Graham Briggs - CEO
(Audio in progress) pleasure to present to you these results. In front of you, you do have the Safe Harbor statement. Please take note, forward-looking statements. There is a statement there that says we have to be careful and consider those forward-looking statements.
I'm going to talk a little bit on strategy. I'm going to talk about our growth ounces. This has really been a focus for us for many, many months and in many quarters. I'm going to talk about PNG. As usual, it's very exciting. We're going to talk a little bit about operations, the quarterly results and quarterly developments. Hannes Meyer will help you with the financial overview and then we'll conclude.
So our strategy really has been a lot about building new mines and we have one here in this photograph. This is our strategy. We really have been working very hard in upgrading the portfolio. Getting the portfolio into an area where we do have free cash flow, we really can afford to pay dividends and to fund our growth and there's three main prongs to that.
It's really about growth, the quality. This means not only better assets, but better grade assets.
It's also about geographic diversity. And for that our focus really in the last few years has been PNG. In Exploration we've really developed quite a large portfolio of exploration tenements and there's a big focus on that. Some of them are in partnerships. And a lot of our focus in South Africa has to be in productivity and optimizing our asset portfolio, in being able to get the best out of our assets and improve those cash costs.
We've shown you in the last while that we can find deposits. We've found some brilliant deposits. We've been developing projects, both here in South Africa as well as in Papua New Guinea. And we are busy commissioning several mines and building up the production from those mines. So quite a broad-based expertise that we've developed in the Company. And we probably have, going forward, some of the better mines in the portfolio of gold mining companies.
The list here shows that -- the mines by name. And if you look at the South African underground operations, if you look at all those operations up to and including Target, those operations should, when they get up to full production, be 200,000 ounces or more production per annum.
We've got a few Surface operations. The international portfolio is growing, and we now have only one equity holding and that's in Wits Gold.
This is the production in kilograms over the last three years. So from March 2008 to the present quarter, so quarterly results.
You can see what the graph looks like in the total production there, but what we've indicated here are those operations that we've closed down and the amounts of kilograms that it's taken out of the portfolio.
You can also see from the columns of red bars, we're slowly building up, and of course we are building up more rapidly now than we have been in the past. So we should see those red bars grow. And that's really what this graph shows. From the newer assets, you can see more production coming from the newer assets and growing. Hidden Valley at the bottom in red, Doornkop, Phakisa and Kusasalethu.
What is also interesting on this graph is if you look at the cash costs in rand per kilogram. So we all know that the mining industry has been suffering from quite large inflationary pressures over the last few years. But you can see as the production is starting to build up, the cash costs have stayed relatively constant. As we build up more, and remembering that every operation has a fully commissioned operating shaft now, we are developing, but as we're building up stoking crews we'll get more dilution to the total overhead costs of any operation. So we'll see those cash costs come down.
The same graph, basically looking at ounces and in dollars per ounce. Once you look at the dollars per ounce, obviously you have to look at a lot of the exchange rate variances over that period.
This is Golpu. You've seen this plan view before. Those three holes are 100 meter step outs. The indicated dotted line there is the deposit as we knew it in June 2010. And you can see that these bore holes are beyond that. And we haven't declared the resource there yet. You can also see from the grades as indicated here, and you can see that these were the declared grades in the different parts of the porphyry. You can see from the bore hole results that they're quite a lot higher than the declared grades. And therefore the expectation is that once we declare those results, which will be somewhat bigger, in June or declare it in July, but we'll do all the calculations end of June, that this resource will be much bigger than the 500m tonnes which we declared last year.
This is the Wafi transfer structure clearly indicating where Golpu is there. This is a 17 kilometer length of trend. And as you all know by now these deposits occur in clusters and therefore, there is a lot more potential in this trend. Very little exploration has happened in these areas. We've done quite a bit in recent months, but really what needs to be done is quite a bit more drilling.
To get to Golpu we need to do some early works. So we are busy doing a pre-feasibility study. On the left you can see the parameters that we're testing. That should be finished towards the end of the year. And then we'll have the results of our pre-feasibility probably in the beginning of next year. And I'm talking calendar year now. So somewhere near end of December we'll finish that pre-feasibility.
But what we also need to do is get down and have a look at those deposits. So what we have there is a planned decline, starting really in the Watut River area, coming down into the deposit and that will be essential to be able to mine this deposit. So it's an early works that's going to be partially -- that information is going to go through to the pre-feasibility and also the feasibility studies.
Why will Golpu be a mine is the question you must ask? Well high grade gold and copper. So it's one of the best grades gold, copper ore fields around in the world. Very close proximity to some good infrastructure. It's about 70 kilometers from the biggest port city in Papua New Guinea called Lae. I think we've indicated that we have an experienced team both in Harmony and of course in our partners Newcrest. Stable environment in Papua New Guinea.
We've built and mined the Hidden Valley mine in Papua New Guinea in the newest development in Papua New Guinea for some period of time. And we've also shown you that it has got significant upside, both in the Golpu deposit itself and in the whole trend.
Obviously, funding a lot of questions have been around funding, but there are multiple options here of funding.
Excellent photo taken looking over the Hidden Valley pit and looking in the distance at some tailings there. And there's the plant site and you can see the paths in the valley there, so quite a great shot of that area.
But there's more excitement in PNG to come. The blue areas here are in the joint venture, Morobe joint venture, and that we have 50% of. There are 3,200 square kilometers. Outside of the joint venture in red we show 8,000 square kilometers of exploration tenure. We're busy working hard on this one at the moment. And I was there a few weeks ago. It's very exciting. So I'm sure there's more to come out of PNG.
Operational efficiency is something we have to keep looking at in our South African operations. I'll give you some detail here just to give you a flavor of what we're looking at in the future and what we've been, I guess, beavering away at in the last while. And you don't see it in the results yet. So these are development grades in centimeter grams per tonne, which is really the channel width multiplied by the grades. We give you an indicator of the grams per tonne there as well. And then on the right hand side, a graph basically showing you the ore deposits at the reserve grade, four month moving average and the last quarter.
Now in any deposit it would be nice to have the grades of the current development equaling grades of the deposit as we declared it in the reserves. And that's what we need to get to. You can see Phakisa is slightly behind. But as we open up new development areas we also get back into that grade.
This is Doornkop. You can see it's virtually spot-on, which is showing that Doornkop is really developing the ore body as we know it. And it's opening up that ore deposit. And what we need to get is more stoking advance in our faces and build up production. So it's an area where build up in production is very important. But you can see where the grades have moved over the last -- longer periods since September 2008, so moving up in the right direction.
Kusasalethu, sometimes we develop slightly higher grade areas. And you can see that in the four month moving average. In a quarter one doesn't get overly concerned about this, but Kusasalethu is developing its ore body as planned. And really this is a case of building up again production in the faces, face advance and the like.
If we just go into the quarterly developments and what happened during this quarter, I'll start with safety. Unfortunately we did have two fatals during this quarter. It's always tragic when one loses lives in the mining industry. But safety still remains our number one operational focus. And it really does remain that from my level down through the Chief Operating Officers. If you want to ask more about safety both Tom and Alwyn are here.
During the quarter some significant safety milestones and achievements. We had some very good safety results from some of our shafts.
In gold production, you've seen some of these numbers, gold production down slightly quarter on quarter. However, that goes with a very good control of costs. So the teams all managed to keep their costs in line with their production. So if they didn't achieve their target, they managed to save some costs. So you can see that the operating costs in either rand per kilogram or dollars per ounce is virtually flat. Underground grade slightly up. And a capital decrease in expenditure there for the quarter.
The star of the show has to be Tshepong in it achieved good results, both production, despite Christmas breaks and the like, as well as increase in grade. It remains the star of the show as I said.
Doornkop you can see that the increase in square meters there also led to an increase in tonnage. However, not all the tonnage was milled and we ended up with close on 28,000 tonnes of ore on the ground at the end of the quarter. And that's indicated in grey here, just to give you a full graph. So you'll see that in the results it doesn't -- it talks about the tonnage, but you don't see it milled. And obviously there's 94 kilograms from the previous quarter which we need to try and keep milling during this quarter. I guess we can thank probably some of the latest Easter breaks for probably trying to reduce some of that stockpile. But the Easter breaks don't help the production unfortunately.
Okay. So now I've lost the presentation.
Unidentified Company Representative
Sorry about this.
Graham Briggs - CEO
Okay. Let's talk about Hidden Valley. Hidden Valley unfortunately has this overland conveyor which failed during the quarter. And it's a conveyor that transports the ore basically from the Hidden Valley pit to the Hamata plant site about five kilometers distance. And it failed during the quarter.
At Hidden Valley we've done major advances on eliminating all the issues that have been problematic in commissioning. We've got recoveries up. We've got various things up. We've even got the mining in a situation now where we've opened a good ore body and multiple faces. So we've now got a bit more flexibility in the pit.
However, we still need to move that ore pressure. We move it to the far side. So that is the area of getting throughput up and it's really a case of everything is happening around that except the big benefit of moving the ore from the pit to the plant site. And that's where we are battling. So at the moment we are tracking it. It's proving to be a little bit more expensive but -- and while we repair it.
This is a pipe conveyor. It's not a problem as such long term. It's a case of ironing out all the issues around it and being able to maintain it properly. We've got some good engineers working hard on that. And I'm looking forward to the end of this quarter when that's again in operation.
Some Group operating results. I guess if you look at these quarter on quarter you can see that there's -- most things are fairly flat quarter on quarter. Slight changes of up to about 3% changes here. The cash operating costs, as I say, looking flat there despite the slight down in the kilograms, but of course that's reflected in saving in costs.
This is the underground operations. Underground operations you can see increase in recovery grade, there was a slight decrease in tonnage and a slight decrease in gold produced. But the gold produced obviously is slightly up because of the grade improvements.
Surface operating results. The surface tonnage from dumps, there was an increase in that because of the Christmas break. There is a bit of a gap in -- so we fill up the capacity there. A slight decrease in grade. So surface not much to talk about there.
Kalgold had a slightly difficult quarter, but it is producing as it should be at the moment. Recoveries need to improve there. And that will show a little bit of improvement in grade here. But really the tonnage wise, Kalgold is not the biggest proportion here.
Hidden Valley results. I think I've talked a little bit about this. And you can see that we were really trying to get better results out of this. Overland conveyor is the big issue here.
I'd like to hand over to Hannes to talk about the financials.
Hannes Meyer - Finance Director
Thanks Graham. Graham talked about a fairly stable quarter and if we look at the production side, production is down slightly. Gold sales were down 3%, but we have reduced cash operating costs in rand million terms resulting in this flatter unit cost quarter on quarter. So resulting in a cash operating cost for the quarter, or cash operating profit this quarter, roughly the same as last quarter.
Looking at the two big items in our income statement this quarter. We've got impairment on investment in respect of Rand Uranium. You saw the announcement from Gold One where they made an offer which was accepted by shareholders for Rand Uranium. We had to take account of the proceeds we're going to realize from this transaction. Harmony will see $36m from this transaction and therefore, we have to -- fair value that will take into account the value recurring on our assets -- on our balance sheet of these assets in respect to what we're going to realize. And we wrote off that ZAR160m.
Deferred tax credit ZAR309m for the quarter. I've got a slide a little later on talking about that.
Net profit ZAR238m, and that resulting in headline earnings of ZAR390m. The big difference between the net profit and the headline earnings is that we add back the ZAR160m impairment to get to the headline earnings. And resulting in headline earnings of ZAR0.91 per share, 32% improvement quarter on quarter.
If I look at the balance sheet, we saw cash flow from operations at ZAR793m. You can see our capital expenditure there at ZAR667m. We reduced that capital expenditure during the quarter as well to match the gold production to cut our costs to what we can afford.
You see exploration expenditure pretty much in line with the previous quarters.
Corporate and social investment costs pretty much the same story.
And restructuring costs coming down quarter on quarter and this is now the last quarter where we would have incurred those restructuring costs. We are now through with that restructuring process that we embarked on over the last six, seven quarters.
If we look at the net debt, we've still got a debt to equity ratio there of 6%, net debt of ZAR1.1b. Debt to EBITDA of 0.78. We've still got another ZAR300m of debt facility plus some cash of ZAR700m at the end of the quarter.
Just go to the deferred tax. It's a big item on our income statement. A lot of credit must go to two gentlemen in the audience here as well, (inaudible) and James Jackson on our tax team. This goes back to many years ago when Harmony acquired these assets from AngloGold, [raised through] the Freegold asset. It's been a -- we've claimed a capital allowance in terms of this which the receiver disallowed. This relates back to a post 1973 gold mine which allows you -- entitles you to additional claims in terms of unredeemed capital.
We were set down to go to court in terms of this on March 14 but then on March 10 the receiver withdrew from this particular case on this item and they then conceded that we're entitled to claim this allowance.
So at that time the allowance was about ZAR1.1b of capital allowances, so in Freegold in future we've got a bit of tax cover there. Therefore, the result is that we look at our average tax rate which we had last year on Freegold which is about 29%, applied that to this allowance resulting in a ZAR333m tax asset for us in future with the resulting credit in our income statement.
Back to Graham.
Graham Briggs - CEO
Thanks Hannes. Quite an interesting photograph here. It's taken from a tailings there in the Free State. It overlooks in the distance there Masimong 4 shaft. So this is what a tailings zone looks like at the top. A lot of blue sky of course indicating all the blue sky of Harmony.
Just to remind you of the strategy. Really focused. In this strategy slide you've seen before in this presentation. You'll see it again. We remain focused on this strategy of providing long-term value for all our stakeholders in Harmony.
Thank you very much, ladies and gentlemen. Questions. I hope there's a mic -- a roving mic. Ellen will get to you with the mike, hopefully.
Allan Cooke - Analyst
Hi, thanks. It's Allan Cooke from JP Morgan Cazenove. Just three questions briefly, Graham. On the -- or at the Hidden Valley with that overland conveyor, I understand the Newcrest guys are saying it might take as much as six months to repair that. You were talking about the end of this quarter. Could you just indicate what the status is with that conveyor belt and perhaps give us some flavor as to what the production at Hidden Valley will be like over the next few quarters of this year and when you're likely to be in full production at Hidden Valley?
And then from the South African perspective, that underground grade has ticked up a little this quarter. What is your -- you've gone to a great extent, or gone to a lot of trouble to show that you're anticipating higher grade from your projects. What's that underground grade going to do over the remainder of this calendar?
And then maybe Hannes could give us some color on CapEx expectations in South Africa, what you're likely to be spending. CapEx down 20% this quarter. Can we expect that level to increase or decrease over the rest of this year?
And then at Wafi-Golpu, you've talked about funding options. How much are you likely to need to fund there? Will the government take up its 30% stake? And when would you be looking to finance the major investment that you're going to make there in the future?
Graham Briggs - CEO
Let me try and answer them in order. The Hidden Valley pipe conveyor, it's quite a difficult area terrain-wise and Allan you've seen it, so the pit level and the plant level is a 500 meters drop over a length of five kilometers. It would be nice if it was nice and gradual all the way down but it goes around -- it loops around. So it is quite a complex bit of engineering. However, it's one of those bits of engineering that actually needs a little bit of tender loving care and understanding of it and understanding how the dynamics work. It's also been much more sensitive than we thought to the crushing process. So you've got to get the rocks the right size. You can't have oversized rocks and so on.
And of course, when we had this bit of a disaster on it, it really ran away and bunched up in a lot of places. So it's a case of taking it out and replacing it.
The time constraint that you're getting I think from probably different areas is the belt supply because we're not sure how much of this belt is damaged and therefore we need to replace the belt. Certainly part of it. And remember now this is a pipe conveyor so the belt is actually 10 kilometers long. So the guys have done an estimate on what it needs to replace.
The estimate at the moment is that for the rest of this quarter the pipe conveyor will be out of production but starting early next quarter it will be back in production. But that estimate goes with the caveat of this belt isn't that damaged that we need to find a heck of a lot more. I think there's about 1.5 kilometers or two kilometers of spare belt on site. But, as you know, that may not be enough. So I think that's the error margin around that.
Leon, who is in South Africa, is the engineer out there and he's actually quite confident that this thing will work very well once we get it going.
Having said that, production-wise last quarter we also had issues with the belt and it hasn't been operating as full capacity. So I've been doing some trucking. My expectation is that the tonnage is going to be fairly flat quarter on quarter. So the quarter we've just had and in next quarter and in building up the quarter after that.
The next question was on grades. We are expecting improvements in grades but they'll be fairly small improvements quarter on quarter. One of the big areas that has been under-performing grade has been Bambanani. That's been an under-performance.
You'll see from the notes we talk about Phakisa and stopping mining at Nyala Shaft. This is a case of we're now opening enough faces at Phakisa which is higher grade than Nyala, so crews will be moving over. So there'll be slow progress on our grade moving upwards, an upwards trend.
I guess the flavor I wanted to give you in this presentation was look at our development and see that there's better stuff to come in the operations.
I'll leave the capital cost for you a little bit later and let's talk about -- what was your question -- detail on Wafi-Golpu? Government?
Yes. Hannes can talk a little bit about the funding. In every tenement that is given in Papua New Guinea the government has the right to buy up to 30% of the operation and that normally happens when a mining lease is declared. And the mining lease goes when the completion of the feasibility studies happens. So that goes hand in hand, part of that process. So you do the pre-feas. You go to the feas and then you say okay, we're in a mining lease or in a mine-less area and that's where the government either buys or not.
The government didn't do it on Hidden Valley and it really depends a lot on the financial capacity of the government at that time. So I don't know what the capacity will be in we're talking what, three years' time when they have to make that decision.
That 30%, if they do it, is full contribution. In other words, the same costs. 30% of the same costs and they have to pay their 30% going forward. They may not decide to do that, they may decide to take 15% for example. I don't know. So a lot depends on the government.
It's very early days to actually say what they're going to do. There are obviously a lot of other things happening in Papua New Guinea right now, both in hard rock mining as well as in the gas business. There's a lot happening on the gas and it really depends on their financial capacity at that time, how much they're exposed to various things, what their revenue stream looks like and so on. So a little bit difficult to answer that question.
Hannes Meyer - Finance Director
Allan, in terms of CapEx, this quarter we obviously increased in CapEx compared to the last quarter. Then we are busy with our business planning process at the moment. I think what you will see in South Africa is that we've basically completed these big capital projects therefore major capital project expenditure should decrease. We'll still be spending ongoing capital development as we open up ore bodies and the normal maintenance capital. So I think in the longer run you should see the trend of capital decreasing, although this quarter you will see an increase in capital compared to this quarter.
If we look at the funding options on Wafi-Golpu, we've talked about $3b of capital in total, half of which will be for Harmony, so we're talking about $1.5b there. If the Papua New Guinea government comes in they're contributing for their share of capital therefore that takes about $450m out of that funding requirement, so then we would be required to fund just over $1.1b.
Unidentified Audience Member
In discussing -- in referring to the working capital, in his presentation, Mr. Meyer stated and I quote, cut our costs to what we can afford. Let me link that also to the ZAR300m. I can't recall (technical difficulty).
Graham Briggs - CEO
If we look at this quarter, we look at the production and as the production builds up then we can afford to spend more capital. So therefore, we -- we did delay some of the capital and Tom and Alwyn on the operations side and the guys from the operations (inaudible) actually reducing capital numbers to see how can we delay certain CapEx which doesn't impact on our projects and see guys we've got to put the kilograms on the table before we spend that capital.
Unidentified Audience Member
(Inaudible - microphone inaccessible).
Graham Briggs - CEO
It's $36m, correct. So that's about ZAR230m odd.
Unidentified Audience Member
(Inaudible - microphone inaccessible).
Hannes Meyer - Finance Director
We've put debt profile whereby we -- a certain portion of our debt is amortizing so we've got ZAR150m odd payment due in June which we will repay. We've got longer-term debt available in terms of that. So we'll pay our debt as it is due. We've got certain cash flows coming in.
Post the quarter end we've done ZAR100m coming in from [Taurun] transaction. I think the Rand Uranium transaction will probably take a while to close so it will probably take a while before we see that $36m inflow. But I think we're getting to a stage in our operations where we pay for the capital, we don't have to go -- I don't want to utilize all our debt facilities to pay for additional capital. The operations must now produce the kilograms and fund their own capital program plus additional costs that we have.
Unidentified Audience Member
(Inaudible - microphone inaccessible).
Hannes Meyer - Finance Director
The post 1974 gold mining tax or the gold mine with reference to the Income Tax Act is -- the significance of that is if the mine is a post 1973 gold mine, it qualifies for an additional 10%. Every year there's an allowance creeping up. So whatever you haven't used on your allowance, so we've got ZAR1.1b now. So that grows by another ZAR100m this year. So that's what the distinction between post and pre-1973. So pre-1973 you just spend the CapEx. Post 1973 there's a 10% growth every year in unutilized unrelieved CapEx.
Unidentified Audience Member
(Inaudible - microphone inaccessible).
Hannes Meyer - Finance Director
Correct. So we've put on a number there of 300 -- sorry, just now trying the page down the slide here. So we've put a total deferred tax number, I think it's about ZAR309m in the income statement. The ZAR333m credit has been incorporated in. So we just need to go one up for the rands. I think it's about ZAR309m the total net amount. The ZAR333m credit has been incorporated in that amount, but then there's normal ongoing deferred tax effects every quarter ongoing.
Unidentified Audience Member
(Inaudible - microphone inaccessible).
Graham Briggs - CEO
(Inaudible - microphone inaccessible). I think it's a difficult market to predict. There are obviously a lot of uranium plants that have been built in the world. Generally, I think the uranium technology plants -- plant technology has improved quite a lot. All these nuclear power stations they're a lot safer than they were. We've had the issue with Japan. Of course that was a terrible incident, not only the earthquake, also the tidal and so that's put things a little bit down and fluctuating. But it's a fairly small market. And uranium is quite a common metal but I don't know what's going to happen to the price. I think there's going to be more demand. All the enriched nuclear fuels are now gradually depleted is now coming from primary production.
Unidentified Audience Member
(Inaudible - microphone inaccessible).
Graham Briggs - CEO
There is a fairly low grade in the South Reef. It mines a combination of South Reef and Kimberley Reef, about 50/50 at the moment. Very low grade in the Kimberley. So the final product (technical difficulty) of uranium in that ore is very low.
Nobody wants to ask any questions after that. Sorry.
Unidentified Audience Member
(Inaudible - microphone inaccessible).
Graham Briggs - CEO
Yes, Martin, in pursuing these issues there's always some costs, whether it's our own gentlemen that are focused on pursuing these things or legal opinion. But up to that stage you at your own risk. But I think as we all know the costs are fairly insignificant compared to going to court. That's when the costs really start racking up. They're fairly small.
Okay. I don't know if there's a roving mic or anything like that. I think you'll just have to shout.
Unidentified Audience Member
(Inaudible - microphone inaccessible).
Graham Briggs - CEO
Yes, we are gold bulls, there's no doubt about that. So we think the gold price is going to go up both in terms of dollars and in terms of rand. However the markets are very sensitive to various things that are happening around the world and we've seen in the last few days -- we didn't know Bin Laden could destroy so much money in the resources industry in what three days. I think he must have destroyed 6% of most market caps in the last three days.
Now -- so it's unpredictable but there are people around that think that the gold price is going to scream up, 5,000 is not an unexpected figure. And you see that from some of the deals that have been made in the industry. So there's good indication that people have got a longer-term view of the gold-mining business and they want to put their hands and feet on gold resources even in the ground where there are no fixed feasibility studies even. So you do see that. So I think it's very optimistic. But if you want a number from me, well I guess my number of 1,500 for this last year has been surpassed now. So if you wanted a prediction from us going forward it's certainly closer to 1,800 in the next year. Our next financial year, so sort of -- yes.
Unidentified Audience Member
(Inaudible - microphone inaccessible).
Graham Briggs - CEO
Yes, copper price -- copper has done very well and you've seen a lot of gold miners get involved in the copper business. The recent transaction that Barrick did was certainly copper only.
Yes, I think it's got a good future because a lot of the things that we use as we industialize, as people become more affluent, they use more copper. One of the good measures of affluence is the number of kilograms of copper you use per year, whether it's in your cellphone, in your fridge or your car. But it certainly has done well.
So long-term copper prices are still predicted somewhere around 250. The copper price remains above [4]. I'm not a guru on pricing and these sorts of things so please don't use them in your financial models.
Are there any more questions? If there are no more questions I just want to thank everyone for coming. Thanks especially to Mr. (Inaudible), our Non-executive Director sitting at the back there and to the various Harmony people. Please feel free to tackle them afterwards for further questions. Thank you very much.