what you would have paid for the layback expected originally planned?
- President & CEO
No.
- Analyst
Okay. And then also to -- a little clarification, the company guidance now is $450. In Q2, the Chirano guidance was $450, so -- does that mean Chirano's guidance for the year is more like $470 or $480?
- CFO
Yes, that probably would be a -- I think we have got -- we have a guidance, I think of $475 for Chirano.
- Analyst
Great. Very good. Thank you very much.
- CFO
Okay.
Operator
Your next question comes from Kerry Smith from Haywood Securities. Please go ahead.
- Analyst
Thanks, operator. Alessandro, can I clarify the comment you made to Don? Did you say a $10 to $15 an ounce reduction in cash cost from [refuel] at Tasiast.
- CFO
That what I said (inaudible) point in time, because I do not -- we haven't seen (inaudible) fully operational, and therefore, I am reluctant to stake my reputation on that.
- Analyst
That's fine. I just wanted to make sure I heard the right number. Have you mined enough tonnage at Tasiast to get some idea on the block model reconciliation, how it's correlated to the actual mining grades and tons that you pulled out of the pit?
- President & CEO
It very much depends on the pit.
- Analyst
Sorry, Rick?
- President & CEO
It depends on the pit.
- Analyst
At Tasiast?
- President & CEO
Yes.
- Analyst
Okay. But overall it is roughly tracking with the model? I'm just wondering -- I'm just trying to get a sense for the material that's going to the dump -- is that material that wouldn't have even been considered to be between 0.3 and 1 gram? Or is it tracking roughly with the model?
- President & CEO
I think the low grade is tracking with the model pretty well. And what we're getting into in certain upper benches, there is -- in one pit there was sort of a reconciliation issue negative, another pit reconciliation positive. We're now just getting down into it deep enough, Kerry, that we're getting some real solid numbers about how this is going to project going forward.
- Analyst
You have said you hit some high grade in some of the pits at Tasiast. Is that material that you expected to be there or is that stuff that you hadn't expected?
- President & CEO
We didn't expect this grade, no.
- Analyst
But it wouldn't account for much in the way of ounces, I guess?
- President & CEO
No, it's basically 200,000 to 300,000 tons at about 4 plus grams.
- Analyst
Okay. Just on the dump leach, it's everything from 0.3 to 1 grams going out on to the pad today. How big will that first pad be? Is 200,000 the maximum size or will it be bigger than that?
- President & CEO
I don't know the answer to that, Kerry, off the top of my head. When I was there a couple of weeks ago, I held that 160,000 to 200,000 tons was about -- just about halfway.
- Analyst
Of that pad?
- President & CEO
Of that pad, and they were already lining the other one.
- Analyst
Okay. So what would the average grade be say going to this pad? Is it in the 0.5 or 0.6 range?
- President & CEO
No idea.
- Analyst
You don't know. So I guess you'll find out.
- President & CEO
Basically by the end of this quarter, and early in the next year, we'll be able to give you a lot more information on the dump leach. Logistically it is pretty amazing. The leach pad is right beside the waste pile and right beside the plant.
- Analyst
And Alessandro, can you give me some idea of what the sustaining CapEx would be in '09, like you spent about $2 million in the operations for the nine months. Just wondering if that's the run rate we should use on a go forward basis.
- CFO
We haven't finalized our plans for '09, but I would say that that would be as good of estimate as any.
- Analyst
Okay. Okay. So just use that rate. And can you give me idea on what the unit costs are on the two operations are these days, for mining on a per ton move basis and for milling?
- CFO
Per tons mined, at Tasiast we are, year to date, at approximately $2 per ton.
- Analyst
Okay.
- CFO
And in Chirano, it is -- oops, sorry. I have to find it. It is is $2.25.
- Analyst
Right. Those are per-ton moved, right?
- CFO
Per-ton moved, right. And milled we are looking at roughly just under $12 per ton milled at Tasiast.
- Analyst
Right.
- CFO
And we are looking at probably close to $13 at Chirano.
- Analyst
And what about the site G&A, how much that would be?
- CFO
Site G&A is around $7 at Tasiast per ton milled, and around $3.50 at Chirano.
- Analyst
Okay. And can you give us any guidance as to what those numbers might look like, even the total number, once you get the expansions up and running -- like would they be 10% lower or -- on the processing side, or should we just assume they would be the same?
- CFO
We see a decrease in that, Kerry, but I can't give you a number of how much right now.
- Analyst
. Okay. That's great. Thanks very much.
- CFO
Okay.
Operator
Your next question comes from Trevor Turnbull from Scotia Capital. Please go ahead.
- Analyst
Good morning, Rick. I had a question -- just going back one more time to the electricity rates there in Ghana, I was wondering, certainly with diesel prices dropping, they are potentially going to be under pressure to revisit those prices they set, but I also wonder if you expect any impact once the election is out of the way? Do you think they are more willing to focus on that once they get through that process?
- President & CEO
I think politics in Ghana is no different than anywhere else in a democratic society. The politicians have been pushing every button they possibly can to make themselves sound better in front of their constituents, and hitting up the gold companies is a very popular thing to do in Ghana.
- Analyst
Right.
- President & CEO
Once the new administration is in place, I think you'll see a lot of things settle down.
- Analyst
I haven't been following it as closely as I should. Is there an obvious outcome that would be more beneficial to the mining companies?
- President & CEO
No, I don't think so. I think that Ghana is very moderate in terms of its leading political parties.
- Analyst
Good. The other question I had, and you may have touched on it. It sounds like you have the gold deposits -- is that something that you anticipate being able to do, or something that the company seems willing -- I'm talking about Mineral Deposits, seems willing to let you do?
- President & CEO
All I can tell you at this point in time, and we would very much like to do site due diligence, but we haven't scheduled any yet.
- Analyst
Okay. My last question, is I guess is far out in the future. When you start running underground at Akwaaba on a steady state basis, get your infrastructure up and running, can you give us a sense of what year-to-year development costs we should be thinking about just to keep enough headings and underground workings going -- like I said once it's through the initial ramp-up phase, but steady state?
- CFO
In 2008, is the initial ramp up phase. In '09, '10, and'11, you are probably looking at $16 million to $18 million a year.
- Analyst
And it's reasonable to assume that that would carryforward even beyond 2010 and '11?
- CFO
No, by then it would decrease dramatically to less than $5 million a year and tapering off.
- President & CEO
Trevor, you are the bottom of the cage then, right?
- Analyst
Of course. Right. So you are coming from the bottom, that's right. You have your infrastructure.
- President & CEO
That's right.
- Analyst
Okay. Great. I guess there was one last question, if you don't mind.
- President & CEO
No.
- Analyst
Several months ago, I guess you were looking at some deeper holes that were coming in across the ore body at Akwaaba, but at a fairly significant depth that hadn't been tested before. Any update as to when those might be available?
- President & CEO
The -- basically the holes were a geological success. It showed us that the mineralized system is continuing, but what we didn't intersect directly below the current Akwaaba ore body were these cross-cutting structures which we now know are very important in basically dilating the main structure, the subvertical structure, opening it up and allowing gold depositions. What we think is going on geologically is there's a series of pods, depending upon whether or not these cross-cutting structures are coming in. And we need to do deeper drilling down the structure, but it's cost prohibitive to do it from surface. We have suspended that program until the sublevel cave operation is down to bottom at the 450 meter level. And then we'll start drilling again.
- Analyst
Okay. Sounds good. Thank you, Rick.
- President & CEO
What I can tell you, though -- we did hit the mineralized system below Akwaaba. We did hit the widths. We didn't get these bonanza grades that we have in the [guts of this] ore body, but we certainly got indications that there is a substantive system that is continuing at depth, and we got to chase it down for grade.
Operator
Your next question comes from [Isi Ravel] from Equinox Partners. Please go ahead.
- Analyst
Good morning, guys.
- President & CEO
Good morning.
- Analyst
Question on strip rates. Effective -- what were the strip rate inclusive of the pit wall failure?
- VP, Corporate Development
Well, the pit wall failure hasn't -- it is only just starting to be cleaned up now, so that's is not included in any E-3 strip ratios. I don't have the strip ratio in front of me. Alessandro might have it there.
- CFO
The strip ratio at Chirano for the year was approximately 5.5 to 1.
- Analyst
5.5?
- CFO
5.5 to 1.
- Analyst
So year to date?
- CFO
Yes.
- President & CEO
Higher --
- Analyst
For the third quarter only or no?
- CFO
For the third quarter, we're at higher than that, but lower in the previous quarters.
- Analyst
I have like 2.8 or something in the first half of the year.
- President & CEO
Yeah, that's right.
- CFO
The first half of the year was maybe not quite 2.8, but it was low, but it went as high as 7 in August, 7 to 1, and as I said, hovered around 5.5 to 6 in the third quarter.
- President & CEO
A couple of reasons, one is obviously that we had to chase lower grade, because Tano -- and at the same time we were doing a lot more development -- we went in early and did the Akwaaba pit above the Akwaaba underground.
- Analyst
I see.
- President & CEO
There was a lot of waste under there that was unexpected in the original scheduling.
- VP, Corporate Development
And we didn't have any choice in that [route], because we had to mine out the Akwaaba pit before we get to the caving part of the underground.
- Analyst
So to get for 5.5 for the year, it's almost 10 strip rate for the third quarter?
- President & CEO
No. No.
- CFO
No. Sorry. Let me make sure we have the numbers straight. We had 5.5 to 6 in the third quarter --
- Analyst
Oh, I see.
- CFO
Okay.
- Analyst
And going forward with the cleanup of the pit, what would you expect fourth quarter and next year?
- President & CEO
Well the fourth quarter is going to go down obviously, and next year we'll get back to more normal numbers, which is in the slightly 3 to 1 range.
- Analyst
I see. And the cost per ton numbers you gave. That was also year to date. Can you break that down for the third quarter only?
- CFO
Yeah, the -- at Chirano, the third quarter was $596, the -- at Tasiast it was $403, and in total it was $485 for the company.
- Analyst
Yes, I'm saying cost per ton?
- President & CEO
He's saying entire costs.
- CFO
Oh. Okay. Mining cost per ton mined at Tasiast for the quarter was $1.50. Again, we are starting to see the benefits of owner mining.
- Analyst
It was a big decrease.
- CFO
Yes. And we continue to see that in the fourth quarter. Per ton milled, it is $9.50, but -- as I said that is a big decrease from year to date. Chirano, I have for the quarter $2.25, probably in line with year to date per ton mined, and milled is probably close to $14.
- President & CEO
Okay?
- Analyst
I see. Other thing I wanted to check was, in the capital spending description that you have on page 5, there's two numbers that I couldn't quite reconcile. This is -- there's one in the table that's $68.5 million, and that's the breakdown, and then there's $54.6 million in the tax. How do these things match up?
- CFO
One is in relation to property time and equipment, which the capital projects with the scheduled plant expansion is the key component in the mining fleet packet, and that is the $68.5 million in the table. The $64.6 million addition to mineral properties that is composed mainly of the underground development at Akwaaba Deeps, the (inaudible) in Chirano, and other activities, such as open-pit cutbacks, and [less] to obtain that.
- Analyst
So it would be -- total those to get the total number?
- CFO
The total number, then is, $68 million plus $54 million is --
- Analyst
I see.
Operator
Your next question comes from David Stein from Cormark Securities.
- Analyst
Good morning, guys. I got disconnected earlier, so I missed one thing earlier, and that was when Jacques was asking about the dump leach cycle. Can you just tell me what your thoughts were there, and would we see any production potential in Q1 '09?
- President & CEO
I think you are basically going to see the benefit of the dump leach realized in -- starting in Q2. It is going to -- they will start irrigating in January, David. And then you are looking at 60 to 90 days before we're getting a really solid flow.
- Analyst
Okay. Great. Thanks. And then on the -- on the Chirano exploration, just some further clarification there -- first of all I'm wondering if you can give new details on the new discovery, and whether this is related to the existing 11 pits or outside that, and what you are looking at there? And then second of all, you had quit a bit of drills under pits like [Fbwasi and Akwaaba] et cetera, and -- I understand you are cutting back on the exploration, but did you get enough done to do a resource estimate there? And when would we see that, thanks.
- President & CEO
On Fbwasi, resource estimate is underway, and basically it is going to the mining department for economics, and we should have a report on that January. In terms of the new discovery, I can tell you it is between two pits, and it is near surface. It is a bit of a surprise -- it didn't show up on geo chem. So we're drilling holes right now, and that's certainly part of the exploration at Chirano. What excites us is the width, plus the grade, and we'll just have to see how it all turns out. But in terms of that discovery, we're certainly not -- there's no reduction in exploration on that one. Where we have done our reduction in exploration was there was a lot of exploration going on in around Akwaaba Deeps for mining purposes, and also we're testing a couple of those deep holes, also for the Fbwasi resource definition, that is now completed. So as I said the focus is on this new discovery, but we haven't taken any drills off of that.
- Analyst
Okay. And again, just to clarify, the resource, or updated resource, what -- is it just Fbwasi or will it include a number of pits around that area of the mine?
- President & CEO
It could be both. It depends. I mean, the resource will come out, but what I'm most focused on, David, quite frankly is whether you can mine it.
- Analyst
Okay. Fair enough.
- President & CEO
And that's not a flippant answer. The reason is obviously we've done a lot of development on these pits. What's going on is the new mine schedule and mine plan. We're going to be backfilling some of these pits, so we need to make decisions very quickly as to whether or not we're going to be doing more mining at depth, and how we're going to do that, whether we're extending the pits themselves or going underground from the bottom of them. As we said, the focus at Chirano is to figure out over the next three to four months how we'll develop this central part of the ore body to get after this higher grade at depth. And that's -- the drilling over the last three months apart from Akwaaba Deeps has been pretty concentrated on this one area, and certainly our goal is to from one access be able to go underground and mine a number of these pods from one access.
- Analyst
I think that's it. Thank you.
Operator
Your next question comes in Don MacLean of Paradigm Capital. Please go ahead.
- Analyst
Quick follow-up on the dump leach impact on Tasiast. I know you don't want to actually give an estimated cost per ounce for it. Do you think it will reduce or increase the average for the project as a whole, total cash cost?
- President & CEO
It is probably going to be about the same.
- CFO
[Mine] is probably not going to make a big difference, but certainly -- I suspect it will have a benefit of impact on cash costs. Because as Rick was alluding before, we had just taken the waste and low grade and treated it, but if we very to establish a much more significant reserve in relation to low grade 4, then that would possibly increase the flow or increase the cost slightly.
- President & CEO
Yes. Alessandro is right. I mean, when I answered you, Don, I was talking about sort of the rough and ready mine plan we've put together for this thing going forward. But certainly for the next year or two, it will have a significant impact on cost, but as we go at and increase the fleet and trekking from longer and going after lower grades, our cost profile is going to go up doing that. But certainly how we calculated the numbers, if we don't think long term that's it is going to increase. Tasiast cost will pretty much be in line.
- Analyst
Terrific. Okay. Thanks, guys.
Operator
Your next question comes from Kerry Smith with Haywood Securities. Please go ahead.
- Analyst
Thanks. Rick, I just wanted to follow up on the new discovery -- if you didn't find it with geo chem, how exactly did you find it?
- President & CEO
My favorite technique, Kerry, drill a hole.
- Analyst
Okay. And how many holes do you actually have in that discovery now?
- President & CEO
I couldn't answer that. I think right now they are probably up to six.
- Analyst
Okay.
- VP, Corporate Development
Yes, that's about right.
- Analyst
And perhaps Alessandro could just give me what the strip ratio is for next year for Tasiast as well. He had given 3 to 1 for Chirano. I was just wondering what Tasiast would be roughly?
- CFO
I don't think Tasiast would be very different what has been today, so again, it is going to be between 3 and 3.5.
- Analyst
Okay. One last question on the CapEx, you have got about $60 million to $70 million left in CapEx at -- for the two plant expansions in Q4 and in '09. And you talk in the MD&A about a commit for $23 million. Is that $23 million of the remaining $60 million to $70 million?
- President & CEO
Yes.
- Analyst
Okay. So you have still got another $40 million to $50 million that hasn't been firmly locked in then?
- President & CEO
Right.
- Analyst
Okay. Okay. Great. Thanks.
Operator
Your next question comes from Isi Ravel from Equinox Partners, please go ahead.
- Analyst
All of my questions was asked right now, but other question I have is currently at Chirano you are mining from 3 bits, I think?
- President & CEO
It varies.
- Analyst
Okay.
- President & CEO
From 2 to 3, yeah.
- Analyst
And incrementally which pits would end and which pits would start? I know there is a schedule going forward there. Is there any incremental CapEx that you would need to prestrip or start a new pit at any of the operations, at the Chirano operations going forward?
- President & CEO
I think that -- well, that's a complicated question to answer, mainly because what is going on with a lot of these pits in the new year are going to be pit wall optimizations and pushbacks. So there's going to be that additional capital to do that under the new mine plan. In terms of the mine pits themselves, each of the pits stop and start under the schedule, depending upon where they are in grade, and how far ahead they have to do grade control. What is complicated in a sense is there's a series of grade control drilling, and when they are doing that, they move on to another pit, then they come back. But the actual strip or waste is -- it would be included in -- the pits now would be in operations costs and not a capital cost unless it's the pit wall pushbacks, and that will be a capital cost.
- Analyst
So there will be pitfall for pushbacks next year -- ?
- President & CEO
Yes.
- Analyst
That will be capitalized as opposed to expense?
- President & CEO
Correct.
- Analyst
Any idea of what that would cost?
- CFO
Right now we have over $10 million in CapEx this year, and -- well, not just CapEx, but a large portion of that is CapEx that -- I don't believe -- we haven't finalized the mining schedule. As a result don't have we exact capitalization for '09, but I don't think it is going to be that high.
- Analyst
I see. Just going back to the power issue here, has the aluminum smelter started in Ghana?
- President & CEO
I don't know the answer to that. Simon might know, but I don't.
- VP, Corporate Development
I'm not -- I haven't checked that information out in the last few days. I know that they had talked about turning it back on, whether that's actually happened right now, I'm not sure. You can imagine that they may not with the election as well.
- President & CEO
My guess --
- Analyst
Okay.
- President & CEO
-- if it's not on, they won't turn it on until after the elections.
- Analyst
Right. Okay. Thanks a lot, guys.
- President & CEO
Okay.
Operator
(OPERATOR INSTRUCTIONS). Mr. Clark, there are no further questions at this time. Please continue.
- President & CEO
Okay. Thank you, everybody for listening in, and your questions, and, you know, please feel free to call ether myself or Alessandro or Simon on any points going forward, and at the same time, feel free to call Kevin Ross. Kevin, unfortunately couldn't be on the call this morning, but he is Chief Operating Officer, and is fully cognizant of all of these numbers and in fact terms of the operation side generates them all, so -- and Kevin, I think many of you talk to him, and he is very open and agreeable, and would be very keen on helping you through your questions. So I look forward to reporting on the fourth quarter. As I said we have had some issues in the third quarter, predominantly related to market conditions and in terms of Chirano, some particular aspects there, but we think that that is behind us now going forward. And as I said we'll full speed ahead on our expansions, and yes, we have a little bit of a capital crunch, but we are on top of that, and we expect to tell you how we're dealing with that. But we will not be slowing down these expansions, and we anticipate reaping the full benefit of them by the middle of next year. Thank you very much, and as I said, look forward to talking to you again for the fourth quarter.
Operator
Ladies and gentlemen, this concludes the conference call for today. Thank you for participating. And please disconnect your lines.
- President & CEO
Thank you, operator.