使用警語:中文譯文來源為 AI 翻譯,僅供參考,實際內容請以英文原文為主
Operator
Good morning, ladies and gentlemen, and welcome to the Harmony Gold Mining Company Limited fourth quarter and financial year end 2013 analysts conference. All participants will be in the listen-only mode and there will be an opportunity to ask questions after some opening remarks by Mr. Abbott. (Operator Instructions). Please also note that this conference is being recorded.
I would now like to turn the conference over to Mr. Frank Abbott. Please go ahead, sir.
Frank Abbott - Financial Director
Thank you. Good morning, ladies and gentlemen. I'd like to deal with a number of accounting technical [entries] and if we could start off with the impairment number.
The impairment includes ZAR2.675b for Hidden Valley and a further ZAR58m in South Africa for the Steyn 2 and the (inaudible) operations. The impairment is the result of using significantly lower gold prices and silver prices than we did the year before. And the large amount was at Hidden Valley where we found that the recovery value is lower than our book value.
We also had to reverse a deferred tax asset in PNG of ZAR547m. You can't maintain a deferred tax asset, if your expectations are that you're not going to generate enough future taxable income to utilize these deductions.
With the reduction in the expected prices, we no longer anticipated that we could generate enough taxable income to utilize these losses. These losses do not disappear and if the gold price improves in the future, we can use these losses. In PNG, the tax law contains favorable concessions and we can actually have double deductions for exploration expenditure. And that leads to the large amount of deferred tax assets in PNG.
We started reporting the deferred tax asset long back in the year 2007, before we sold 30% to Newcrest. We cannot add back the deferred tax asset for headline earnings because of the accounting laws. In the case of the impairment, we can add that back to headline earnings. And I would then like to take you through page 29 on the -- our results, the presentation slide, and where we've tried to deal with these accounting entries.
If you look at slide 29, you see that our net loss for the period was ZAR2.3b. If you add back the impairment of ZAR2.7b, and then there were some other items that you fully deduct, which were profit on sale of assets, you get the headline earning as we reported it through the year, ZAR204m.
A number of exceptional items happened during this period. The one was the impact of Kusasalethu of ZAR1.2b, and then the deferred tax asset write-back at Hidden Valley which we unfortunately couldn't add back for headline earnings. And then in the last two quarters we also had a foreign exchange translation loss on our US dollar loan of ZAR350m. So if we add that back to the our headline earnings, as previously reported, we do have a normalized profit of ZAR2.3b, and that compares to the ZAR2.4b in the year before.
Thank you, ladies and gentlemen. I would like to answer any questions.
Operator
Thank you very much, sir. (Operator Instructions).
Our first question comes from Adrian Hammond from BNP Paribas. Please go ahead.
Adrian Hammond - Analyst
Morning, gentlemen. Just a couple of questions if I may. Firstly, the BEE deal, can you just explain the financing around that and whether it's [going to be] financing or not?
As well, could you explain what happened in exploration costs in the last quarter? It seems to have gone up. And if you could tie in your thinking on Wafi-Golpu. It's not exactly clear to me what you're planning there for the next year. It appears you're pulling back there. And what's Newcrest's position on that? Thanks.
Frank Abbott - Financial Director
Thank you, Adrian.
Just on the transaction, what we did is we have the Phoenix operation, we sold all the Phoenix operations into a new company. We sold 30% of the new company's shares. 5% were presale to the community in the area, that's 5%. The other 25% we sold to various BEE companies. The total value of the transaction -- of the value we put on Phoenix was ZAR450m. And we sold that 25% to them at market value. They put in an equity portion and the balance of it, sort of, in the financing which is funded by [Omni], and we are charging them bank interest rates.
Your second question was on the exploration expenditure. I'm handing that over to Graham.
Graham Briggs - CEO
Hi, Adrian. Yes, exploration expenditure in the last year has been fairly substantial. We've had lots of rigs operating on the Golpu assets, and some related infrastructure. Been collecting some very valuable information, especially on the upper mine of Golpu, and obviously this new information has led us to the conclusion of a scalable modular type of mine that we can probably have there.
So it's led to some valuable information. And now the information that we need to do is some drilling, but also some more study work. So in the next 9 to 12 months, it's really going to be fewer rigs on infrastructure. Probably two of the rigs are going to be focused on Golpu and two others on the exploration areas in the immediate Golpu facility. So, yes, the exploration expenditure was a bit higher during the last quarter.
Adrian Hammond - Analyst
Thanks. And just on Newcrest's position regarding the JV?
Graham Briggs - CEO
Well, as you know, as this JV is not managed by one or the other, so between Newcrest and ourselves, we meet regularly. We have committees that operate on these things, whether it be exploration or Hidden Valley, and therefore we reach consensus on the way forward. So everything that we present, we're certainly hopeful that Newcrest will agree with everything we're presenting and vice versa.
Adrian Hammond - Analyst
Thanks very much.
Graham Briggs - CEO
Adrian, sorry, if I may, just before you leave the call, the BEE transaction, also we have intent there of obviously creating a new entity which can exploit the large numbers of tailings dams in that area. So this essentially is a black participation of what's potentially going to be a big tailings organization in the future. Page 26 in the quarterly report tells you a bit more information about that.
Adrian Hammond - Analyst
Thank you.
Operator
Thank you very much. Our next question comes from Andrew Byrne from Absa Capital. Please go ahead.
Andrew Byrne - Analyst
Hi, good morning guys. Just a very straightforward question to be honest.
With regards to the impairments, what gold and silver price did you use?
Frank Abbott - Financial Director
Thank you. On the gold price, we used a short-term price of $1,250 for the first year, and then -- and that's our financial year which is from June to June. And then we used $1,300 an ounce for the year 2014 to 2015. And then after that we used the long-term price of $1,400 an ounce.
The silver price we used was $20.
Andrew Byrne - Analyst
In perpetuity, yes?
Frank Abbott - Financial Director
Yes.
Andrew Byrne - Analyst
Brilliant. Okay, thanks. As I say, very straightforward.
Operator
Thank you very much.
Graham Briggs - CEO
Thank you.
Operator
(Operator Instructions).
Our next question comes from Allan Cooke from JP Morgan. Please go ahead.
Allan Cooke - Analyst
Good morning, Graham; good morning, Frank. Just a request for the presentation just now or unless you want to give the numbers now, because there are so many swings and roundabouts. Could you perhaps give us an underlying earnings number for the quarter and for the year excluding these (inaudible) like the deferred tax reversal and also Evander, because in your disclosure, the [head] includes not just the (inaudible) but also Evander for the two years. So if we looked at underlying earnings level, what would it be like in terms of say, [rand million] for the year and for the quarter, if I could request that.
And then the other question is around all-in costs, the World Gold Council standard. Do you have those numbers for the quarter and for the year? And will you be reporting all-in costs and all-in sustaining costs in the future please, Frank?
Graham Briggs - CEO
Well, I can talk a bit about the all-in cost. I'll let Frank talk about the number that you want.
Allan Cooke - Analyst
Thanks, Graham.
Graham Briggs - CEO
Thank you and --
Frank Abbott - Financial Director
Yes. I mean so the -- on page 29 -- [you've got] the presentation, Allan?
Allan Cooke - Analyst
Okay, I have (multiple speakers).
Frank Abbott - Financial Director
That still includes a profit on Evander.
Allan Cooke - Analyst
Yes.
Frank Abbott - Financial Director
So I'll have to strip it out for you.
Allan Cooke - Analyst
Okay.
Frank Abbott - Financial Director
We'll do that. We'll have that really for you at the --
Allan Cooke - Analyst
If you don't mind, Frank, sorry to be a pain, it's just that that's a better underlying or core earnings number in my opinion.
Frank Abbott - Financial Director
Yes. We can do that for you. Okay.
Allan Cooke - Analyst
Thank you.
Graham Briggs - CEO
Okay. Allan, on the all-in sustaining costs, as you know, we're not members of the World Gold Council, and therefore we don't spend our money on dollars per ounce for them. However, they apparently have guided and given out some information which I've seen of course, and their recommendation to gold companies is that this be introduced January 1, 2014. Some companies are already starting to give indication. Those become a little bit complicated because, for instance, all-in sustaining cost includes corporate costs. Now we can't give all-in sustaining cost per operation like we do; we can for the Company.
So if you were to look and look at our slide 35, we've got what we call a sort of a total cost there. We have been reporting [our costs] for some time. It's cost that includes cash, royalties, maintenance capital, growth capital, local economic development and the like. And we've given numbers per operation there. So if you look at the total number, you'll see our intent for next year is somewhere between 325 and 360. We've given a range there.
The only numbers that really need to be added back to that are corporate costs, I don't know, somewhere around ZAR100m a quarter, and then exploration which is about, for the next year, about ZAR100m a quarter as well. So those are the two costs that aren't in that number.
So we'll obviously spend a bit of more time in the next six months doing it. Our intention is that, starting on our first quarter -- quarter one which is the one we've already started, by the end of the quarter we'll give a good dash at giving similar numbers to what other companies will be doing.
Allan Cooke - Analyst
Thanks very much. Thanks, Graham; thanks, Frank.
Graham Briggs - CEO
Okay.
Operator
Thank you very much. Our next question comes from Chris Nicholson from RMB Morgan Stanley. Please go ahead.
Chris Nicholson - Analyst
Morning guys.
Just in relation to a comment you made in the press release, on capping the total CapEx for next year to ZAR2.1b. Could you give us an indication of how that is split between South Africa and PNG? And I do understand that the majority has been cut back from PNG. Thanks.
Graham Briggs - CEO
Sure. And I'll just [chat] on behalf of Frank. But if you go to the presentation which really disclose our history as well as our forecast in capital, in rand terms it's on slide 38 and on dollar terms slide 39, you can see the breakdown of growth maintenance, ongoing capital which is really development, and then Hidden Valley and Wafi-Golpu. And if you look at those figures, you'll see that actual for 2013 was around about ZAR2.6b and forecast for 2014 is about ZAR2.6b. So it's virtually flat in South Africa on our capital.
Chris Nicholson - Analyst
Okay, thanks guys.
Graham Briggs - CEO
Good. Thank you.
Operator
Thank you very much. We have a follow-up question from Andrew Byrne from Absa Capital. Please go ahead.
Andrew Byrne - Analyst
Hi guys. Just one on the impairment question.
In terms of kind of the order of magnitude, if you kept the $1,250 gold price flat, what would that have done to your impairments both in Hidden Valley but then also would that have generated impairments in South Africa?
Frank Abbott - Financial Director
Thank you. When we look at South Africa, we used a rand gold price of ZAR400,000 per kilogram. Okay? Because, you know, we believe that that's the sort of level we look at South Africa.
Andrew Byrne - Analyst
Yes.
Frank Abbott - Financial Director
And at ZAR400,000 a kilogram, the only impairment that we had at -- was the ZAR58m, that's in South Africa. Of course if we use $1,250, the impairment in Hidden Valley would have been bigger.
If we look at the reports, this is the results -- quarterly report, on page 27, note 10, you see that we do [work out sensitivities]. We [say] a 10% decrease in the gold price used in the models, and it tells us what the change would have been. A 10% lower gold price in the case of Hidden Valley would have led to a further deferred impairment of ZAR1.96b.
Andrew Byrne - Analyst
Okay. But then -- so basically if that -- so that really drags any kind of taking it to $1,250 from 2015 onwards then, is that additional ZAR2b write-off?
Frank Abbott - Financial Director
[So yes], if the gold price stays at $1,250 going forward, then there would be a further impairment in the future at Hidden Valley.
Andrew Byrne - Analyst
Okay. And then just to be clear, on South Africa, you've used equivalents of about (inaudible - multiple speakers).
Frank Abbott - Financial Director
No, sorry. We use ZAR400,000 a kilogram. And in our view exchange rate depends on what exchange rate you want to use.
Andrew Byrne - Analyst
Yes.
Frank Abbott - Financial Director
So you can't just convert that back to a dollar amount.
Andrew Byrne - Analyst
Okay. But you use 400 flat, you haven't escalated that like you've done --
Frank Abbott - Financial Director
We use it in real terms, yes.
Andrew Byrne - Analyst
Okay, perfect. Thanks very much.
Operator
Thank you very much. (Operator Instructions).
Our next question comes from Derryn Maade from HSBC. Please go ahead.
Derryn Maade - Analyst
Good morning, Frank; good morning, Graham. Just a quick one.
Looking at the slide on the CapEx, you're saying no capital expenditure in respect of Wafi-Golpu from FY '16. Have you pushed the project or the start of development out and beyond what we can see on this graph?
Graham Briggs - CEO
Yes. So our thinking is something like this, that we have a -- we have the intent now of building a mine which is going to be scalable and modular, probably much lower risk, starting with the upper ore body. We're going to look at the studies of reducing the footprint. And in reducing that footprint, obviously there's a lot less cost. So if you have footprints in Papua New Guinea, because of the amount of earth works you have to do, obviously there's a large amount of costs.
Now although we've got a lot of work done on the pre-feasibility of last year, once you start doing those significant changes, you're obviously going to have a significant change to capital. On top of that, the capital market has changed a lot in that various companies that do EPCM and engineering companies and so on, have certainly sharpened their pencil a great deal in the last [while]. And so, you know, it's going to be a different capital cost.
What is that cost going to be? Well, we don't know yet. And we've allowed for the study cost and drilling cost in the next two years, this year and into next year. But we don't know what the cost is going to be in the future.
On top of that, what we're also saying is that we will look at external sourcing for funds for Wafi-Golpu. Now that comes about because a lot of our shareholders, you know, have got demands for, you know, sort of free cash and dividends in the short term, and therefore would probably prefer for us to pay dividends than invest a lot of money from our cash-generating South African operations into Wafi-Golpu and maybe Wafi-Golpu should be financing itself in the future.
So with those sort of thoughts, we've put a footnote to that that says that we won't put any capital expenditure in our sort of Harmony profile going forward. That depends a lot on the studies as to what the capital is going to be. And then on top of that, we're going to be looking at external financing.
Derryn Maade - Analyst
Thanks, Graham. Do you have any indication how advanced the rejig of the studies are now and when we're likely to see some sort of an indication as to what the new Wafi-Golpu plan will look like?
Graham Briggs - CEO
Yes. In the last year since August 2012 we have been spending, you know, quite a bit of money on drilling, mainly the upper ore body. The grade has improved as you'll see in the estimates from what we previously had. Metallurgical recoveries have improved. And therefore, you know, the upper ore body is better than we thought. So we now believe that in relooking at the studies instead of going for a large decline, we can probably access ore body by vertical shafts and that will not only shorten the time, but actually shorten the costs and reduce the costs a lot. But shafts have a limitation in that, you know, you probably would only get to a reduced tonnage in the initial mine. But that's not bad because you'll actually start getting cash flow quicker. So a lot of work has been done on it, but we're not there where we can give an estimate of exactly what's happening.
We have given a bit of a -- a sort of a timeline in the presentation -- slide 48, a bit of a guide as to what we're thinking. And you can see on that we're talking about underground infrastructure in the near term. Now part of that is trying to reduce the risk as well, is get underground and have a look at ore body.
Derryn Maade - Analyst
Okay, great. Thanks very much.
Operator
Thank you very much. Our next question comes from Kane Slutzkin from UBS. Please go ahead.
Kane Slutzkin - Analyst
Morning, guys. Morning, guys. Just a quick one for me on Hidden Valley.
Can you just comment on how things are progressing with the installation of the crusher and ramp-up of overland conveyor? And when do you sort of anticipate moving to free cash flow positive position or even a free cash neutral position?
Graham Briggs - CEO
It's certainly going fairly well. There's been a lot of restructuring -- a lot of restructuring in all aspects. The crusher is working well. It's basically gone through most of the commissioning stage. The overland conveyor is working. The mill is working okay. So everything is starting to come together. You know, we are certainly -- have on the plan for this year to be basically at breakeven at $1,400 an ounce. That's after capital and all costs. So that's our plan for this year. Obviously we're hopeful that we can probably try and exceed our plan, but that's the plan for this year.
I don't think we'll see those sort of numbers this quarter, the quarter that we're in, but certainly hopeful that by the end of the quarter we'll be looking closer to those numbers.
Kane Slutzkin - Analyst
Good. Thanks.
Operator
Thank you very much. (Operator Instructions).
It appears that we have no further questions. Do you have any final comments, sir?
Frank Abbott - Financial Director
Thank you, ladies and gentlemen. We will see you later.
Graham Briggs - CEO
Thank you.
Operator
Thank you very much, sir. On behalf of Harmony Gold Mining Company Limited, that concludes this morning's conference. Thank you for joining us and you may now disconnect your lines.