使用警語:中文譯文來源為 AI 翻譯,僅供參考,實際內容請以英文原文為主
Graham Briggs - CEO
Good morning ladies and gentlemen. It gives me great pleasure to give you the results for the quarter ended June, and also the year ending June 2010. First let me welcome, there's a couple of directors here. Andre Wilkens is here and Fikile is here, Fikile De Buck. At the Board meeting on Friday Fikile de Buck was nominated as the Lead Director for Harmony. Well done Fikile and we wish you well. So independent non-executive director is Lead Director for Harmony. And to any shareholders here, of which I'm hoping there's quite a few, thank you very much for being here.
The notice, which is important thing, the Safe Harbor Statement, and then I'm going to take you through these topics. A little bit on the strategy, a look at the operations. Hannes will do the financial overview, we'll touch a little bit on exploration and I'll conclude.
As far as the strategy goes, this is a familiar picture. You've seen it before. It talks about four main thrusts. We talk about growth in production ounces. That hasn't happened during the last year. We're basically static, 2% down for the year. However, that's better than the South African industry which I believe is something like 5.5% down. We talk about growth through acquisition and when we talk about acquisition we're talking exploration as well as possible operations. We have, as you know, acquired quite a large tenement in Papua New Guinea, several tenements where we'll continue exploring.
Increasing operational efficiency, these really are focused on our new projects, the capital that we've spent predominantly and the build up in production from those capital projects. Optimizing the asset portfolio, that is multi-faceted but that also has involved quite a lot on the closure of operations. And you're well aware that we have closed several operations in the last eight months or so.
For 2010 really safety we've had great success in a lot of our safety factors. Unfortunately our fatalities, still a lot of work to be done there, and our strive to get to zero fatals is obviously top of our list. We've closed high-cost and loss-making shafts. Reserve levels, that's quite an interesting fact that despite all the closures our reserve levels are static at about 48m ounces. Ore resources down about 9% and that 9% obviously relates a lot to the shaft closures. Healthy margin is what we're all about. We intend to produce cash and fund our own growth, pay dividends and you will see at the bottom of the list there is a dividend announcement there. We are going to pay a dividend of ZAR0.50.
So the majority of our capital is spent on our operations, we've still got a bit more to go and the build up over the next two and a half years or so is going to be quite critical to us. Hannes will talk about debt levels.
Really talking a little bit more about the actions, what we've done, progress to date and where we're aiming at. Commissioning of projects obviously is key in this and in Tshepong we are actually producing from the decline, so that's going well. Not at full production yet but it is producing. Kusasalethu is well on the way and you can see increases in production there, as well as from Phakisa and Doomkop. So those are all on the right trajectory. Getting maximum number of ounces out is what it's all about and our aim on productivity, they have 120 ounces per grams per man is obviously key, and that's from the underground operations.
On growth, exploration in Papua New Guinea is very important and that Wafi/Golpu is obviously, we intend it to be one of our next mines and its going to be going through concept studies. I will take you through some of the concept studies and proposals that we are looking at there. And that's somewhere around 2016.
Acquisition, we've been looking around for acquisitions. Obviously in the good gold price environment they are expensive. It's not going to be something we do at top dollar and it's not going to be something we do unless we can add value to it. So at the moment acquisitions really has remained with exploration tenements.
This is our ounces profile. On August 25 we will be having an Investor Day and at that Investor Day we will be talking about our different operations. And this is really the build up of those, so there's quite a lot of detail here. I'll leave you to look at that yourselves. But you can see that there's a nice profile in growth, in ounces as well as grade, and this is underground grade.
Cash costs and total costs, the red is the cash cost portion. The gray color is the maintenance capital and then there's growth capital on top of that. You will see that for the next year in the documents we are talking about roughly ZAR195,000 a kilogram in cash costs and you're talking somewhere around ZAR260,000 total costs including all capital.
This is a similar graph really just in metric. On the left hand graph the red is underground, gray is surface and then we have ounces from PNG, that's Hidden Valley. And the blue line is the grade and it's a total grade, surface and underground so it looks fairly low here. Then on the right hand graph the blue line is ounces.
This is the portfolio as it stands and you can see that we are building up to have some great mines in South Africa, probably some of the best operations. They will be and they rank really from the highest producer down to the lowest. Kusasalethu, Pahkisa, Doomkop, Tshepong and Target are going to be above 200,000 ounces and all have fairly substantial lives, and we're talking 15 to 25 years there. So we we're going to have a formidable portfolio of operations.
But even operations, and if you go down the list and look at Bambanani that's going to be a good mine. It's got still a substantial amount of life. It will be mining its pillar in probably two and a half years time and it will be a very profitable operation.
This is the reserve table, looking at reductions as well as increases. And you can see that what I was talking about, static there, really starting off with 48.2m ounces and ending at 48.1m ounces, an insignificant change there. Mineral resources at close to 190,000 ounces -- sorry, 190m ounces and that's down about 9% from the previous year.
Looking at operations, unfortunately we had seven fatals in the quarter. Again this is despite some great improvements in lost times, some excellent records from fatal free shifts on a lot of operations, but obviously we need to do a lot more in this area. A significant increase in the resource that was reported to you in press releases. Hidden Valley now in commercial production. In this quarter's results there are two months of commercial production.
And then cash operating profits improved by 49% and it's now at ZAR942m. There was a substantial increase in the gold price during this quarter at 11%. But satisfactory, despite some increases in electricity, winter tariffs and the like, and also reducing ounces from closed operations, we managed to keep our costs steady at around just below the ZAR200,000 a kilogram mark. And that's in South Africa. If you add Papua New Guinea it's just over the ZAR200,000 a kilogram. And improvement in the underground grade at 4.71 gram a tonne.
So some of the detail here. I won't go through all of it. You can see at the bottom exchange rate is virtually flat at 7.54. You can see the cash operating costs there fairly flat, 1% negative, almost insignificant, and you can see the gold production improving by 4% quarter on quarter.
For the year on year figures, just over the 1.4m ounces there of gold sold but 1.428m ounces at gold produced, 2% down on the previous year, very small. And then cash operating costs, you can see there's a 16% deterioration there in cash operating costs. Interesting to look at the exchange rate here. We're going from 9 for the previous year to 7.58. So there's quite a bit of pressure from the rand there. And despite the increase in the US dollar per ounce, by 37% -- sorry have I got that right? No, by 26%, the gold price in rand only 6% improvement.
Quarter on quarter underground operations grade coming up 6%, very pleasing. Tonnes and recovery there in line with our expectations and remember that there were some closures during this quarter. Exchange rate again flat and you can see that the operating costs are down there by about 1%.
Surface operations again very satisfactory. Remember that a lot of our surface operations are rock dumps, clean-ups, but also Phoenix tailings operations, so fairly flat in the grade as well as the production there. Tonnes fairly a little bit improvement, but now and again we get a bit lucky and some of the clean up from plants, so the previous quarter had a bit of a clean up in kilograms.
Hidden Valley, as I said, achieved commercial production in May. Gold production improved. Plant throughput increased. It's looking better and better. However, it hasn't achieved in this quarter what we set out to do and there's some critical performance improvements that we are doing. It will have a better quarter that's for sure coming up. And hopefully within the next six months we'll really be able to boast about this one.
I'm going to hand over to Hannes talking about the finances.
Hannes Meyer - FD
Thank you Graham. Good morning everyone. If we look at the income statement quarter on quarter, revenue is up by 21%. That can be attributed to 11% increase in the gold price plus a 6% increase in gold sold for the quarter.
Cash operating costs up by ZAR140m. That can mainly be attributed to Hidden Valley now being accounted for the first time in this quarter, so operating costs, ZAR110m of that increase is attributable to Hidden Valley. Electricity price increases accounted for about ZAR80m increase in this quarter. So despite those increases, ZAR110m and ZAR80m, only up by ZAR140m which is due to the closure of some of our operations. Royalties are up at ZAR28m this quarter, ZAR25m of that in South Africa being the first quarter where royalties was in effect for the full quarter, plus ZAR3m of royalty in Papua New Guinea. That resulted in operating profit up nearly ZAR300m for the quarter.
Then if we look at impairments, we've dealt with most of the impairments in the previous quarters, just a little bit in this quarter that we accounted for. Employment termination/restructuring costs, ZAR82m for this quarter. It mainly relates to Merriespruit 3 and Harmony 2 closures. I think we've dealt with now with most of these operations that were loss making, and we've incurred those costs and we're really positioned now for the future in terms of most of our shafts.
Exploration pretty much in line with the previous quarter and then the big change or the big charge in our income statement relates to tax and mainly to the deferred tax. And there's a ZAR233m in that ZAR210m that relates to a rate adjustment at the end of the year. That relates to evaluation of our business plans every year. Looking forward then at the gold price that we're using and seeing how profitable are we going to be in the future for adjusting the rate accordingly to that. So that accounted for quite a significant charge in our income statement.
That resulted in a net profit for the quarter of ZAR13m, a total headline loss of ZAR0.10 a share, and then if I eliminate that restructuring cost giving me ZAR0.17 per share headline, adjusted headline profit.
If we look at -- we're just going to skip past our income statement, the dollar one on page 23. If we look at that balance sheet, we've still got low gearing levels, 4% debt-to-equity and then debt-to-EBITDA, and there excluded the write offs in terms of impairments, 0.6 to 1 in terms of debt, so still low debt levels. We started this quarter off with ZAR1b of debt, ended the quarter at ZAR1.2b of debt.
Cash increased by about ZAR300m and if we look at how that changed during the quarter, cash flow from operations is nearly ZAR400m more quarter on quarter. Significant increase -- a portion of that was the gold price which was higher by about -- although revenue received was about a higher ZAR300m from that side. Capital expenditure up by ZAR100m. That relates mainly to the Pamodzi assets that we acquired which we call now Target 3 and the President Steyn assets ZAR47m attributable to those assets. Purchased some generators of ZAR29m in the Free State for standby generators for operations. Then Doornkop we incurred additional costs on a belt and some more underground equipment.
Exploration, pretty much the same as the previous quarter. Again that restructuring cost, ZAR82m, also dealt with. Resulting in net debt improving by ZAR100m quarter on quarter from the ZAR520m to ZAR420m.
I'm just going to fudge past the dollar one. Then if we go to the income statement year on year, that's slide 26. Look at revenue, revenue's slightly down year on year. Production costs up by 9%. That's pretty much the inflationary effect of our costs. We had a big change in this year with operations that slowed, some operations coming in. Royalties now the first time in effect this year, ZAR33m.
If we look at operating profit for the year, ZAR2.9b. Amortization and depreciation's up by 10% year on year and that's as we commission our growth projects, we will start incurring more and more amortization/depreciation costs in there. Impairments this year ZAR331m. That was the Evander 2, 5 and 7 shafts, the [Brunt] shaft, Merriespruit 3 and Harmony 2 shafts that we closed, that we incurred those impairment costs for. Employment and restructuring, this year ZAR205m in total, dealing with the same set of shafts as mentioned earlier.
And to the next slide, social investment cost. That's part of our social labor plans and you can see there's a significant increase in our commitment to our communities around our mines and the areas where our mine workers come from. So ZAR81m for the year compared to ZAR33m in the previous year. Exploration, South Africa pretty much the same, and in dollar terms in South East Asia we've spent the same number. It just reflects lower in rands due to the stronger rand. And if we look at tax again, the deferred tax there, the big number, ZAR251m charge versus last year a credit of ZAR480m. So that in all about a swing of ZAR720m year on year.
All that resulted in net loss for the year, ZAR192m, and a total headline loss of ZAR0.07 per share. And again similarly if I do adjusted calculation and adjust for these restructuring costs, getting to ZAR0.49 adjusted headline earnings.
Going to skip through the next two pages in dollars. Then on slide 30 just do a calc. on what we call normalized earnings and say net profit for the quarter ZAR13m. If we eliminate the employment restructuring costs which we say is not of an ongoing nature, ZAR82m, impairments of ZAR30m for the quarter and deferred tax, getting to about ZAR330m of a sustainable earnings point of view. And on the year, eliminating those similar charges, to about ZAR600m then for the year.
With that I'd like to hand back over to Graham.
Graham Briggs - CEO
Thanks Hannes. On exploration a key part of the exploration of this is the Wafi/Golpu area. You can see the Golpu area there in red and the Wafi gold, those are the two main deposits that we're doing the concept studies on at the moment. But you can see that there's a fair amount of exploration focus in these circled areas as well as the yellow areas there. Western zone has been quite elusive. We've drilled several holes into that and really not be enable to key it together, but we will continue doing some more work on that. However, with the exploration happening, we're still going to be continuing with those concept studies.
And really this slide tries to deal with those concept studies. The difference between these, although it doesn't look significant when you read through the text, really we're talking about different open-pit structures. So the first one is an open pit on the oxide levels, which is easy recoverable gold, then looking at the other areas, at underground. And then looking at an alternative taking a bigger pit which is transition as well as oxide. Then the third scenario really is a much bigger pit which takes out most of Wafi as well as part of the Golpu project. And Golpu really looks like it is going to be a block-cave-underground type operation, a big block cave at that.
So those are the concept studies that we're busy with. People ask what sort of expenditure. It's not huge expenditure at the moment because a lot of it is the information we've got. We've got holes into the different deposits for metallurgical studies. So a lot of it is lab work and a lot of hard work by the technical people at the moment. Obviously, that will lead to further drilling and so on, and the exploration in the adjacent deposits will carry on.
Just to conclude, we've got some great plans. Our strategic and business plans, you've seen some diagrams from them and they really indicate growth and costs coming down. Key actions, obviously increase in production, mainly from our projects. That's a key to it. Improving productivity is very important. There's a whole host of issues around that and that deals from safety through to health, through to training. There's a huge focus on that, improving productivity.
Exploration, key to that is in Papua New Guinea, but we have done a fair amount of exploration in South Africa as well. We drilled six bore holes in Joel, which really indicate that we've got another level to go in Joel. Potentially, that could double the life of Joel. At the moment, we are the lowest South African underground producer, when you talk about rand per tonne. That certainly puts us in a little bit of a strategic advantage on dealing with everything we have to do in South African environment.
And then we're really set to grow and get our own money, develop our own projects, have enough cash flow to grow and obviously to pay dividends. Again, you've seen the strategy. You'll see it over and over again. Really positioned to deliver, we're going to grow the Company and we're going to generate free cash flow.
Thank you very much, ladies and gents. I'd like to open ourselves for some questions.
Allan Cooke - Analyst
Morning Graham. It's Allan Cooke from JP Morgan Cazenove. Just two questions. On the Hidden Valley there have been a number of problems. I think the Newcrest guys had spoken about the rainfall there and perhaps some constraints and problems with the design of the plant and a deeper layer of oxide material coming through there. Could you just briefly talk to Hidden Valley and maybe update us on what you expect for the next quarter or the next year ahead, if there's going to be a lower than plan, or a different plan at Hidden Valley as a result of those changes? Perhaps additional CapEx and what you're expecting in terms of the production?
And then on slide 12, I just saw Evander and 8 shaft still factored in your plans there. You mentioned in the past that you may look at doing something else with Evander. Is that still in your thinking or is Evander now firmly part of the Harmony portfolio?
And then in general have we seen all of the shaft closures we're likely to see or can we expect further impairment charges and restructuring charges associated with restructuring the portfolio in financial 2011?
Graham Briggs - CEO
Thanks Allan. Hidden Valley production for this coming year for us, that is 50% of Hidden Valley, is somewhere between 100,000 and 120,000 ounces, probably closer to the 105,000 ounces. So that doesn't quite take it to its level where it should be at 140,000 ounces and that's really because, the next six months we're still predicting quite a lot of the issues. And one of the biggest issues has really been the weathering level that we've experienced there. And it's -- you may say that's nice because easier to dig it out, but it's created all sorts of hassles in the waste-dump areas. And to get fresh rock for the waste dump is one of -- has been one of the biggest issues around Hidden Valley.
Obviously, the plant is a new plant and getting it working properly is still going to take a bit of time. But the guys are having good success. I'm quite happy. And when you go up there and you walk around the plant and speak to the guys, they're really knocking over some of the issues. So I'm not quite as pessimistic maybe as other people are on Hidden Valley.
Evander, yes, we've done -- the intent, and looking at Evander as a separate company, we went through that, and several people here, Bob Atkinson and Alwyn and the rest of the ex-co spent a lot of time looking at it. There's quite a lot of boxes that one needs to tick in going through an IPO and a separate listing process and Evander doesn't tick them all. It would have been a very difficult listing if we did it.
At the same time, we spent a lot of time looking at the existing operations, completed a feasibility on Evander South and it wasn't as robust as we believed. And you'll see that we've taken it out of our reserves and that indicates that it's not that robust. It would require some more exploration and enhancement, mainly because of grade. And of course the capital went up. So that had a few things against it. We're drilling at Poplar so that's not in a state where we can do any banking on that one.
But at the same time, 8 Shaft, we've done some restructuring. We've solved a lot of the environmental conditions there. And it's really focusing on the high-grade portions of 8 Shaft. So, yes, it's part of our portfolio and we're not going to go ahead with that separate listing.
As far as shaft closures go, the only one out there is Merriespruit 1. There's 1,400 people at Merriespruit 1. At the moment we've got that agreement. We'll see how it works. I'm optimistic. There's good cooperation between management and the unions on that operation, but it may close in the future.
Now, 1,400 people, generally we've been able to avoid a lot of the retrenchments. In fact, surprisingly few, inverted commas, compulsory retrenchments we've had. We've had quite a few voluntary retrenchments when we have done retrenchments. And I guess my expectation is that if we were to close it within the next, say, three months or so, we'd probably be able to transfer more than half of those people onto our existing operations. And that's because we always need miners and the like on our existing operations and there's build up coming from Phakisa and Doornkop. I'm sure that we could transfer a lot of those people.
So as far as restructuring costs go, there's nothing in our plan for the quarter coming up. But there may be some small charges still from the previous quarter that we just haven't -- maybe there's a couple coming through but it's going to be small, very small.
Allan Cooke - Analyst
Sorry. Then just one more if I may. Could you also indicate what you expect to be contributed by the Pamodzi assets and the Free State assets that you acquired in terms of your growth plans there?
Graham Briggs - CEO
Yes. For the next quarter, Steyn is still going to be fairly small but there should be a little bit of an increase in what you've -- what we've reported this quarter. Target 3 again fairly static, but we're working quite hard in getting down to the basal reefs, that's through the subshaft. But that's required quite a lot of work in the subshaft to fix it up. These assets were very neglected and as soon as one starts pumping the bottom of the shaft out, you find all sorts of fissures. So that's still going to require a little bit of hard work in the next quarter or so.
But Target 3 will be significant in that it takes probably Target 1 at about 140,000 ounces a year and Target 3 will probably be about 60,000 ounces. And that's where I get to the number of 200,000 ounces in the document you've got. So Target 3 certainly we've got some good ambitions for.
Allan Cooke - Analyst
That's great.
Brendan Ryan - Media
Hi Graham. Brendan Ryan, Mining MX. Two questions please. You say that Evander didn't tick a number of boxes for an IPO. Could you please be more specific on that as to where it fell short?
And then secondly, if I look at your financials, it doesn't seem to me you can afford a dividend so why are you paying one?
Graham Briggs - CEO
Yes. Okay, the box-ticking process, I don't want to go into all of them, but let me take you through some of them. I think from advice on banks and so on, there's a critical size that one needs to go to. If you're going to go to the market, you need to make sure investors have got a reasonable size of operation to invest in. The number that I have given to me is the asset should be worth roughly 3b plus and it doesn't quite get there. And then of course it depends on how much you're actually going to list, what percentage are you as a company going to retain. So it's a size thing.
The next one probably is it has to have a robust plan or at least some good planning objectives, good business plan objectives. And in Evander in our mind when we started off it was raising capital for Evander South. And we thought that would be a reasonable amount of capital. It ended up at plus ZAR2.5b as capital and obviously that was quite considerably more than we thought. The project Libra is still there. That's a possibility and we'll probably go through some pilot studies to see what that's like. But it's not in a robust position where you could actually get it going right now.
And then there's Poplar. Poplar's got lots of potential, but unfortunately the one area in Poplar was that, despite all the drilling that's been done over the years, the core that was there from previous drilling programs was destroyed. And that really is a problem in getting the tick in the box with the competent person's report and saying this has been verified. So some of that drilling has got to be repeated to be able to get the results verified.
So there's quite a few issues. But really the business plan of Evander as a separate listed company was not really amenable to listing it separately.
And your next question was, sorry?
Brendan Ryan - Media
On the dividend.
Graham Briggs - CEO
Dividends. I think our shareholders deserve getting paid a bit of dividend. It's not a huge amount of money when you look at the amount that we're spending on capital. And we believe we've got a very healthy Company and certainly some of the times have been tough, but this year is going to be a good year and then the following years even better. And I would guess the amount of dividend we're talking about is probably less than, what, ZAR250m -- sorry, ZAR215m. Yes, they deserve, our shareholders deserve a little bit of credit and being with us and getting a bit of payment for it. So, good.
Steve?
Steve Shepherd - Analyst
Yes. Steve Shepherd, JP Morgan Cazenove. Graham, obviously the wage increases are coming through on July 1. The power costs are going up. You are going to struggle with a number of your shafts, aren't you, in terms of costs because of that alone?
And then you've obviously got this quite exciting prospect in Papua New Guinea, Wafi/Golpu. Where is this leading us? Because it's obvious, isn't it, that some of these smaller operations in South Africa, you are just going through the motions? They're ultimately going to close because they're too small, the overheads are too high. You've said to Allan just now that you don't foresee any impairments in the coming year. I'm finding it a little bit difficult to reconcile that with some of the operations of Virginia, maybe Evander. Can you talk to that a little bit more please?
Graham Briggs - CEO
Yes, yes. So, yes, there are some cost pressures coming up. And if you look through this quarter's financials, you'll see that there was a substantial increase in the electricity charge. You will also see that there's some -- there's one month of winter tariffs. You'll also see the royalties, full quarter for royalties and despite that you can look at the resultant rand per kilogram.
Now I guess that comes from hard work on the operational level. And if you look at the detail of electricity, when I was getting quizzed probably 18 months, two years' ago on what the electricity cost is going to be in Harmony's account, we were talking probably around 16%. In fact it's closer to 13%. So the guys have done some brilliant savings on electricity as an example. The increases coming through in labor, yes, there's a 7.5% increase in labor from July 1. But if you look at our productivity in ounces, in grams per man, that's where we're trying to regain it. So there are a lot of initiatives to get more productive.
I can give you an example, and you can quiz Tom on it for, as an example, or [Arbrie] for instance. Target now has a medical station much closer to the headgear. In other words, you now have people not being transported to a hospital which has been centralized for a long time. You now catch people early so you don't lose the day transport to the hospital, the day transport back, the day that is queuing at the hospital. You're actually dealing with a man right there at the shaft and the maximum you lose is a day, is a shift. Now, I'm talking about little medical problems that people have. But that creates all sorts of productivity issues.
So there's lots of things happening like that. If you look at Masimong the amount of training that they've done on people that's where we have to recover a lot of lost ground in South Africa.
On impairments, Merriespruit 1 has been impaired, if I'm right. So even if that closes, that's not going to happen. The Bambanani is moving into the shaft pillar. The electricity bill in three years' time is going to be dramatically less than it is at the moment and that's a big electricity consumer.
So we have to keep working not only at a rand per kilogram, but also at a rand per tonne. And that's why I talk about that. You've got to keep all your costs in check. So a lot of hard work going on on the costs, a lot of hard work in productivity and we've got a good set of assets, a good suite of assets.
Steve Shepherd - Analyst
Thank you Graham. I've got a second question, which you might not want to answer. But on the political front in this country we've seen the Kumba debacle. We've now seen the Lonmin debacle. You produce silver and osmiridium and some other metals. Do you have any concerns about being interfered with, in terms of your mining permissions? And for how much longer must we sit and wait for the chief executive officers and the like - you can only speak for yourself - to keep rolling over and accepting this rather interesting treatment, shall we say, from the authorities?
Graham Briggs - CEO
Yes. I don't want to get into the debate on what's happening in other companies. I can simply talk about our own. And in our own obviously the events are concerning and it requires you to re-look at everything you've got from a different angle, a different perspective. But we've done that. We'll continue doing that.
And -- but we -- our production is quite a lot simpler than, for instance, the relationship that you have with the Merensky Reef or the UG2. It's fairly simple. We only produce a little bit of silver. There's that. And we don't have people with participation in our properties. We've actually cleaned that up in our portfolio. So we don't have any outside parties with mineral rights or potential mineral rights, or partnerships and so on in South Africa. So ours is a much simpler business. So, although it's concerning on the macro front in South Africa, as a Company it's not something that we spend too much time worrying about.
Steve Shepherd - Analyst
Finally, on illegal mining, can you give us a brief update there?
Graham Briggs - CEO
Yes, it's certainly been big in the press. It's still a concern. We have had our biggest illegal mining issues in the Free States. We spent a huge amount on securing the shaft heads with fencing and dual-access controls. We've had some good participation from the unions and the like on food bans and so on. But it's still a concern. It's still an ongoing fight to make sure that we have no illegals underground. And it's unfortunate that we still have that sometimes through people getting through the loopholes and so on, but it's a continual process. It has been better of late than we've experienced certainly last year, but it's still a concern and it's still something we spend a lot of money on.