Operator
Operator
Good morning, ladies and gentlemen. Thank you for standing by. Welcome to the Hudbay Minerals third quarter 2026 results conference call. (Operator Instructions) I would like to remind everyone that this conference call is being recorded today, November 12, 2026, at 11:00 a.m. Eastern Time.
各位女士、先生,早安。感謝各位稍候。歡迎參加 Hudbay Minerals 2026 年第三季業績電話會議。(接線員指示)提醒各位,本次電話會議將於今日(2026 年 11 月 12 日)美東時間上午 11:00 錄音。
I will now turn the conference over to Candace Brule, Senior Vice President, Capital Markets and Corporate Affairs. Please go ahead.
現在我將把會議交給資本市場與企業事務資深副總裁 Candace Brule。請開始。
Candace Brule - Senior Vice President of Capital Markets & Corporate Affairs
Candace Brule - Senior Vice President of Capital Markets & Corporate Affairs
Thank you, operator. Good morning, and welcome to Hudbay's third quarter 2026 results conference call. Hudbay's financial results were issued this morning and are available on our website at www.hudbay.com.
謝謝接線員。各位早安,歡迎參加 Hudbay 2026 年第三季業績電話會議。Hudbay 的財務結果已於今早發布,並可在我們的網站 www.hudbay.com 查閱。
A corresponding PowerPoint presentation is available on the Investor Events section of our website, and we encourage you to refer to it during this call. Our presenter today is Peter Kukielski, Hudbay's Chief Executive Officer.
相對應的 PowerPoint 簡報可在我們網站的「投資人活動」專區取得,我們鼓勵各位在本次會議期間參考。今天的簡報人是 Hudbay 執行長 Peter Kukielski。
Accompanying Peter for the Q&A portion of the call will be Eugene Lei, our President and Chief Financial Officer, and Rob Carter, our Chief Operating Officer.
在問答環節,將由我們的總裁兼財務長 Eugene Lei,以及營運長 Rob Carter 陪同 Peter 回答問題。
Please note that comments made on today's call may contain forward-looking information, and this information, by its nature, is subject to risks and uncertainties, and as such, actual results may differ materially from the views expressed today. For further information on these risks and uncertainties, please consult the company's relevant filings on SEDAR plus and EDGAR.
請注意,今日電話會議中的評論可能包含前瞻性資訊;此類資訊本質上存在風險與不確定性,因此實際結果可能與今日所表達的觀點有重大差異。關於這些風險與不確定性的更多資訊,請參閱公司在 SEDAR plus 與 EDGAR 上的相關申報文件。
These documents are also available on our website. As a reminder, all amounts discussed on today's call are in US dollars unless otherwise noted.
這些文件亦可在我們的網站上取得。提醒各位,除非另有說明,今日電話會議中討論的所有金額均以美元計價。
And now I'll pass the call over to Peter Kukielski.
現在我把電話會議交給 Peter Kukielski。
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
Thank you, Candace. Good morning, everyone, and thank you for joining us. Hudbay delivered record results in the third quarter, and our operating performance has positioned us well to achieve our annual consolidated copper production guidance for the 12th consecutive year and annual consolidated gold production guidance for the sixth consecutive year.
謝謝你,Candace。各位早安,感謝各位加入。Hudbay 在第三季交出創紀錄的成果;我們的營運表現使我們有利於連續第 12 年達成年度合併銅產量指引,並連續第 6 年達成年度合併黃金產量指引。
The strength of our diversified operating platform and the dedication of our people helped us achieve record mill throughput at Constancia, significant increases in mine productivity at Lalor, record mill throughput at New Britannia and record gold recoveries at Stall. At Copper Mountain, our three-year operational turnaround delivered the first quarter of positive free cash flow since our acquisition.
我們多元化營運平台的優勢與同仁的投入,協助我們在 Constancia 達成磨礦廠處理量新高、在 Lalor 的礦山生產力顯著提升、在 New Britannia 達成磨礦廠處理量新高,並在 Stall 創下黃金回收率新高。在 Copper Mountain,我們為期三年的營運轉型,使其自我們收購以來首次出現單季正向自由現金流。
Following the quarter, we reached a significant milestone with the final investment decision for the construction and development of Copper World.
在本季之後,我們就 Copper World 的建設與開發作出最終投資決策,達成一項重要里程碑。
These milestones come on the eve of Hudbay's Centennial, and we were pleased to recently be recognized as a 2026 TSX 30 top performer, ranking among the top 30 performing stocks over the past three years.
這些里程碑正值 Hudbay 百年慶前夕;我們也很高興近期獲選為 2026 年 TSX 30 頂尖表現者之一,名列過去三年表現最佳的前 30 檔股票。
Furthermore, we were ranked as one of Canada's top growing companies by The Globe and Mail's Report on Business and as one of Fortune's fastest-growing companies in 2026.
此外,我們亦獲《環球郵報》(The Globe and Mail)《商業報告》(Report on Business)評選為加拿大成長最快企業之一,並入選《財富》(Fortune)2026 年成長最快公司之一。
These recognitions reflect our consistent operational execution, strong financial performance and commitment to delivering shareholder returns as a premier Americas-focused copper producer. Starting on Slide 3.
這些肯定反映我們一貫的營運執行力、強勁的財務表現,以及作為以美洲為核心的頂級銅生產商,致力於為股東創造報酬的承諾。請從投影片第 3 頁開始。
Hudbay delivered record performance this quarter with revenue of $766 million, achieving a new quarterly record, and adjusted EBITDA of $413 million, resulting in record trailing 12-month adjusted EBITDA of over $1.5 billion.
Hudbay 本季創下紀錄表現,營收達 7.66 億美元,刷新單季新高;調整後 EBITDA 為 4.13 億美元,使過去 12 個月的調整後 EBITDA 創下超過 15 億美元的紀錄。
The strong results this quarter were driven by steady operating performance, attractive operating margins and strong exposure to copper and gold across Hudbay's diversified operating portfolio.
本季強勁成果主要來自穩健的營運表現、具吸引力的營運利潤率,以及 Hudbay 多元化營運組合中對銅與黃金的高度曝險。
During the third quarter, our operations delivered consolidated copper production of 30,000 tonnes and gold production of 70,000 ounces, increasing compared to the second quarter due to operating efficiencies throughout the business.
第三季,我們的營運帶來合併銅產量 30,000 公噸與黃金產量 70,000 盎司;由於全公司營運效率提升,較第二季增加。
We have reaffirmed our full year 2026 consolidated production guidance for all metals given our strong operating performance year-to-date.
鑑於年初至今的強勁營運表現,我們重申 2026 年全年度各金屬的合併產量指引。
We continue to demonstrate industry-leading margins during the third quarter with consolidated cash costs of negative $0.19 per pound of copper and sustaining cash cost of $1.61 per pound of copper.
第三季我們持續展現業界領先的利潤率:合併現金成本為每磅銅負 0.19 美元,維持性現金成本為每磅銅 1.61 美元。
Year-to-date results are trending well below the low end of the consolidated cost guidance ranges as our operating efficiencies and strong exposure to gold by-product credits have more than offset external cost pressures.
年初至今的結果顯示,我們的成本走勢明顯低於合併成本指引區間的下緣;營運效率提升與黃金副產品抵減(by-product credits)的強勁貢獻,已超過外部成本壓力的影響。
This has allowed us to improve our full year 2026 consolidated cash cost guidance for a second time this year to a range of negative $0.55 to negative $0.35 per pound of copper.
因此,我們今年第二次上調 2026 年全年度合併現金成本指引,調整為每磅銅負 0.55 美元至負 0.35 美元的區間。
This is an additional improvement of $0.10 from the previously updated guidance range. We are also improving our full year 2026 consolidated sustaining cash cost guidance to a range of $1.40 to $1.80 per pound of copper, a $0.30 improvement from the original guidance range.
相較於先前更新的指引區間,這次再額外改善 0.10 美元。我們也將 2026 年全年度合併維持性現金成本指引上調至每磅銅 1.40 美元至 1.80 美元的區間,較原始指引區間改善 0.30 美元。
Full year consolidated sustaining capital expenditures are expected to be $35 million lower than 2026 guidance with lower capitalized stripping in Peru and BC as well as capital deferrals and efficiencies.
全年度合併維持性資本支出預期將較 2026 年指引低 3,500 萬美元,主要因秘魯與卑詩省的資本化剝採量降低,以及資本遞延與效率提升。
During the third quarter, operating cash flow before change in noncash working capital was $314 million, an increase of $104 million compared to the second quarter.
第三季,未計入非現金營運資金變動前的營運現金流為 3.14 億美元,較第二季增加 1.04 億美元。
Adjusted net earnings were $150 million or $0.34 per share, reflecting strong gross profit margins from the continued focus on cost efficiencies and higher metal prices more than offsetting higher input costs.
調整後淨利為 1.50 億美元(每股 0.34 美元),反映我們持續聚焦成本效率所帶來的強勁毛利率,以及較高的金屬價格,足以抵銷較高的投入成本。
Slide 4 demonstrates the continued strong free cash flow generation as a result of our steady operating performance and strong margins.
投影片第 4 頁顯示,在穩健的營運表現與強勁利潤率帶動下,我們持續產生強勁的自由現金流。
We generated $202 million in free cash flow during the quarter, an increase of approximately $100 million compared to the second quarter through higher production and continued strong operating margins. And as I mentioned earlier, this quarter was the first quarter of positive free cash flow at Copper Mountain since our acquisition.
本季我們產生 2.02 億美元的自由現金流,因產量提高與營運利潤率持續強勁,較第二季增加約 1 億美元。如我先前所提,本季亦為我們收購 Copper Mountain 以來首次出現單季正向自由現金流。
Over the first 9 months of the year, we have generated more than $400 million of free cash flow even after investing over $325 million of sustaining capital in the business, resulting in record trailing 12-month free cash flow of $631 million.
今年前 9 個月,即使我們在業務上投入超過 3.25 億美元的維持性資本,仍已產生超過 4 億美元的自由現金流,使過去 12 個月的自由現金流創下 6.31 億美元的紀錄。
As of September 30, our total liquidity was $964 million, including $789 million in cash and $175 million of undrawn availability on our revolving credit facilities. At the end of the quarter, we had a net cash position of $0.1 million, bringing our net debt-to-EBITDA ratio to 0.0x.
截至 9 月 30 日,我們的總流動性為 9.64 億美元,包括 7.89 億美元現金,以及循環信貸額度中 1.75 億美元的未動用額度。季末我們的淨現金部位為 10 萬美元,使淨負債對 EBITDA 比率為 0.0 倍。
Consistent with our prudent balance sheet management and balanced capital allocation framework during the quarter, we repaid $22 million of the outstanding $272 million draw of our revolving credit facility.
秉持我們審慎的資產負債表管理與均衡的資本配置框架,本季我們償還了循環信貸額度已動用 2.72 億美元中的 2,200 萬美元。
Subsequent to quarter end, we proactively amended and extended our revolving credit facilities, upsizing the capacity to $700 million from $450 million and extending the maturity by two years to November 2030.
在季後,我們主動修訂並展延循環信貸額度,將額度由 4.5 億美元提高至 7 億美元,並將到期日延長兩年至 2030 年 11 月。
The amended agreement includes an improved pricing grid and greater financial flexibility that reflects our robust cash flow, strong balance sheet position and recently upgraded credit rating.
修訂後的協議包含更佳的定價級距與更高的財務彈性,反映我們強勁的現金流、穩健的資產負債表狀況,以及近期上調的信用評等。
After adjusting for the $250 million increase in size of the credit facilities, our pro forma liquidity is approximately $1.2 billion.
在將信貸額度規模增加 2.5 億美元納入調整後,我們的備考(pro forma)流動性約為 12 億美元。
As shown on Slide 5, our Peru operations continue to demonstrate steady operating performance with production and costs well positioned to achieve our annual guidance ranges.
如投影片第 5 頁所示,我們在秘魯的營運持續展現穩健表現,產量與成本均處於有利位置,可望達成年度指引區間。
The Constancia mill achieved record throughput of approximately 91,000 tonnes per day in the third quarter and is on track to achieve 34 million tonnes per annum in 2027.
Constancia 磨礦廠第三季達成約每日 91,000 公噸的處理量新高,並正按計畫於 2027 年達成年處理量 3,400 萬公噸。
We completed the installation of a third rougher line in September, which immediately had a positive impact on recoveries.
我們已於 9 月完成第三條粗選(rougher)線的安裝,並立即對回收率產生正面影響。
We also continue to advance the installation of 2 pebble crushers with commissioning expected later this month.
我們也持續推進兩台卵石破碎機(pebble crushers)的安裝,預計將於本月稍晚進行試車投運。
Together, these enhancements will allow Constancia to continue to deliver steady annual copper production despite lower grades following the depletion of Pampacancha at the end of 2025.
綜合而言,這些強化措施將使 Constancia 即使在 2025 年底 Pampacancha 枯竭後品位下降的情況下,仍能持續實現穩定的年度銅產量。
During the third quarter, the Peru operations produced 21,000 tonnes of copper, 5,000 ounces of gold, 577,000 ounces of silver and 301 tonnes of molybdenum.
第三季,秘魯營運產出銅 21,000 公噸、黃金 5,000 盎司、白銀 577,000 盎司,以及鉬 301 公噸。
Copper and molybdenum production was slightly higher compared to the second quarter, reflecting higher mill throughput because of efficiency improvements and the impact of the semiannual plant maintenance shutdown last quarter. Gold production was comparable to the second quarter.
與第二季相比,銅與鉬產量略有增加,反映出因效率提升而帶動的磨礦處理量提高,以及上一季半年一次的選廠維修停機所帶來的影響。黃金產量與第二季相當。
We are on track to achieve our 2026 production guidance for all metals in Peru with gold expected to exceed the top end of the guidance range.
我們正按計畫達成秘魯所有金屬的 2026 年產量指引,其中黃金預期將高於指引區間上緣。
Total material moved was 25 million tonnes during the third quarter, achieving a new monthly record in July. Total ore mined increased by 16% to 12.7 million tonnes compared to the second quarter, supported by active mining across three exposed ore phases and positive reconciliation.
第三季總移運量為 2,500 萬公噸,並於 7 月創下新的單月紀錄。與第二季相比,總採礦礦石量增加 16% 至 1,270 萬公噸,受惠於三個已揭露礦體階段的積極採礦作業以及良好的對帳結果。
Our focus on mining exclusively in one pit unlocks operational efficiencies, including shorter hauling distances, haul route optimizations and high truck fleet utilization.
我們專注於僅在單一礦坑採礦,可釋放營運效率,包括更短的運距、運輸路線最佳化,以及卡車車隊的高利用率。
The record mill throughput of 91,000 tonnes per day was a 7% increase compared to the second quarter, primarily due to higher plant availability and lower ore hardness as well as the benefits of increased mill processing capacity supported by the recently approved permit amendment.
磨礦處理量創紀錄達每日 91,000 公噸,較第二季增加 7%,主要由於選廠可用率提高、礦石硬度降低,以及近期核准的許可證修訂所支持之磨礦處理能力提升所帶來的效益。
Third quarter cash costs in Peru were $2.23 per pound of copper. This increased from the prior quarter due to lower silver and gold by-product credits, higher profit sharing, higher fuel prices and higher fuel consumption from increased material moved.
秘魯第三季現金成本為每磅銅 2.23 美元。相較前一季上升,原因包括白銀與黃金副產品抵減減少、利潤分成提高、燃料價格上升,以及因移運量增加而導致燃料消耗提高。
Cash costs for the quarter were above the 2026 guidance range.
本季現金成本高於 2026 年指引區間。
However, year-to-date cash costs continue to outperform the low end of the full year guidance range, so we remain well positioned to achieve the 2026 cash cost guidance in Peru. Moving to our Manitoba operations on Slide 6.
然而,年初至今的現金成本仍優於全年指引區間的低端,因此我們仍具備良好條件在秘魯達成 2026 年現金成本指引。接著看投影片 6 的曼尼托巴營運。
We delivered a strong third quarter, achieving key operational performance targets and executing on our commitment to deliver a stronger second half of 2026.
我們第三季表現強勁,達成關鍵營運績效目標,並落實我們對於在 2026 年下半年交出更強表現的承諾。
Our Manitoba operations produced 57,000 ounces of gold, 3,000 tonnes of copper, 3,700 tonnes of zinc and 268,000 ounces of silver in the third quarter.
我們曼尼托巴營運第三季產出黃金 57,000 盎司、銅 3,000 公噸、鋅 3,700 公噸,以及白銀 268,000 盎司。
Production increased compared to the second quarter as a result of higher mill throughput and improved gold feed grades.
由於磨礦處理量提高以及黃金入料品位改善,產量較第二季增加。
We are on track to achieve our 2026 production guidance for all metals in Manitoba. Performance at the Lalor mine improved significantly during the quarter with improved equipment utilization driving efficiencies in underground development and increases in mine production.
我們正按計畫達成曼尼托巴所有金屬的 2026 年產量指引。本季 Lalor 礦山表現顯著改善,設備利用率提升帶動地下開發效率提高並增加礦山產量。
To address prior labor availability constraints and accelerate development at the 1901 deposit, we embedded an experienced mining contractor, which allows our skilled internal workforce to be redeployed toward critical development areas at Lalor.
為解決先前勞動力供給限制並加速 1901 礦床的開發,我們引進具經驗的採礦承包商,使我們熟練的內部人力得以重新部署至 Lalor 的關鍵開發區域。
In tandem, we have expanded our internal capacity by onboarding over 150 new employees this year. Our underground improvement efforts during the quarter included operational testing of a roadheader continuous mining unit to understand its potential in lateral development.
同時,我們今年已招募超過 150 名新員工以擴充內部產能。本季地下改善工作包括對巷道掘進機(roadheader)連續採掘單元進行營運測試,以了解其在橫向開發中的潛力。
The Lalor mine hoisted an average of 4,200 tonnes of ore per day during the quarter, strategically prioritizing gold feed. Development activity at the 1901 deposit focused on exploration and infill drilling, ore body access and critical infrastructure with late 2027 remaining the targeted time line for full production.
本季 Lalor 礦山平均每日提升 4,200 公噸礦石,並策略性優先供應黃金入料。1901 礦床的開發活動聚焦於探勘與加密鑽探、礦體通達以及關鍵基礎設施,全面投產的目標時程仍為 2027 年底。
The New Britannia mill achieved a new quarterly throughput record averaging 2,250 tonnes per day in the quarter, aligning with gold ore output from Lalor.
New Britannia 選廠本季平均每日處理量達 2,250 公噸,創下新的季度處理量紀錄,並與 Lalor 的金礦礦石產出相匹配。
The mill achieved gold recoveries of approximately 92%, reaching a new quarterly record. The Stall mill demonstrated higher throughput compared to the second quarter of 2026, while achieving record gold recoveries of 74% as a result of our recovery-focused initiatives.
該選廠黃金回收率約 92%,創下新的季度紀錄。Stall 選廠相較 2026 年第二季展現更高處理量,並在我們以回收率為核心的措施帶動下,黃金回收率創紀錄達 74%。
We initiated early works on the Stall Hot Tails Leaching Project, which will unlock additional gold recovery from material processed at the Stall mill through leaching at New Britannia. We have also initiated early evaluation work on processing legacy tailings and mineralized piles to utilize excess mill capacity.
我們已啟動 Stall 熱尾礦浸出(Hot Tails Leaching)專案的前期工程,將透過在 New Britannia 進行浸出,從 Stall 選廠處理的物料中釋放額外的黃金回收。我們也已啟動對處理歷史尾礦與礦化堆料的前期評估工作,以利用多餘的選廠產能。
We continue to advance key sustaining capital environmental initiatives, including the cyanide recycling project at New Britannia and the dam lift at Anderson tailings, both of which remain on track for completion by year-end.
我們持續推進關鍵的維持性資本環境措施,包括 New Britannia 的氰化物回收再利用專案,以及 Anderson 尾礦庫的壩體加高工程,兩者皆仍按計畫於年底前完成。
Manitoba gold cash costs in the third quarter were $403 per ounce, a decrease of 48% compared to the second quarter, driven by higher gold production and higher byproduct credits. We are well positioned to achieve our 2026 cash cost guidance range in Manitoba.
曼尼托巴第三季黃金現金成本為每盎司 403 美元,較第二季下降 48%,主要受更高的黃金產量與更高的副產品抵減所帶動。我們具備良好條件達成曼尼托巴 2026 年現金成本指引區間。
At our operations in British Columbia, we achieved significant milestones in mining productivity, operational performance and project execution in the third quarter, as outlined on Slide 7.
在卑詩省的營運方面,我們第三季在採礦生產力、營運績效與專案執行上達成重要里程碑,如投影片 7 所示。
We also received ISO 14001 and ISO 45001 certifications at Copper Mountain, reflecting our focus on safety and environmental management.
我們亦在 Copper Mountain 取得 ISO 14001 與 ISO 45001 認證,反映我們對安全與環境管理的重視。
The positive free cash flow generation at Copper Mountain this quarter demonstrates the benefits from our continued operating efficiencies, recent mill improvement initiatives and the ongoing execution of the accelerated stripping program.
Copper Mountain 本季正向自由現金流的產生,展現了我們持續提升營運效率、近期選廠改善措施,以及加速剝採計畫持續執行所帶來的效益。
Copper Mountain produced 6,600 tonnes of copper, 7,000 ounces of gold and 52,000 ounces of silver in the third quarter.
Copper Mountain 第三季產出銅 6,600 公噸、黃金 7,000 盎司,以及白銀 52,000 盎司。
Compared to the second quarter, copper and gold production increased with higher head grades and improved recoveries more than offsetting the impact of the primary SAG mill maintenance downtime.
與第二季相比,銅與黃金產量增加;較高的入磨品位與回收率改善,已足以抵銷主要 SAG 磨機維修停機時間的影響。
We are on track to achieve our 2026 production guidance for all metals in British Columbia. Total material movement at Copper Mountain was 27 million tonnes in the quarter, which continues to be elevated with the accelerated stripping program.
我們正按計畫達成卑詩省所有金屬的 2026 年產量指引。Copper Mountain 本季總移運量為 2,700 萬公噸,在加速剝採計畫下仍維持高檔。
During the quarter, total ore mined increased 56% quarter-over-quarter, driven by favorable ore release timing from the North Pit. Mill copper grades averaged 0.27% in the quarter and copper recoveries slightly increased to approximately 80%. British Columbia cash costs were $3.09 per pound of copper.
本季總採礦礦石量較上季增加 56%,主要受 North Pit 有利的出礦時點所帶動。本季選廠入磨銅品位平均為 0.27%,銅回收率小幅提升至約 80%。卑詩省現金成本為每磅銅 3.09 美元。
The improvement from the prior quarter reflects higher copper production, lower treatment and refining charges and strong by-product credits, which offset the higher site operating costs.
相較前一季的改善,反映更高的銅產量、更低的冶煉與精煉費用,以及強勁的副產品抵減,抵銷了較高的現場營運成本。
Year-to-date costs reflect higher site operating costs, including elevated fuel prices, and we expect full year cash costs to track toward the high end of the annual guidance range in British Columbia.
年初至今的成本反映較高的現場營運成本(包括偏高的燃料價格),我們預期卑詩省全年現金成本將落在年度指引區間的高端附近。
The next slide highlights the progress we have made with our optimization efforts at Copper Mountain since our acquisition, leveraging our strong operational expertise and social license to unlock significant value. Quarterly material movement has more than doubled, increasing 108% compared to the levels prior to our ownership.
下一張投影片重點呈現自我們收購以來在 Copper Mountain 所推動的最佳化成果;我們運用強大的營運專業能力與社會許可,釋放顯著價值。季度移運量已較我們持有前的水準增加逾一倍,增幅達 108%。
With a three-year stripping program ending this year, we anticipate delivering higher grades starting next year, which together with the benefits of our mill enhancements is expected to result in a doubling of our annual copper production in British Columbia.
隨著為期三年的剝採計畫於今年結束,我們預期自明年起可交付更高品位;再加上選廠強化的效益,預期將使我們在卑詩省的年度銅產量倍增。
During the third quarter, following the scheduled replacement of the primary SAG mill feed and head in July, the mill has achieved successive monthly mill throughput increases. In September, the mill achieved mill throughput of approximately 43,500 tonnes per day.
第三季中,在 7 月按計畫完成主要 SAG 磨機入料端與端蓋(head)的更換後,選廠已連續數月達成月度處理量提升。9 月,選廠處理量約達每日 43,500 公噸。
We remain on track to achieve the target of 50,000 tonnes per day by the end of the year, which would represent a 44% increase compared to the mill throughput prior to our ownership.
我們仍按計畫在年底前達成每日 50,000 公噸的目標,這將較我們持有前的選廠處理量增加 44%。
These operational improvements have allowed us to significantly improve cash costs and deliver a long-term sustainable operation that will generate strong free cash flow.
這些營運改善使我們得以大幅改善現金成本,並打造可長期永續運作、可產生強勁自由現金流的營運體系。
I'm very pleased with the progress the team has made to turn around this operation and unlock significant value at Copper Mountain.
我對團隊在扭轉這項營運並於 Copper Mountain 釋放顯著價值方面所取得的進展感到非常滿意。
Turning to Slide 9.
接著看第 9 張投影片。
As part of our global exploration program, we continue to look for ways to extend mine life across our operations.
作為我們全球勘探計畫的一部分,我們持續尋找在各項營運中延長礦山壽命的方法。
This program has resulted in some exciting exploration news in Peru. At Constancia, recent drilling intersected a potential new high-grade feeder system, including over 200 meters of 0.43% copper and 0.03% molybdenum.
該計畫在秘魯帶來了一些令人振奮的勘探消息。在 Constancia,近期鑽探穿越了一個潛在的新高品位供礦系統,其中包括超過 200 公尺、銅品位 0.43% 及鉬品位 0.03% 的礦段。
For context, that is almost 50% higher copper grade and 3x the molybdenum grade that was processed in the third quarter.
作為對照,這幾乎比第三季處理的銅品位高出 50%,而鉬品位則高出 3 倍。
The two deep diamond drill holes successfully intersected lateral and down-dip extensions of the porphyry system and mineralized breccia zones below and adjacent to the Constancia pit. This has been the most promising exploration results we've seen at Constancia over the past decade.
兩個深部金剛石鑽孔成功穿越了斑岩系統的側向與傾向延伸,以及位於 Constancia 礦坑下方及鄰近區域的礦化角礫岩帶。這是我們在過去十年於 Constancia 所見最具前景的勘探成果。
Notably, the holes intersected significant widths of mineralized breccia extending beyond the limits of the current resource at grades higher than current reserve grades.
值得注意的是,鑽孔穿越了顯著寬度的礦化角礫岩,其延伸超出目前資源量界限,且品位高於目前儲量品位。
Follow-up drilling is underway, along with geological vectoring to test the geometry and structural controls and determine the scale of mineralization down plunge and at depth.
後續鑽探正在進行,同時配合地質向量分析,以測試其幾何形態與構造控制,並判定礦化在下傾方向及深部的規模。
This high-grade system has the potential to enhance Constancia's long-term production profile. Slide 10 provides an update on our growth and exploration activities in Canada, where high-return brownfield opportunities and prospective exploration programs across Manitoba and British Columbia are being advanced to continue to extend mine life and increase production.
此高品位系統有潛力提升 Constancia 的長期產量概況。第 10 張投影片更新我們在加拿大的成長與勘探活動;我們正推進曼尼托巴省與卑詩省的高回報棕地機會及具前景的勘探計畫,以持續延長礦山壽命並提高產量。
In Manitoba, we are executing an extensive exploration program across our highly prospective land package of more than 400,000 hectares, which extends across the Flin Flon and Snow Lake Greenstone Belt.
在曼尼托巴省,我們正在超過 40 萬公頃、極具前景的土地包上執行大規模勘探計畫,該土地包橫跨 Flin Flon 與 Snow Lake 綠岩帶。
Our strategy focuses on 3 avenues of opportunity. First, focusing on converting our 1.5 million ounces of gold in inferred resources to reserves through infill drilling.
我們的策略聚焦於三個機會途徑。第一,透過加密鑽探,將我們推定資源中的 150 萬盎司黃金轉換為儲量。
We are confident in our ability to do so based on historical track records of converting approximately 90% of inferred resources to reserves at Lalor over the past five years.
基於過去五年在 Lalor 將約 90% 推定資源轉換為儲量的歷史紀錄,我們對達成此目標充滿信心。
Second, we continue to extend the current mine life of our anchor deposit, Lalor and 1901, which continue to show potential for extensions of high-grade stacked lenses and remain open down plunge.
第二,我們持續延長作為核心礦床的 Lalor 與 1901 的現有礦山壽命;兩者仍展現高品位疊置透鏡體延伸的潛力,且在下傾方向仍為開放。
During the third quarter, advancement of underground exploration drifts at Lalor and 1901 established new drilling platforms that will enable additional infill drilling and testing for extensions along mineralized trends.
在第三季,Lalor 與 1901 的地下勘探巷道推進建立了新的鑽探平台,將可支援更多加密鑽探,並測試沿礦化趨勢的延伸。
And third, we are highly focused on looking for a new anchor deposit through regional exploration and advancing the Britannia Gold Project, which I will discuss later in the presentation.
第三,我們高度聚焦於透過區域勘探尋找新的核心礦床,並推進 Britannia 黃金專案;我將在簡報稍後進一步說明。
In British Columbia, following the June groundbreaking at New Ingerbelle, the infrastructure development continues to progress on schedule, derisking the path to first production in late 2028.
在卑詩省,繼 6 月於 New Ingerbelle 動工後,基礎設施開發持續按進度推進,降低於 2028 年底首次投產路徑的風險。
We completed the West Access road and established a temporary construction bridge to facilitate the installation of the permanent bridge.
我們已完成西側進場道路,並建立臨時施工橋梁,以利永久橋梁的安裝。
New Ingerbelle is expected to support continuous operations beyond 2040 and provide access to higher grade ore at approximately one-third of the strip ratio seen in recent historical mining areas.
New Ingerbelle 預期可支援 2040 年以後的持續營運,並可在剝採比約為近期歷史採礦區域三分之一的情況下,取得更高品位礦石。
We are also nearing completion of a 66,000-meter infill and expansion drilling program of New Ingerbelle, which will potentially allow us to convert additional inferred resources to measured and indicated and test for possible extensions beyond the limits of the current mineral resource.
我們也接近完成 New Ingerbelle 的 66,000 公尺加密與擴展鑽探計畫,該計畫可能使我們將更多推定資源轉換為探明及控制資源,並測試現有礦產資源界限以外的可能延伸。
The drilling remains on track for completion in the fourth quarter with results to be reflected in our annual reserve and resource update in March 2027. Additional geotechnical drilling and geometallurgical sampling are underway to support mine plan optimization and metallurgical recovery modeling.
鑽探仍按計畫於第四季完成,成果將反映在我們 2027 年 3 月的年度儲量與資源更新中。此外,為支援礦山計畫最佳化與冶金回收率模型,我們正進行額外的岩土鑽探與地質冶金取樣。
Slide 11 highlights the recent Snow Lake mine plan announcement and the significant increase in life of mine gold production.
第 11 張投影片重點說明近期 Snow Lake 礦山計畫公告,以及礦山壽命期間黃金產量的大幅提升。
The updated mine plan reflects a 37% increase in gold production over the next five years and a 60% increase in total gold production over the life of mine based on current mineral reserves compared to the prior technical report.
更新後的礦山計畫顯示,未來五年黃金產量增加 37%,且在目前礦產儲量基礎上,相較先前技術報告,礦山壽命期間的黃金總產量增加 60%。
The updated mine plan maintains average production of 185,000 ounces of gold over the next five years, reflecting several optimization initiatives, including higher mill throughput at New Britannia and higher gold recoveries at the Stall mill to better utilize the combined 6,300 tonnes per day of processing capacity.
更新後的礦山計畫在未來五年維持平均年產 185,000 盎司黃金,反映多項最佳化措施,包括提升 New Britannia 的磨礦處理量,以及提高 Stall 選礦廠的黃金回收率,以更有效利用合計每日 6,300 噸的處理產能。
Snow Lake's reserve mine life has been extended to 2043 with total current mineral reserve estimates of 27 million tonnes, including roughly 2 million ounces of gold.
Snow Lake 的儲量礦山壽命已延長至 2043 年,目前礦產儲量估計總量為 2,700 萬噸,其中約含 200 萬盎司黃金。
The increase is due to resource conversion at Lalor and 1901, higher reserves at the WIM and three Zone satellite deposits and the first reserve estimates for Talbot and Rail.
此增幅主要來自 Lalor 與 1901 的資源轉換、WIM 與 Three Zone 衛星礦床的儲量提高,以及 Talbot 與 Rail 的首次儲量估算。
The updated mine plan represents a conservative view based on Hudbay's historical high resource to reserve conversion rate.
更新後的礦山計畫採取保守觀點,係基於 Hudbay 歷來資源轉儲量的高轉換率。
The mine plan has been optimized for higher mill throughput rates at New Britannia, increasing milling rates from the current 2,000 tonnes per day, exceeding the nameplate of 1,500 tonnes per day and ramping up to 2,300 tonnes per day starting in 2027.
該礦山計畫已針對 New Britannia 較高的磨礦處理量進行最佳化,將磨礦速率自目前每日 2,000 噸提高,超越名目產能每日 1,500 噸,並自 2027 年起逐步提升至每日 2,300 噸。
It also reflects the benefits from the Stall Hot Tails Leaching Project that aims to recover additional gold and silver through expansion of the cyanide leaching and carbon infrastructure at New Britannia to accommodate material from Stall to increase overall gold and silver recoveries starting in early 2028.
同時也反映 Stall Hot Tails 浸出專案的效益;該專案旨在透過擴建 New Britannia 的氰化浸出與活性碳設施,以容納來自 Stall 的物料,並自 2028 年初起提高整體黃金與白銀回收率。
The full technical report was filed last week. Slide 12 highlights the Britannia Gold Project, where multiple targets are being developed down-plunge and along strike from known mineralization across a mineralized corridor that spans 5 historical deposits.
完整技術報告已於上週提交。第 12 張投影片重點介紹 Britannia 黃金專案;在一條跨越 5 個歷史礦床的礦化走廊上,我們正沿已知礦化的下傾方向與走向開發多個目標。
All of the deposits remain open at depth with high-grade ore shoots tracking in predictable plunge directions and the large untested gaps along strike between the known deposits represent immediate potential for new discoveries.
所有礦床在深部仍為開放,高品位礦柱沿可預測的傾伏方向延伸,而已知礦床之間沿走向存在的大型未測試空隙,代表近期發現新礦體的直接潛力。
During the quarter, digitalization and remodeling of decades of historical data identified several high-priority target areas laterally and down-plunge.
本季期間,透過將數十年的歷史資料數位化並重新建模,我們在側向與下傾方向辨識出數個高優先目標區。
Drilling from surface is underway in parallel with our assessment of options to restore historical underground access from the New Britannia shaft infrastructure, which provides the potential for accelerated access.
地表鑽探正在進行,同時我們也在評估利用 New Britannia 立井基礎設施恢復歷史地下通道的選項,以加速進入作業區的可能性。
Altogether, the Britannia Gold Project provides the opportunity to redevelop an underexplored, past-producing deposit with the potential to become a new anchor in the Snow Lake camp.
整體而言,Britannia 黃金專案提供重新開發一處勘探不足、曾經生產的礦床之機會,並有潛力成為 Snow Lake 礦區的新核心資產。
Moving to Copper World on Slide 13.
接著看第 13 張投影片的 Copper World。
We have taken a significant step towards establishing a major US copper division. Together with our partner, Mitsubishi, we announced the final investment decision to proceed with the construction and development of Copper World.
我們已朝建立美國主要銅業事業部邁出重要一步。我們與合作夥伴三菱(Mitsubishi)共同宣布最終投資決策,將推進 Copper World 的建設與開發。
This will be the next major copper mine in the United States and one of the largest open pit copper mines in the country.
這將成為美國下一座大型銅礦,也是全美最大的露天銅礦之一。
First production is targeted for the second half of 2029, establishing Hudbay's strategic footprint in the region.
首批投產目標為 2029 年下半年,藉此建立 Hudbay 在該區域的策略性布局。
The final investment decision is supported by the robust economic returns with low capital intensity outlined in the definitive feasibility study, which delivers average annual copper production of 102,000 tonnes over the first 10 years at attractive cash costs of $1.65 per pound of copper.
最終投資決策係以確定性可行性研究所揭示的強勁經濟報酬與低資本強度為支撐;該研究顯示,前 10 年平均年產銅 102,000 噸,且現金成本具吸引力,為每磅銅 1.65 美元。
The base case contemplates a 15-year mine life based on mineral reserves of 319 million tonnes and requires only state and local permits.
基準情境假設在 3.19 億噸礦產儲量基礎上,礦山壽命為 15 年,且僅需取得州與地方層級許可。
The base case further optimizes the 2023 pre-feasibility mine plan with an in-pit crushing and conveying system in year four and an expansion of the concentrator from 60,000 tonnes per day to 90,000 tonnes per day in year five.
基準情境亦在 2023 年預可行性礦山計畫基礎上進一步最佳化:於第 4 年導入坑內破碎與輸送系統,並於第 5 年將選礦廠產能由每日 60,000 噸擴增至每日 90,000 噸。
The concentrator expansion enables a 43% increase in average annual copper production to 120,000 tonnes in year 6 to 10 compared to the first five years.
選礦廠擴建使第 6 至第 10 年的平均年產銅量相較前五年提高 43%,達到 120,000 噸。
The base case generates an after-tax net present value or NPV of $1.2 billion and an internal rate of return or IRR of 17% at a long-term copper price of $5 per pound.
基本情境在長期銅價每磅 5 美元下,產生稅後淨現值(NPV)12 億美元及內部報酬率(IRR)17%。
At a $6 copper price, the NPV increases to $2.3 billion and the IRR increases to 22%. The extension case contemplates a 37-year mine life utilizing only measured and indicated mineral resources and expands mining activities onto federal lands in year 10, subject to obtaining federal permits.
在銅價每磅 6 美元時,NPV 增加至 23 億美元,IRR 提升至 22%。延伸情境設想 37 年礦山壽命,僅使用已探明與指示礦產資源,並在第 10 年將採礦活動擴展至聯邦土地,但須取得聯邦許可。
It maintains annual copper production of 117,000 tonnes from years 11 to 20 and generates an after-tax NPV of $2.5 billion and an IRR of 19% at $5 per pound of copper.
在銅價每磅 5 美元下,該延伸情境於第 11 至第 20 年維持每年 117,000 公噸的銅產量,並產生稅後 NPV 25 億美元及 IRR 19%。
The extension case NPV increases to $4 billion and the IRR increases to 24% at a copper price of $6. Copper World is anticipated to increase our consolidated annual copper production to approximately 250,000 tonnes, doubling our current production levels, and it is expected to deliver peer-leading low cash cost of $1.65 per pound over the first 10 years as summarized on Slide 14 and 15.
在銅價每磅 6 美元時,延伸情境的 NPV 增加至 40 億美元,IRR 提升至 24%。如投影片 14 與 15 所彙總,Copper World 預期將把我們合併年度銅產量提高至約 250,000 公噸,使目前產量水準倍增,並預期在前 10 年交付同業領先的低現金成本每磅 1.65 美元。
The initial growth capital of $2 billion includes approximately $200 million related to changes in project scope since the 2023 pre-feasibility study.
20 億美元的初始成長資本包含約 2 億美元,係與自 2023 年預可行性研究以來專案範疇變更相關。
We have put in place a prudent low leverage funding plan that will maximize risk-adjusted returns. Sources of capital include Mitsubishi's $600 million initial investment and Wheaton's $230 million stream deposit with a plan to put in place up to $650 million in project level debt financing, representing less than 30% leverage.
我們已建立一項審慎、低槓桿的融資計畫,以最大化風險調整後報酬。資金來源包括三菱 6 億美元的初始投資,以及 Wheaton 2.3 億美元的串流(stream)預付款,並計畫安排最高 6.5 億美元的專案層級債務融資,槓桿比率低於 30%。
This defers Hudbay's first capital contribution to 2028 with our contribution expected to be roughly $500 million, representing less than 25% of the initial growth capital.
此安排將 Hudbay 的首次資本出資延後至 2028 年,我們的出資預期約為 5 億美元,占初始成長資本的比例低於 25%。
With this funding structure, the levered IRR to Hudbay increases to 32% in the base case at a $5 copper price and to 44% in the extension case at a $6 copper price.
在此融資結構下,Hudbay 的槓桿後 IRR 在基本情境、銅價每磅 5 美元時提高至 32%,在延伸情境、銅價每磅 6 美元時提高至 44%。
With the sanctioning of Copper World, we now expect full year growth expenditures related to the Copper World Joint Venture to total $245 million in 2026, an increase of $110 million related to project construction and development costs in the fourth quarter.
隨著 Copper World 核准推進,我們目前預期 2026 年與 Copper World 合資企業相關的全年成長支出合計為 2.45 億美元,其中第四季因專案施工與開發成本增加而上調 1.1 億美元。
The Copper World project is expected to generate significant benefits for the community and local economy in Arizona through significant job creation, tax revenue and economic development.
Copper World 專案預期將透過大量創造就業、稅收收入與經濟發展,為亞利桑那州的社區與地方經濟帶來顯著效益。
Copper World is expected to contribute more than $1.1 billion in US taxes over the 15-year mine life in the base case and up to $3.7 billion over the 37-year mine life in the extension case.
在基本情境下,Copper World 預期在 15 年礦山壽命期間貢獻超過 11 億美元的美國稅收;在延伸情境下,於 37 年礦山壽命期間最高可達 37 億美元。
We expect to create more than 1,000 jobs during construction, over 500 permanent operating roles and up to 3,000 indirect employment opportunities at Copper World. Slide 16 benchmarks Copper World's capital intensity against peer projects and recently completed builds.
我們預期在施工期間創造超過 1,000 個工作機會、超過 500 個永久營運職位,並在 Copper World 帶來最多 3,000 個間接就業機會。投影片 16 將 Copper World 的資本強度與同業專案及近期完工的建置案進行對標比較。
The project maintains an attractive capital intensity of approximately $22,600 per annual tonne of copper production, positioning it well relative to peers. What differentiates Hudbay is our track record of low-risk, low capital intensity projects such as our Copper Mountain optimization project and our Constancia greenfield project built more than a decade ago.
該專案維持具吸引力的資本強度,約為每年每公噸銅產量 22,600 美元,使其相較同業具備良好定位。Hudbay 的差異化在於我們在低風險、低資本強度專案方面的實績,例如我們的 Copper Mountain 最佳化專案,以及十多年前建成的 Constancia 綠地(greenfield)專案。
We will leverage this proven track record of efficient mine building expertise and operational excellence to deliver our next major copper mine development in Copper World, followed by Cactus to build the third largest copper district in North America.
我們將運用這項經驗證的高效率建礦專業與卓越營運實績,在 Copper World 推進下一個大型銅礦開發,之後再推進 Cactus,以打造北美第三大銅礦區。
Concluding on Slide 17, our focus on demonstrating continued operational excellence while prudently advancing our many organic growth opportunities will deliver significant copper production growth in the near term, medium term and long term.
在投影片 17 的結語中,我們專注於展現持續的卓越營運,同時審慎推進多項內生成長機會,將在短期、中期與長期帶來顯著的銅產量成長。
Our portfolio of long-life assets in Tier 1 jurisdictions provides a strong foundation for growth. With brownfield investments at our operating mines in Peru, Manitoba and British Columbia, we are expected to increase consolidated copper production by more than 25% starting next year.
我們在第一級(Tier 1)司法管轄區擁有長壽命資產組合,為成長提供堅實基礎。透過在秘魯、曼尼托巴與卑詩省營運礦山的棕地(brownfield)投資,我們預期自明年起合併銅產量將增加超過 25%。
With the sanctioning of Copper World, our annual copper production will double to approximately 250,000 tonnes.
隨著 Copper World 核准推進,我們的年度銅產量將倍增至約 250,000 公噸。
And with the staged development of Cactus and Mason to follow, we have an attractive pathway to more than 500,000 tonnes of copper per year in the next decade.
此外,隨後分階段開發 Cactus 與 Mason,我們在未來十年具備一條具吸引力的路徑,可達到每年超過 500,000 公噸的銅產量。
What sets Hudbay apart is its low-risk, low capital intensity growth located in some of the best mining jurisdictions in the world, underpinned by our unique diversification in copper and gold exposure, strong margins and a rock-solid balance sheet.
Hudbay 的獨特之處在於其低風險、低資本強度的成長,位於全球一些最佳的採礦司法管轄區;並以我們在銅與黃金曝險上的獨特多元化、強勁利潤率與極為穩健的資產負債表作為支撐。
As we continue to advance all these attractive growth initiatives across the portfolio, we remain committed to prudently allocating capital to the highest risk-adjusted return opportunities that will double our copper production per share and generate strong value for our stakeholders.
在我們持續推進投資組合中所有這些具吸引力的成長計畫之際,我們仍致力於審慎配置資本至風險調整後報酬最高的機會,以使我們每股銅產量倍增,並為利害關係人創造強勁價值。
We have the right assets, the right team and the financial strength to execute on our strategic plans as we continue to solidify our position as the premier Americas-focused copper producer.
我們擁有合適的資產、合適的團隊與財務實力來執行我們的策略計畫,並持續鞏固我們作為以美洲為重點的頂尖銅生產商之地位。
And with that, we are pleased to take your questions.
接下來,我們很高興回答各位的提問。
Operator
Operator
(Operator Instructions) Richard Garchitorena, Barclays.
(接線員指示) Barclays 的 Richard Garchitorena。
Richard Garchitorena - Analyst
Richard Garchitorena - Analyst
Great, thanks. Congrats on all the progress. My first question is on the outlook for '26 and '27. Given you've maintained the production guidance for '26, pretty wide range for the fourth quarter.
很好,謝謝。恭喜各項進展。我的第一個問題是關於 2026 年與 2027 年的展望。鑑於你們維持了 2026 年的產量指引,但第四季的區間相當寬。
Maybe you could talk about where you think you could maybe come in at the high end versus low end across each of your operations in '26 and how they are set up in terms of run rates for -- as you exit fourth quarter into '27?
也許你們可以談談,在 2026 年你們各項營運中,哪些情況下可能落在區間高端或低端?以及在第四季結束、進入 2027 年時,就運轉率(run rate)而言會是怎樣的配置?
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
Thanks, Richard. This is Peter. Thanks. Great question. Thanks for the kind words about the quarter. Eugene, do you want to comment a little bit on the outlook?
謝謝你,Richard。我是 Peter。謝謝。問得很好。也謝謝你對本季的肯定。Eugene,你要不要就展望補充說明一下?
Eugene Lei - President and Chief Financial Officer
Eugene Lei - President and Chief Financial Officer
Yes. Thanks, Richard. We're pleased to reaffirm our production guidance for the year. We're tracking toward the midpoint of both copper and gold production. Pleased to have done that.
是的,謝謝你,Richard。我們很高興重申今年的產量指引。我們目前在銅與黃金產量方面都朝向指引中位數推進。很高興能做到這點。
And as you'll see that after three quarters, we're approximately 75% through the production for the 9 months and on track to meet that.
如你所見,在三個季度之後,我們在前 9 個月的產量已完成約 75%,並按計畫達成目標。
As we look toward 2027, we're looking for increased production in copper. I think as Peter highlighted, the three-year stabilization and optimization program will be complete at Copper Mountain, and we're looking to have about a 25% increase in consolidated copper production in 2027.
展望 2027 年,我們預期銅產量將增加。我想如 Peter 所強調,Copper Mountain 的三年穩定化與最佳化計畫將完成,而我們預期 2027 年合併銅產量將增加約 25%。
We expect our gold production to be around the same levels given the strong outlook and performance that we've seen at our Manitoba operations and the stable operations that we've showed in Peru.
鑑於我們在曼尼托巴營運的強勁展望與表現,以及秘魯營運所展現的穩定性,我們預期黃金產量將大致維持在相同水準。
With the brownfield enhancements, both the third rougher line and the pebble crushers in Peru, we're looking to increase throughput in Peru in 2027, and that's going to, again, help us increase a little bit of that production in copper. So we're really pleased to reaffirm 2026 and '27 looks even brighter for us.
透過棕地增強措施,包括秘魯的第三條粗選(rougher)線與卵石破碎機(pebble crushers),我們預期在 2027 年提高秘魯的處理量,這也將再次幫助我們在銅產量上略有提升。因此,我們很高興重申 2026 年指引,而 2027 年對我們而言看起來更為亮眼。
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
No, I was going to say, Richard, just add to what Eugene has said that obviously, in 2027, the biggest contributor to increased production will be BC and cadence may tilt slightly towards H2.
不,我想說的是,Richard,補充 Eugene 的說法,顯然在 2027 年,產量增加的最大貢獻將來自卑詩省(BC),而產量節奏可能會稍微偏向下半年(H2)。
Richard Garchitorena - Analyst
Richard Garchitorena - Analyst
Okay. Got it. I appreciate that color. And then maybe just as a follow-up on Copper World, congrats on the FID again. On the CapEx, I guess, with the initial growth CapEx of $2.07 billion includes $200 million in scope changes since the 2023 PFS.
好的,了解。謝謝你提供這些補充說明。接著可能再追問一下 Copper World,再次恭喜你們做出最終投資決定(FID)。關於資本支出(CapEx),我想初始成長資本支出 20.7 億美元包含自 2023 年 PFS 以來 2 億美元的範疇變更。
I was wondering if you could just give some color into what the scope changes are within that number and how that potentially could benefit in terms of synergies going forward as you develop Cactus and potentially Mason down the line?
我想請教您是否可以就該數字中範疇變更的內容提供一些說明,以及隨著您推進 Cactus 的開發、並可能在後續推進 Mason,這些變更在未來協同效益方面可能帶來哪些好處?
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
Yes, Richard, so the additional $200 million is pretty well no-regrets changes to the scope. It's money that will be very, very well spent and would avoid significant downtime with respect to future expansion.
好的,Richard,額外的 2 億美元基本上是對範疇進行的、幾乎沒有後悔風險的調整。這筆錢會花得非常、非常值得,並可避免未來擴建時出現顯著的停機時間。
So we've done a lot of -- we're doing a lot of preparatory work for a future expansion that would minimize downtime, which otherwise would take the operation down for weeks or months at a time. The breakdown of the $200 million is roughly $40 million of mine development and bulk earthwork adjustments.
因此我們已經做了很多——也正在做大量——為未來擴建所需的前期準備工作,以把停機時間降到最低;否則可能會讓營運一次停擺數週甚至數月。這 2 億美元的拆分大致為:礦山開發與大規模土方工程調整約 4,000 萬美元。
Then there's about $60 million for the concentrator capital, which is -- includes primary crusher upgrades, some larger cyclone feed pumps, upgraded ball mill, space allocation for the larger grinding circuit, et cetera, that sort of thing.
接著約 6,000 萬美元用於選礦廠資本支出,其中包括一次破碎機升級、更大型的旋流器給料泵、球磨機升級、為更大型磨礦迴路預留空間等等,諸如此類。
And then there's some $50 million included for enhancements to the tailings storage facility and then about $50 million or so in indirects.
另外約 5,000 萬美元用於尾礦庫的強化,還有約 5,000 萬美元左右屬於間接費用。
Operator
Operator
Orest Wowkodaw, Scotiabank.
Orest Wowkodaw,加拿大豐業銀行(Scotiabank)。
Orest Wowkodaw - Analyst
Orest Wowkodaw - Analyst
Good morning.A couple of questions on Copper Mountain, if I could. It sounds like the major repairs or not repairs, upgrades were done in Q3. Can you give us an update on what performance is looking like from a throughput perspective here quarter-to-date in Q4?
早安。我有幾個關於 Copper Mountain 的問題。聽起來主要的維修——或不是維修,是升級——已在第三季完成。能否請您更新一下第四季截至目前(quarter-to-date)的處理量表現如何?
And then I'm wondering if when we think about '27 for Copper Mountain, the 50,000 tonnes a day, is that also sort of second half weighted and we should expect more of a ramp-up of throughput through the first half?
另外我想問,當我們看 Copper Mountain 在 2027 年的目標——每日 50,000 噸——是否也會偏向下半年較多?也就是說,上半年處理量仍會逐步爬坡?
Robert Carter - Chief Operating Officer
Robert Carter - Chief Operating Officer
Yes. Orest, it's Rob Carter here. I can take that. Yes, let's just maybe just replay the quarter just a little bit, right? So the primary SAG was temporarily down for about 33 days in the quarter, right?
是的。Orest,我是 Rob Carter。我來回答。是的,我們先把這一季稍微回顧一下,好嗎?本季一次 SAG 磨機暫時停機大約 33 天,對吧?
So after that, we did see, call it, month-over-month improvements on the ramp-up. September was about 43,500 tonnes per day. And through that process, we've really demonstrated what I call like sprint capacity exceeding more than 50,000 tonnes per day and really several days there.
之後我們確實看到爬坡過程中按月(month-over-month)的改善。9 月大約是每日 43,500 噸。在這個過程中,我們也證明了我所說的「衝刺產能」,有好幾天其實超過每日 50,000 噸。
However, really sustaining this run rate remains a little bit of a challenge for us. And really, the team is focused on operating maintenance and really stabilizing the grinding performance.
不過,要長期維持這個運轉速率對我們來說仍有些挑戰。團隊目前的重點在於運轉維護,以及真正把磨礦表現穩定下來。
And I guess I would say as well is that we're very confident that the mill remains on track to ramp up to its 50,000 tonnes per day going into the end of the year.
另外我也想說,我們非常有信心磨機仍按計畫在年底前爬坡到每日 50,000 噸。
We did have a little bit of planned maintenance and some ball mill liners as well as some screen decks and discharge grates that we kind of struggled with a little bit in October.
10 月我們確實有一些計畫性維護,包括一些球磨機襯板,以及一些篩網甲板(screen decks)和排料格柵(discharge grates),我們在這些項目上有點吃力。
And we really got the cadence here up at the beginning of November. And we truly believe that we've got the right team, the mill is capable of producing this, and we will exit the year around 50,000 tonnes per day. And then when we -- I think the second part of your question was around 2027.
而在 11 月初,我們已把節奏真正拉起來。我們確實相信我們有合適的團隊、磨機也有能力做到,我們將在年底時以約每日 50,000 噸的水準收官。接著——我想你問題的第二部分是關於 2027 年。
So we'll exit the year at 50,000 tonnes per day. We will continue that through all of 2027. And then I think maybe Eugene kind of highlighted a little bit. It is more back-end weighted for grade, right? So North Pit finishes mining here in December.
所以我們會在年底達到每日 50,000 噸。我們會在整個 2027 年持續維持這個水準。然後我想 Eugene 也稍微提到了一點。品位(grade)會比較偏向後段,也就是下半年較多,對吧?North Pit 會在 12 月完成採礦。
We're really back into Pit 3. And the really higher grade of 0.4% and 0.5% really comes in H2 2027. In saying that, though, we do have about 2.5 million tonnes of ore ahead of the crusher here right now, and we've never been in that position before.
我們會真正回到 Pit 3。而 0.4% 與 0.5% 的較高品位,主要會在 2027 年下半年(H2 2027)進來。不過話說回來,我們目前在破碎機前方已經有大約 250 萬噸的礦石堆存,這是我們以前從未有過的狀況。
Orest Wowkodaw - Analyst
Orest Wowkodaw - Analyst
Thank you. I appreciate that. If I could ask a follow-up. Just on -- in Peru and Constancia, the drill results you disclosed today, can you speak more about that in terms of the potential? And I'm just wondering, does that -- does this mean you potentially both extend or could extend the mine life, but also maybe maintain a higher level of copper production for longer than we previously thought?
謝謝。我很感謝這些說明。如果可以我再追問一下。關於秘魯的 Constancia,你們今天披露的鑽探結果,能否就其潛力多談一些?我也想確認,這是否表示你們可能不僅延長——或可延長——礦山壽命,還可能在更長時間內維持比我們先前預期更高的銅產量?
Robert Carter - Chief Operating Officer
Robert Carter - Chief Operating Officer
Yes, I can take that, Orest. I think you kind of hit it there, right? So I would say we're very excited about the 2 exploration holes at Constancia.
是的,Orest,我可以回答。我想你已經點到重點了,對吧?我會說,我們對 Constancia 的兩個探勘孔感到非常振奮。
They intersected really significant core lengths of mineralization in a breccia that's really extending the limits of the current resource at grades that you can see that are much higher than the current reserves that we're mining today. These intersections likely represent a potential new high-grade feeder system, right?
它們在角礫岩(breccia)中穿越了相當顯著的礦化核心長度,這實際上把目前資源量的邊界往外延伸;而且從你看到的品位來看,明顯高於我們目前正在開採的現有儲量品位。這些穿越結果很可能代表一個潛在的新高品位供礦(feeder)系統,對吧?
And that feeder system is really aligned with the main fault structure like the Yanak Fault along the more southwest side of the pit. We've seen some positive reconciliations from mining along this structure due to -- uncovering really pockets of really high-grade skarn that were really not identified in the drilling.
而這個供礦系統與主要斷層構造(例如 Yanak 斷層)在礦坑西南側的走向高度一致。我們也看到沿著這個構造採礦時出現一些正向的對帳(reconciliation)結果,原因在於——我們揭露出一些在鑽探中未被識別的、局部非常高品位的矽卡岩(skarn)礦體。
Yes, and we've got follow-up drilling. It is currently underway. I'd say with further positive assay results from this, we could expect to see an increase in our mineral resource update for Constancia next year.
是的,而且我們已安排後續鑽探。目前正在進行中。我會說,如果後續化驗結果持續正面,我們預期明年 Constancia 的礦產資源量更新中會看到增加。
And I would say we'll take a little bit more time to define the potential reserves and include it in the mine plan, but it definitely has the potential for really long-term production profile and to optimize the mine plan really post 2030 when the grade seems to naturally decrease. So it will really help it to prop it up. And we're very excited about this.
另外我會說,我們還需要多一些時間來界定其潛在儲量並納入礦山計畫,但它確實有潛力改善長期產量曲線,並在 2030 年之後(當品位看起來會自然下降時)進一步優化礦山計畫。因此它將能在那個階段把產量支撐住。我們對此非常興奮。
Orest Wowkodaw - Analyst
Orest Wowkodaw - Analyst
Yes, sounds very promising. Thanks for the update.
是的,聽起來非常有前景。謝謝更新。
Operator
Operator
George Eadie, UBS.
George Eadie,瑞銀(UBS)。
George Eadie - Equity Analyst
George Eadie - Equity Analyst
Hi, Tim. Thanks for the update as well. Just focusing on Copper Mountain a little bit more. So for next year, FY '27, could you give us a bit of a steer of on-site cost here? Year-to-date, I think you're running at around $265 million annualized. How does this look next year? Is it sort of sideways or potentially lower?
嗨,Tim,也謝謝你的更新。我再多聚焦一下 Copper Mountain。針對明年,也就是 2027 財年,你能否就現場成本(on-site cost)給我們一些指引?截至目前(year-to-date),我想你們年化大約在 2.65 億美元左右。明年會是什麼樣子?是大致持平,還是可能更低?
And then also maybe CapEx, thinking sort of $100 million, is that sort of the right level as the stripping campaign wraps up there, too?
另外也想問資本支出(CapEx),如果以大約 1 億美元來看,隨著剝採(stripping)活動也接近收尾,這是否是合理的水準?
Robert Carter - Chief Operating Officer
Robert Carter - Chief Operating Officer
Yes, I can answer that. It's Rob Carter here. Yes, as we go into next year on a mining cost, obviously, mining cost was slightly elevated in Q3. The unit cost, I think, was about $35, something like that. Obviously, there was a fair bit of planned maintenance.
是的,我可以回答。我是 Rob Carter。是的,展望明年的採礦成本,顯然第三季採礦成本略為偏高。單位成本我記得大約是 35 美元左右,差不多是那個水準。很明顯,當季有相當多的計畫性維護。
We had some higher diesel prices and some other equipment maintenance. But as we kind of go into Q4, things are starting to stabilize. So from a unit cost basis, we're roughly somewhere between $20 to $25, and we kind of expect that roughly to be next year as well. And then converting that to really a cash cost. Next year is a very significant year for us on metal production.
我們也遇到柴油價格較高,以及其他一些設備維護。但進入第四季後,情況開始穩定下來。因此以單位成本來看,我們大約落在 20 到 25 美元之間,我們也預期明年大致會是這個水準。接著把它換算成實際現金成本(cash cost)。明年對我們而言將是金屬產量非常顯著的一年。
We will be doubling our metal production in 2027. The cash costs are in line with kind of low $2 type of cash cost really per pound range.
我們將在 2027 年把金屬產量提高一倍。現金成本大致符合每磅約 2 美元左右、偏低的現金成本區間。
Eugene Lei - President and Chief Financial Officer
Eugene Lei - President and Chief Financial Officer
If I could add, with capital coming down, Eugene. There was a significant amount of capital for 2026, both in sustaining capital and the capitalized stripping. That program comes to an end. So you'll see the sustaining cash cost drop significantly to around that $3 per pound level.
Eugene,如果我可以補充一下,隨著資本支出下降。2026 年在維持性資本以及資本化剝採方面都有相當可觀的資本投入。那個計畫將告一段落。因此你會看到維持性現金成本大幅下降,降到每磅約 3 美元左右的水準。
George Eadie - Equity Analyst
George Eadie - Equity Analyst
And sorry, Eugene, what's total CapEx spend at site like $100 million all in? Is that sort of a best guess then?
抱歉,Eugene,現場的總資本支出(CapEx)大概是全部加總約 1 億美元嗎?那這算是目前最好的估計嗎?
Eugene Lei - President and Chief Financial Officer
Eugene Lei - President and Chief Financial Officer
That's a good ballpark. We haven't released the '27 estimate yet. But yes, it's a significant drop from well over $150 million to around $100 million level.
這是個不錯的概略估算。我們還沒公布 2027 年的估算。但沒錯,這會從遠高於 1.5 億美元大幅下降到約 1 億美元的水準。
George Eadie - Equity Analyst
George Eadie - Equity Analyst
Yes. No, that's awesome. I mean things look a lot better at Copper Mountain, so well done. Maybe just one last, Rob, quarter this grade, like your comments before 0.4, 0.5 second half next year, but is sort of 0.3 around the right level today? And sort of how do we think about first half? Is it sort of low 0.3 is the best guess as well?
是的。不,這太棒了。我是說,Copper Mountain 的情況看起來好很多,做得很好。也許最後再問一個,Rob,本季這個品位(grade),你先前提到明年下半年 0.4、0.5,但今天大概 0.3 是否是合理水準?那我們該如何看待明年上半年?是否也可以推測大概是偏低的 0.3 左右?
Robert Carter - Chief Operating Officer
Robert Carter - Chief Operating Officer
Yes. So I think we're referring to grades here at Copper Mountain. I think our average grade in Q3 was about 0.27. Q4, we believe we're going to exit the year around about 0.3, 0.31. We'll likely maintain that 0.3 or just a little bit above for the majority really of the first half of next year and then really move into the 0.4 and 0.5 and further takes us into those type of grades at the first half of 2028 as well.
是的。我想我們這裡指的是 Copper Mountain 的品位。我認為我們第三季的平均品位約為 0.27。第四季,我們相信年底會在約 0.3、0.31 左右收尾。
Operator
Operator
Lawson Winder, Bank of America Merrill Lynch.
Lawson Winder,美國銀行美林。
Lawson Winder - Analyst
Lawson Winder - Analyst
Thanks very much, operator. Good morning, Peter and team, and thank you for today's update. If I could, I'd like to ask about just Copper World and the regulatory environment there. So just with respect to groundwater in Arizona, it was certainly a part of the Democratic platform in the midterms. And obviously, Copper World has its water permit and things are well underway. But can you just speak to water use at the project relative to industry standards and then the proportion of recycled water and how that project stacks up? And then similarly, are there any ongoing permits that are still outstanding needed as work proceeds on that project?
非常感謝,接線員。早安,Peter 與團隊,謝謝今天的更新。如果可以的話,我想問一下 Copper World 以及當地的監管環境。就亞利桑那州的地下水而言,這確實是期中選舉時民主黨政綱的一部分。而且顯然 Copper World 已取得用水許可,相關工作也進展順利。但你們能否談談該專案的用水量相對於產業標準的情況,以及回收水的比例,這個專案的表現如何?同樣地,隨著該專案工作推進,是否仍有任何尚未取得、仍需辦理的許可?
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
Lawson, we have all the permits required to extract groundwater sufficient for the base case at Copper World as well as for the extension case.
Lawson,我們已取得在 Copper World 依基本情境以及延伸情境所需、足以抽取地下水的所有許可。
So we've completed drilling of wells to supply all of this water. We've also voluntarily committed to recharge over 100% of the groundwater that we withdraw for Copper World, and we're using water sourced from outside the region as well. So we've done a bunch of storage in the interim and have actually complied with a significant piece of the commitment already, but we're planning to recharge 105% of the water that we use in the end. So we don't see -- foresee any issues.
因此我們已完成供應所有這些用水所需的水井鑽探。我們也自願承諾,對於 Copper World 所抽取的地下水,回補(recharge)量將超過 100%,而且我們也使用來自該區域以外的水源。因此我們在過渡期間已做了大量儲存,且其實已經履行了相當一部分承諾;但最終我們計畫回補 105% 的用水量。所以我們不認為——也不預期會有任何問題。
Lawson Winder - Analyst
Lawson Winder - Analyst
And in terms of ongoing permits to proceed construction, I mean do you have everything in hand that you could possibly need to get the project right through to commercial production?
那就持續推進施工所需的許可而言,我是說,你們是否已經把所有可能需要的許可都拿到手,足以讓專案一路推進到商業化生產?
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
We have all of the primary permits that we need to get through to commercial production. There are the odd little construction permits here and there that are required from local authorities and things. But in general, we have all of the permits in place to proceed with construction.
我們已取得推進到商業化生產所需的所有主要許可。當然,仍有零星一些施工許可需要向地方主管機關等單位申請。但整體而言,我們已具備推進施工所需的所有許可。
Lawson Winder - Analyst
Lawson Winder - Analyst
Okay. Understand. That's great. And then maybe putting the cart ahead of the horse just a little bit here, but the model for Copper World here was to get the project well along to, or at least close to a sanctioning decision and then finalize a partnership for that. I mean when you think about Cactus and Mason, is that type of partnership profile something that you guys would consider with those assets? I guess I'll just leave the question there.
好的,了解。很棒。接下來也許有點本末倒置、先把車放在馬前面,但 Copper World 的模式是把專案推進到、或至少接近核准投資(sanctioning)決策,然後再敲定合作夥伴。那你們在看 Cactus 和 Mason 時,是否也會考慮採用類似的合作夥伴模式?我想我就先把問題留在這裡。
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
In general, the base case for Cactus is we have the capacity to be able to fund it ourselves. So for the next couple of years, in any case, we're looking at spending about $30 million a year, concluding the studies, the study work that we need to do on the PFS side and the DFS side. We have no plans at the moment to enter into a JV, but it certainly is something that we could consider in the future, depending on what the needs for capital are on a risk-adjusted basis. But base case is we'll do it ourselves. But we do know that it's regarded very highly by many of the counterparties with whom we had discussions with respect to Copper World.
一般而言,Cactus 的基本情境是我們有能力自行出資。因此在接下來幾年,無論如何,我們預計每年投入約 3,000 萬美元,用於完成我們在 PFS 與 DFS 階段所需的研究與工作。目前我們沒有進行合資(JV)的計畫,但未來當然也可能視風險調整後的資本需求而考慮。但基本情境是我們會自己做。不過我們也知道,就 Copper World 相關討論而言,許多與我們接觸的對手方都對它評價很高。
Lawson Winder - Analyst
Lawson Winder - Analyst
Those are both very helpful answers. I appreciate the color.
這兩個回答都非常有幫助。感謝你提供的補充說明。
Operator
Operator
Charles Ehidiamhen, Jefferies.
Charles Ehidiamhen,Jefferies。
Charles Ehidiamhen - Analyst
Charles Ehidiamhen - Analyst
Thank you for taking my question. So I'm asking on behalf of Fahad. So maybe my first question is on the LSIB judicial review. Can you clarify the specific grounds of the challenge and the remedy being sought? I mean, I appreciate that you remain confident that the permits would be upheld, but if for any reason, the court doesn't rule in your favor, what's the realistic downside here? Is there like a potential delay to 2028 first production or permit and maintenance? Just any color on that would be helpful.
謝謝讓我提問。我是代 Fahad 提問。我第一個問題是關於 LSIB 的司法覆核(judicial review)。你能否釐清挑戰的具體理由(grounds)以及所尋求的救濟(remedy)是什麼?我理解你們仍有信心許可會被維持,但如果基於任何原因法院沒有做出對你們有利的裁定,實際可能的下行風險是什麼?例如是否可能導致 2028 年首次投產延後,或是許可與維護方面的影響?任何補充說明都會很有幫助。
Robert Carter - Chief Operating Officer
Robert Carter - Chief Operating Officer
Yes, I can answer that, Charles. It's Rob here. So the Lower Similkameen Indian Band filed an application for a judicial review in March of 2026. This is really regarding the provincial government's administrative decision related to issue the permit amendment and really the consultation process. So Hudbay is part of this -- or participating in this process, and we're supporting the province's regulatory process really as well.
好的,我可以回答,Charles。我是 Rob。Lower Similkameen Indian Band 在 2026 年 3 月提出司法覆核申請。這主要是針對省政府與核發許可修正相關的行政決定,以及諮詢程序。因此 Hudbay 也是此程序的一部分——或說參與其中,我們也在支持省政府的監管程序。
So the permit remains in effect today. We've got active dialogue with LSIB and Upper Similkameen Indian Band as well as part of our participation agreement mechanisms. Construction activities continue to advance, and we remain confident in the regulatory process. And we really expect the court to uphold that decision at a hearing that's anticipated in the first quarter of next year, right? So like I said, we maintain an active relationship.
因此該許可目前仍然有效。我們也與 LSIB 以及 Upper Similkameen Indian Band 保持積極對話,這也是我們參與協議(participation agreement)機制的一部分。施工活動持續推進,我們對監管程序仍有信心。我們確實預期法院會在預計於明年第一季舉行的聽證會上維持該決定,對吧?所以如我所說,我們維持積極的關係。
We're engaged constructively having our mechanisms that we have as our participation agreement as part of our joint committees that we have with Upper and Lower. And yes, we believe the process will be upheld.
我們以建設性的方式參與,透過我們的參與協議機制,以及我們與 Upper 與 Lower 共同設立的聯合委員會。是的,我們相信該程序會被維持。
Charles Ehidiamhen - Analyst
Charles Ehidiamhen - Analyst
Okay, thank you. Just second question on Copper World here. I think there was some news recently about the Senate advancing the permitting reform bill. I'm just curious if this change -- whether this change could change the way you're thinking about Copper World longer term?
好的,謝謝。第二個問題是關於 Copper World。我想最近有一些消息提到參議院推進了許可改革法案。我只是好奇,這項變化是否會改變你們對 Copper World 長期規劃的看法?
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
This is Peter. Not really. The primary point is that we only require state permits for Copper World Phase 1. If the regulatory environment changes with respect to the legislation that is underway right now and it proceeds on the basis that it's currently proposed, I think it may be helpful with respect to advancing Phase 2 at the time, but we have plenty, plenty of time in order to be able to advance Phase 2. And if you look at precedent, other companies who have received permits to expand on to -- three companies have received permits to expand on to federal land for expansion phases, the typical amount of time taken is about 4 years.
我是 Peter。不完全是。重點是,Copper World 第 1 期我們只需要州政府的許可。如果目前正在推進的立法所涉及的監管環境發生變化,且最終依照目前提出的方案通過,我認為屆時可能有助於推進第 2 期,但我們有非常、非常充裕的時間來推進第 2 期。而且如果你看先例,其他公司在擴建階段獲准擴展到聯邦土地上——有三家公司獲得了在聯邦土地上擴建的許可——通常所需時間大約是 4 年。
So we're not considering expanding on to private land for quite a while. So we have plenty of time ahead of us. So there is no real impact of this legislation, although we think if it passes in its current form, it will be marginally positive for the project going down the road.
所以我們在相當長一段時間內都不會考慮擴展到私人土地上。因此我們前面還有充裕的時間。所以這項立法並沒有實質影響,不過我們認為如果以目前的形式通過,長遠來看對該專案會有些微正面作用。
Charles Ehidiamhen - Analyst
Charles Ehidiamhen - Analyst
Thank you. That's all I had.
謝謝。我就這些。
Operator
Operator
Martin Pradier, Veritas.
Martin Pradier,Veritas。
Martin Pradier - Analyst
Martin Pradier - Analyst
I have two questions. The first one is on Chile and a little bit -- you're installing the pebble crushers would be a lot of downtime in the quarter. Does this have a ramp-up time or is quick once it is installed? And then the last thing on that one is some update on the satellite deposits that you have been talking about in the past. And in terms of Copper World, how much of the workforce has been mobilized? And when does the construction start and if you have the equipment on site to start construction?
我有兩個問題。第一個是關於智利,還有一點——你們正在安裝卵石破碎機,這會讓本季有很多停機時間。這個有爬坡期嗎?還是安裝完成後就能很快上線?另外,想請你們更新一下過去提到的衛星礦床的進展。至於 Copper World,目前動員了多少人力?何時開始施工?以及你們是否已經把設備運到現場、可以開始施工?
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
Sure, Martin. So the first question was with respect to pebble crushers in Peru. We expect to commission those this month. We don't expect there to be any downtime associated with the commissioning because you're literally just turning on a switch and feeding into the milling circuit. And we expect the contribution of those pebble crushers to be in place before the end of the year.
當然可以,Martin。第一個問題是關於秘魯的卵石破碎機。我們預期本月會進行試車投運(commission)。我們不預期試車投運會造成任何停機,因為基本上就是把開關打開,然後把物料送入磨礦迴路。我們預期卵石破碎機的貢獻會在年底前到位。
On the satellite deposits, you heard we spoke a little bit about the drilling success that we've had in the Constancia pit itself. So that's on the one hand, is a further source of potential production post 2030. On Maria Reyna and Caballito, we are still going through the permitting process. We still do not have the prior consultation permits in hand, and those are unlikely to be touched during the remainder of this year, while local elections are underway. Once local elections are underway, we'll get back to it, and we should have an update on that sometime later on next year.
關於衛星礦床,你們也聽到我們稍早提到在 Constancia 礦坑本體的鑽探成果。這一方面是 2030 年之後潛在產量的進一步來源。至於 Maria Reyna 和 Caballito,我們仍在走許可流程。我們目前仍未取得事前諮商(prior consultation)的許可,而且在今年剩餘時間內,因為地方選舉正在進行,這些許可不太可能有進展。等地方選舉結束後,我們會再回到這項工作,並且應該會在明年稍晚的某個時間點提供更新。
Your third question with respect to Copper World and the workforce. So from an operating perspective or from the operating company, we have roughly 180 people out of 220 or so that will be required by the end of the year. On the construction side, we have commitments for all of the primary long lead equipment that are required, such as SAG mills, ball mills, the gearless drives, et cetera. We have made commitments on the trucks that we require or the trucking fleet that we will require. And then with progress itself in the field, we are in the process of installing the water pipeline.
第三個問題是關於 Copper World 與人力。就營運面或營運公司而言,到年底所需的人力大約是 220 人左右,目前我們已經有約 180 人。在施工方面,我們已就所有主要的長交期設備做出承諾,例如 SAG 磨機、球磨機、無齒輪驅動系統(gearless drives)等等。我們也已就所需卡車或車隊做出承諾。至於現場進度,我們正在安裝輸水管線。
We have all of that material on site right now. I think we're about 60% complete with the water pipeline. So things are underway. We will ramp up the construction workforce as is required and reflected in the construction schedule. We've seen no problems doing that so far.
目前所有材料都已在現場。我想輸水管線大約完成了 60%。所以工作已經在進行中。我們會依照施工進度表的需求,逐步擴增施工人力。到目前為止,我們在這方面沒有看到任何問題。
Operator
Operator
Anita Soni, CIBC World Markets.
Anita Soni,CIBC World Markets。
Anita Soni - Analyst
Anita Soni - Analyst
Good morning, and thanks for taking my questions, and thank you for all the color that you provided on operating outlook for each of the assets. If I could ask about recovery rates, starting with Peru. I'm wondering how recovery rates will look in Q4 and 2027 for copper recovery.
早安,謝謝你們回答我的問題,也謝謝你們就各項資產的營運展望提供了很多細節。我想問一下回收率,先從秘魯開始。我想了解第 4 季以及 2027 年的銅回收率會是什麼樣的表現。
Robert Carter - Chief Operating Officer
Robert Carter - Chief Operating Officer
Yes, I can answer that, Anita. It's Robert. Yes, it's -- I think Peter kind of touched on a little bit in the discussion earlier on about the third rougher flotation line. So that came in place or was commissioned roughly in September, and we immediately saw about a 2% uplift, right, from the recovery model that we were predicting, right? So we've continued to take that through in October.
好的,我可以回答,Anita。我是 Robert。是的——我想 Peter 先前在討論第三條粗選浮選線(third rougher flotation line)時有稍微提到。那條線大約在 9 月投運,我們立刻看到相較於我們原先預測的回收率模型,大約提升了 2%,對吧?所以我們在 10 月也持續維持這個表現。
We've seen some pretty good recoveries kind of in the mid-80% range, right? And then along with that, right, so helping us through on the capacity side of things as we complete our ramp-up this year to achieve approximately like 93,000 tonnes per day going into next year, right, we've got 34 million tonnes per annum. The pebble crushers are going to help further kind of support that. And we believe we're going to be roughly in from a recovery basis, really around that 84% to 85% recovery.
我們看到相當不錯的回收率,大概在 80% 中段的水準,對吧?此外,隨著我們今年完成產能爬坡、在明年以前達到約每日 93,000 噸(約每年 3,400 萬噸)的處理量,這也有助於產能面。卵石破碎機也會進一步支撐這一點。我們認為就回收率而言,大致會落在約 84% 到 85% 左右。
Anita Soni - Analyst
Anita Soni - Analyst
All right. That's what I was driving at because I think that's what I have in my model and Q3 was a little light. And then just going to BC, a similar question in terms of the recovery rate profile. Now that you're looking to exit the year at higher processing rate, how would that impact the recovery rate?
了解。我之所以這樣問,是因為我模型裡大概就是這個數字,而第 3 季稍微偏低。接著談到卑詩省(BC),也有一個類似的問題:回收率的走勢。既然你們預期年底時會以更高的處理量收尾,這會如何影響回收率?
Robert Carter - Chief Operating Officer
Robert Carter - Chief Operating Officer
Yes. Let's talk maybe just a little bit about it. I think we had -- the quarter was roughly 79% or 80% kind of on recovery. Obviously, those can fluctuate with the different ore types. I talked a little bit earlier is that there's some ore that's coming in from North Pit, a little bit softer, right, a little bit of different recovery metrics from that and really from really Pit 3, right?
好的。我們稍微談一下。我想本季回收率大約是 79% 或 80%。當然,回收率會隨不同礦石類型而波動。我先前也提到,有一部分礦石來自 North Pit,質地比較軟一些,對吧?它的回收率指標會和 Pit 3 的礦石有所不同。
So we expect to be in a very similar range for recoveries in Q4. And then as we enter next year, I think everybody notices recovery grade models, the grade increases, generally recovery increases there as well. So we're looking at somewhere for budgeting somewhere between about 81% to 83% recoveries for next year.
所以我們預期第 4 季的回收率會在非常相近的區間。到了明年,我想大家也都注意到在回收率/品位模型中,品位上升通常也會帶動回收率上升。因此我們在明年的預算上,回收率大概抓在約 81% 到 83% 之間。
Anita Soni - Analyst
Anita Soni - Analyst
Okay. And then just lastly, on the gold side of the equation in Peru, I noticed you still have your guidance of 15,000 to 20,000 ounces, but I think you're almost there. So is there -- with 3 quarters. So is there a reason why you just kept the gold guidance where it's at, it looks like you'll probably exceed it? Or is it just not material enough for you to worry about?
好的。最後一個問題,關於秘魯的黃金。我注意到你們的指引仍是 15,000 到 20,000 盎司,但我想你們幾乎已經達到了,而且才過了三個季度。所以你們把黃金指引維持不變,是有什麼原因嗎?看起來你們可能會超過。還是說對你們而言不夠重要,所以不特別調整?
Robert Carter - Chief Operating Officer
Robert Carter - Chief Operating Officer
Yes. I don't know, maybe it's too material. I can kind of maybe answer that maybe a little quicker. Obviously, we're very pleased with the gold performance really year-to-date. And as of October month end, we have already exceeded the top end of the guidance for gold.
是的。我不確定,或許是太重要了。我可以簡短回答一下。顯然我們對今年迄今的黃金表現非常滿意。截至 10 月底,我們的黃金產量已經超過指引區間的上緣。
Anita Soni - Analyst
Anita Soni - Analyst
Okay. So no reason to expect any kind of change from your year-to-date performance on gold?
了解。所以沒有理由預期黃金表現會偏離你們今年迄今的趨勢?
Robert Carter - Chief Operating Officer
Robert Carter - Chief Operating Officer
No.
沒有。
Anita Soni - Analyst
Anita Soni - Analyst
Thank you. That's it for my question.
謝謝。我的問題就到這裡。
Operator
Operator
Rodrigo Gotardo, BTG Pactual.
Rodrigo Gotardo,BTG Pactual。
Rodrigo Gotardo - Analyst
Rodrigo Gotardo - Analyst
Good morning, Peter and Kim. Thanks for the opportunity. I have two questions on my side. First one, it's on regards to capital allocation. We now see Hudbay in a very comfortable net cash position. And despite having all these attractive growth projects ahead, we see Hudbay well positioned to fund this growth pipeline, especially with the structure on Copper World and so. So given the supportive balance sheet and the supportive metal prices, do you see room for some opportunistic M&A?
早安,Peter 和 Kim。感謝給我這個機會。我這邊有兩個問題。第一個是關於資本配置。我們現在看到 Hudbay 的淨現金部位非常充裕。儘管前方有這些具吸引力的成長專案,我們仍看到 Hudbay 具備良好條件為這條成長管線提供資金,尤其是 Copper World 的架構等等。因此,在資產負債表穩健以及金屬價格有利的情況下,您是否認為有空間進行一些機會型的併購(M&A)?
If yes, do you have some preferences for commodities or jurisdictions? Also on this capital allocation profile, do you see some room for more meaningful shareholder remuneration given all the supportive backdrop? That's my first question.
如果有的話,您對商品或司法管轄區是否有偏好?另外就這個資本配置輪廓而言,在整體環境支持下,您是否認為有空間進行更具意義的股東回饋?這是我的第一個問題。
Peter Kukielski - President, Chief Executive Officer, Director
Peter Kukielski - President, Chief Executive Officer, Director
Hi, Rodrigo, it's Peter. Thanks for the question. Look, I think that, as you know, we have an attractive pipeline of high-return brownfield and greenfield opportunities, and we are focused on allocating capital to the highest risk-adjusted return opportunities. As you indicate, the strength of the balance sheet plus the proceeds from the JV transaction positions us very well to continue to allocate capital to advance these high-quality organic initiatives and to create value. On the inorganic side, what I would say is that we continue to look for opportunities that meet our very, very stringent criteria.
嗨,Rodrigo,我是 Peter。謝謝你的提問。你也知道,我們有一條具吸引力、回報率高的棕地與綠地機會管線,我們專注於把資本配置到風險調整後回報最高的機會上。如你所指出,資產負債表的強勁加上合資(JV)交易的收益,使我們非常有利於持續配置資本、推進這些高品質的有機計畫並創造價值。至於非有機方面,我想說的是,我們仍持續尋找符合我們非常、非常嚴格標準的機會。
We've got a very skilled team when it comes to highly efficient operations and world-class development projects. But our strategy hasn't changed, and we will continue to be disciplined as we evaluate assets that fit our strategic and financial criteria. We know that copper assets are scarce. We would only pursue opportunities that are accretive and value creating for shareholders. So yes, it's very, very difficult to find these things, but we certainly continue to look.
我們在高效率營運與世界級開發專案方面擁有非常熟練的團隊。但我們的策略沒有改變,我們在評估符合我們策略與財務標準的資產時,將持續保持紀律。我們知道銅資產很稀缺。我們只會追求能增厚(accretive)並為股東創造價值的機會。所以,是的,這些機會非常、非常難找,但我們確實會持續尋找。
And if something came up that met those criteria, we would certainly consider it. Our focus would be entirely on copper, though.
如果出現符合這些標準的標的,我們當然會考慮。不過,我們的重點會完全放在銅上。
Eugene Lei - President and Chief Financial Officer
Eugene Lei - President and Chief Financial Officer
Rodrigo, it's Eugene Lei here. With respect to capital returns, as Peter highlighted, we have a very holistic capital allocation framework that allows us to make -- allocate capital to highest risk-adjusted returns. And this allows us to not only develop the Copper World with low leverage without the requirement for hedging and for -- to put the balance sheet at risk while making generational investments in the brownfields projects across our entire platform. We're in a privileged position to be able to also reduce debt and target a net debt-to-EBITDA level below 1x throughout this development cycle. We think this is a low-risk way for us to have prudent growth, balanced growth, and we expect to continue to do so.
Rodrigo,我是 Eugene Lei。關於資本回饋,如 Peter 所強調,我們有一個非常全面的資本配置框架,使我們能夠將資本配置到風險調整後回報最高的項目上。這讓我們不僅能在低槓桿、無需避險的情況下開發 Copper World,也不必為了這些投資而讓資產負債表承擔風險,同時在我們整個平台的棕地專案上進行具世代意義的投資。我們也處於一個有利位置,能夠降低負債,並在整個開發週期中將淨負債對 EBITDA 的水準維持在 1 倍以下。我們認為這是一種低風險方式,讓我們能夠審慎成長、平衡成長,我們也預期會持續如此。
As we look forward into 2027, we expect strong free cash flow generation from our 3 operating assets. We have some growth capital ahead of us in terms of Copper World and advancing both brownfield projects in Manitoba and Peru and BC, but also advancing Mason and Cactus, the recently acquired project. And so I think that is our focus. But as we have excess cash flow and no lack of opportunity, we'll look at shareholder returns. You will notice that we had increased our dividend earlier this year for the first time in Hudbay's history, and that's with an eye to long-term sustainable returns to shareholders, and we're beginning to be able to look at that at the same time as allocating capital to our projects.
展望 2027 年,我們預期三個營運資產將帶來強勁的自由現金流。在 Copper World 以及推進曼尼托巴、秘魯與卑詩省(BC)的兩個棕地專案方面,我們前方仍有一些成長資本需求,同時也會推進 Mason 與 Cactus 這個近期收購的專案。因此我認為這就是我們的重點。但當我們有超額現金流且機會不虞匱乏時,我們也會檢視股東回饋。你會注意到,我們今年稍早在 Hudbay 歷史上首次提高股利,這是著眼於對股東的長期可持續回報;我們也開始能在配置資本到各專案的同時,兼顧這一點。
And so I think this is a prudent way to advance the company and to grow the company, and we look forward to being a sustainable dividend payer once Copper World is complete, that we're starting that even earlier than we expected today.
因此我認為,這是一種審慎推進公司並讓公司成長的方式;我們也期待在 Copper World 完成後成為一個可持續配息的公司,而我們今天甚至比原先預期更早開始朝這個方向前進。
Rodrigo Gotardo - Analyst
Rodrigo Gotardo - Analyst
That's very clear. My second question goes in regards to the other 2 projects. So we now expect the PFS on Cactus and Mason in the second half of next year. So could you share with us how is it advancing some of your findings on this project, especially how do you see the current findings on these studies versus the previous numbers published on the technical reports? Thank you guys.
非常清楚。我的第二個問題是關於另外兩個專案。所以我們現在預期 Cactus 和 Mason 的 PFS(預可行性研究)會在明年下半年出爐。您能否與我們分享這些專案目前的推進情況與一些發現,特別是這些研究的目前發現與先前技術報告中公布的數字相比如何?謝謝各位。
Eugene Lei - President and Chief Financial Officer
Eugene Lei - President and Chief Financial Officer
Thank you for your question. We're really pleased with our acquisition of Cactus and our due diligence findings prior to acquisition have proven to be consistent with what we've seen with the project and the team 3 months into ownership. We are running trade-off studies on a number of the assumptions that we had made and also doing some tollgate work on a lot of the feasibility work that the team has advanced. So all this comes together into an updated Hudbay pre-feasibility study for the project. We're well underway on that.
謝謝你的提問。我們對收購 Cactus 感到非常滿意,而我們在收購前的盡職調查結果,已證明與我們在取得所有權三個月後對該專案及團隊所看到的情況一致。我們正在針對多項先前假設進行取捨研究(trade-off studies),同時也對團隊已推進的許多可行性工作進行階段性審查(tollgate work)。這些將整合成該專案更新後的 Hudbay 預可行性研究。我們已經在積極推進中。
I think there's over 16 trade-off studies we're doing there, and we're excited to move that project forward. The time line for that is to take -- is to issue a pre-feasibility study in the third quarter next year and then move into a feasibility study that will take roughly a year with some of those opportunities more fleshed out for potential FID by the end of 2028. And that is the target for Cactus, and we're really on track with that and building the team, taking some of the team members who had been doing sort of the technical work and engineering work at Copper World and applying them to Cactus, but also building out an independent team at Cactus so that it's ready for FID in about 1.5 years' time.
我想我們在那裡正在做超過 16 項取捨研究,我們很期待推動該專案向前。時程方面,我們的目標是在明年第三季發布預可行性研究,接著進入可行性研究,約需一年時間,並把其中一些機會更充分地細化,以期在 2028 年底前達成潛在的 FID(最終投資決策)。這就是 Cactus 的目標;我們確實按計畫推進,同時也在擴編團隊,把部分原本在 Copper World 進行技術與工程工作的成員調配到 Cactus,但也在 Cactus 建立一支獨立團隊,使其在約 1.5 年後能準備好進行 FID。
At the same time, with a totally separate team, we're advancing the Mason project in Nevada. And that pre-feasibility study is now about 47% complete.
同時,我們以一支完全獨立的團隊推進內華達州的 Mason 專案。而該預可行性研究目前約完成 47%。
We're really excited to have another option for our growth in the United States, and we're really refreshing the study that was last done in 2021 and taking into account a lot of the lessons that we've learned as we've gone through the full PEA to feasibility process with Copper World. And we're building out a very significant US regional team that's going to support all 3 of the projects and really be a cornerstone of Hudbay's growth for the next decade.
我們很高興在美國又多了一個成長選項;我們正在更新上一次於 2021 年完成的研究,並納入我們在 Copper World 從完整的 PEA(初步經濟評估)到可行性研究流程中所學到的許多經驗。我們也正在建立一支規模相當可觀的美國區域團隊,將支援這三個專案,並真正成為 Hudbay 未來十年成長的基石。
Rodrigo Gotardo - Analyst
Rodrigo Gotardo - Analyst
Okay, that's clear. Thank you, gentlemen.
好的,很清楚。謝謝兩位先生。
Operator
Operator
This concludes the question-and-answer session. I'd like to turn the conference back over to Candace Brule for any closing remarks.
問答環節到此結束。我想把會議交回給 Candace Brule,請她做任何結語。
Candace Brule - Senior Vice President of Capital Markets & Corporate Affairs
Candace Brule - Senior Vice President of Capital Markets & Corporate Affairs
Thank you, operator, and thank you, everyone, for joining us today. If you have any further questions, please feel free to reach out to our Investor Relations team. Thanks, and have a great day.
謝謝主持人,也謝謝各位今天加入我們。如果您還有任何進一步問題,歡迎隨時聯繫我們的投資人關係團隊。謝謝,祝各位有美好的一天。
Operator
Operator
This brings to a close today's conference call. You may disconnect your lines. Thank you for participating, and have a pleasant day.
今天的電話會議到此結束。您可以掛斷電話線。感謝您的參與,祝您有愉快的一天。