  • Operator

    Operator

  • Good afternoon. Thank you for attending the Babcock & Wilcox Enterprises fourth quarter and full-year 2025 conference call. (Operator Instructions)

    午安.感謝您參加巴布科克-威爾科克斯企業2025年第四季及全年業績電話會議。(操作說明)

  • I would now like to turn the conference over to your host, Sharyn Brooks, B&W's Director of Communications. Thank you. You may proceed, Ms.

    現在我謹將會議交給主持人,B&W 通訊總監 Sharyn Brooks。謝謝。您可以繼續了,女士。

  • Brooks.

    布魯克斯。

  • Sharyn Brooks - Director of Communications

    Sharyn Brooks - Director of Communications

  • Thank you, Tamita, and thanks to everyone for joining us on Babcock & Wilcox Enterprises Fourth Quarter and Full Year 2025 Earnings Conference Call. I'm Sharyn Brooks, Director of Communications. Joining the call today are Kenny Young, B&W's Chairman and Chief Executive Officer; and Cameron Frymyer, Chief Financial Officer, to discuss our fourth quarter and full-year results.

    謝謝 Tamita,也謝謝大家參加 Babcock & Wilcox Enterprises 2025 年第四季及全年財報電話會議。我是傳播總監莎琳‧布魯克斯。今天參加電話會議的有 B&W 董事長兼執行長 Kenny Young 和財務長 Cameron Frymyer,他們將討論我們第四季和全年的業績。

  • During this call, certain statements we make will be forward-looking. These statements are subject to risks and uncertainties, including those set forth in our safe harbor provision for forward-looking statements that can be found at the end of our earnings press release published on March 4, 2026, and in our annual report on Form 10-K that has been filed with the SEC today.

    在本次電話會議中,我們所做的某些陳述將具有前瞻性。這些聲明存在風險和不確定性,包括我們在 2026 年 3 月 4 日發布的盈利新聞稿末尾以及今天向美國證券交易委員會提交的 10-K 表格年度報告中所列的前瞻性聲明安全港條款。

  • Additionally, except as required by law, we undertake no obligation to update any forward-looking statements. We also provide non-GAAP information regarding certain of our historical and targeted results to supplement the results provided in accordance with GAAP. This information should not be considered superior to or as a substitute for the comparable GAAP measures.

    此外,除法律要求外,我們不承擔更新任何前瞻性聲明的義務。我們還提供有關我們某些歷史業績和目標業績的非GAAP信息,以補充根據GAAP提供的業績。此資訊不應被視為優於或取代相應的GAAP指標。

  • A reconciliation of historical non-GAAP measures can be found in our fourth quarter and full year 2025 earnings release published on March 4, 2026, and in our company overview presentation filed on Form 8-K, which is posted on the Investor Relations section of our website at babcock.com. I will now turn the call over to Kenny.

    有關歷史非GAAP指標的調整說明,請參閱我們於2026年3月4日發布的2025年第四季及全年收益報告,以及我們以8-K表格提交的公司概況介紹,該介紹已發佈在我們網站babcock.com的投資者關係欄位中。現在我將把電話交給Kenny。

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • Thanks, Sharyn. Well, good afternoon, everyone, and thank you for joining us on our fourth quarter and full-year 2025 earnings call.

    謝謝你,莎琳。大家下午好,感謝各位參加我們2025年第四季及全年財報電話會議。

  • Over the past year, Babcock & Wilcox has seen significant growth due to higher demand in electrical generation. Our company has reached a new pinnacle, which combined with recent announcements, allows us to increase our 2026 adjusted EBITDA target range to between $80 million and $100 million. Our core business, excluding data centers, continued to grow as our parts and services saw elevated demand from the increased operation of baseload generation in North America and beyond.

    過去一年,由於電力生產需求增加,巴布科克-威爾科克斯公司實現了顯著成長。我們公司已達到新的巔峰,加上最近發布的公告,使我們能夠將 2026 年調整後的 EBITDA 目標範圍提高到 8,000 萬美元至 1 億美元之間。除了資料中心外,我們的核心業務持續成長,因為隨著北美及其他地區的基荷發電量增加,我們的零件和服務需求也隨之提高。

  • As energy needs continue to expand from consumers, industries and data centers that utilize grid power, coal plants are being reconditioned and reengaged by utilities to help meet that accelerating demand. Existing coal plants in the US have been operating at less than 50%, and these power plants have untapped capacity that is starting to be used to support the increased power demand.

    隨著消費者、工業和資料中心對電網電力的需求不斷增長,公用事業公司正在對燃煤電廠進行改造和重新啟用,以幫助滿足不斷增長的需求。美國現有的燃煤電廠的運作率一直低於 50%,這些電廠還有未開發的產能,現在正開始利用這些產能來滿足不斷增長的電力需求。

  • As natural gas prices climb, the cost of coal operations has become more attractive, which translates into greater use of Parts and Services as well as upgrades and enhancements, all of which increased demand for our core business. Our Parts and Services revenues grew by over 17% in 2025, and we saw growth continuing in 2026 as well.

    隨著天然氣價格上漲,煤炭營運成本變得更具吸引力,這意味著零件和服務的使用量增加,以及升級和改進的增加,所有這些都增加了對我們核心業務的需求。2025年,我們的零件和服務收入成長超過17%,我們預計2026年也將持續成長。

  • As a reminder, the majority of our parts, services and small upgrade revenues are not in our backlog as the book-to-bill cycle is much quicker than longer-term projects. The increasing demand for power in North America serves as a catalyst for B&W's continued growth, positioning us to play a pivotal role in supporting AI data center expansion and increased baseload generation needs in the years ahead.

    需要提醒的是,我們的大部分零件、服務和小額升級收入並不在我們的積壓訂單中,因為從預訂到開票的周期比長期項目要快得多。北美地區日益增長的電力需求推動了B&W的持續成長,使我們能夠在未來幾年為支援人工智慧資料中心擴張和不斷增長的基礎負載發電需求發揮關鍵作用。

  • Our recent announcement of a full notice or full approval to proceed on our project with Base Electron is an exciting step forward into the AI data center space. Our agreement with Base Electron backed by Applied Digital is valued at $2.4 billion and is intended to deliver 1.2 gigawatts of electricity that will be directly connected to the grid in support of AI factory campuses.

    我們最近宣布已獲得全面通知或全面批准,可以與 Base Electron 開展我們的項目,這是我們在人工智慧資料中心領域邁出的激動人心的一步。我們與 Applied Digital 支援的 Base Electron 達成的協議價值 24 億美元,旨在提供 1.2 吉瓦的電力,這些電力將直接併入電網,以支援人工智慧工廠園區。

  • Combining steam turbines with our previously designed and engineered 300-megawatt boilers enables us to eliminate months of initial development work that is required with typical new boiler projects.

    將蒸汽渦輪機與我們先前設計和製造的 300 兆瓦鍋爐相結合,可以省去典型的新鍋爐專案所需的數月初始開發工作。

  • Overall, this can help accelerate a standard delivery schedule by up to a year. Site visits are now underway, and we've started the boiler manufacturing process. Siemens Energy has started the fabrication process of the turbines and work is scheduled to commence at the site later this year, with most of the construction, including civil and mechanical scheduled for 2027 and 2028.

    總體而言,這可以幫助將標準交付週期縮短最多一年。目前已開始現場考察,鍋爐製造過程也已啟動。西門子能源公司已開始渦輪機的製造過程,預計今年稍後在現場開工,大部分建設工作(包括土木工程和機械工程)計劃於 2027 年和 2028 年進行。

  • We are also working closely with the boiler maker union to ready the labor force needed at peak periods throughout this project. Currently, just over $430 million of this contract is fixed price, specifically the boilers and the steam turbines, while the remaining work is covered under a cost-plus approach.

    我們也與鍋爐製造商工會密切合作,為專案高峰期所需的勞動力做好準備。目前,該合約中超過 4.3 億美元為固定價格,具體包括鍋爐和蒸汽渦輪機,其餘部分則採用成本加成方式。

  • Applied Digital is backstopping the contract with a guarantee of full and timely performance of all of Base Electron's obligations. Base Electron has also indicated its interest in purchasing another 1.2 gigawatts of power from B&W, possibly at a different location. The impact of this contract on B&W is truly profound, and we have now added $3 billion to $5 billion in additional AI data center opportunities to our portfolio.

    Applied Digital 為該合約提供擔保,保證 Base Electron 全面、及時地履行其所有義務。Base Electron 也表示有興趣從 B&W 購買另外 1.2 吉瓦的電力,可能位於不同的地點。這份合約對 B&W 的影響非常深遠,我們現在為我們的投資組合增加了價值 30 億至 50 億美元的人工智慧資料中心機會。

  • We believe our proven technologies are well positioned to deliver the reliable, high-capacity power generation that is required to meet the growing demands of power grid today. Furthermore, we are in real-time discussions with additional data center customers around specific opportunities.

    我們相信,我們成熟的技術能夠提供可靠的、高容量的發電,以滿足當今電網日益增長的需求。此外,我們正在與更多資料中心客戶就具體合作機會進行即時洽談。

  • A few of these are actively underway right now, and we hope to be able to issue further announcements and details in the coming weeks. These potential projects with other developers, hyperscalers and utilities, if booked, will also utilize B&W boiler designs in combination with steam turbines. As a result, and even after converting $2.4 billion of our pipeline to backlog, these new opportunities are now reflected in our current pipeline of over $12 billion.

    其中一些項目目前正在積極進行中,我們希望能夠在未來幾週內發布更多公告和細節。這些與開發商、超大規模資料中心營運商和公用事業公司的潛在項目,如果能夠落實,也將採用 B&W 鍋爐設計與蒸汽渦輪機相結合的方式。因此,即使在將 24 億美元的專案儲備轉化為積壓訂單之後,這些新的機會也反映在我們目前超過 120 億美元的專案儲備中。

  • Additionally, we are seeing increased utilization of coal-fired power generation along with upgrades and enhancements driven by initiatives from the US Department of Energy and the National Energy Dominance Council, combined with rising demand for fossil fuel-based power generation and extended lead times for combustion turbines, these dynamics highlight our ability to deliver solutions more quickly by leveraging our proven steam generation technologies.

    此外,我們看到燃煤發電的利用率不斷提高,同時在美國能源部和國家能源主導委員會的倡議推動下,燃煤發電也在進行升級和改進;再加上對化石燃料發電的需求不斷增長,以及燃氣渦輪機交付週期延長,這些動態凸顯了我們利用成熟的蒸汽發電技術更快地提供解決方案的能力。

  • We are now in early discussions regarding the potential of new power generation utilizing coal technologies and are excited to see this development moving forward. For utilities, Coal is an offset to higher natural gas prices and either through upgrades or new build, we see the reliance on coal technologies continuing here in the US with additional facilities being added in Asia as well.

    我們目前正在就利用煤炭技術進行新型發電的潛力進行初步探討,並很高興看到這項發展取得進展。對於公用事業公司而言,煤炭可以抵消天然氣價格上漲的影響,無論是透過升級改造還是新建項目,我們看到美國繼續依賴煤炭技術,亞洲也在增加更多煤炭設施。

  • Our backlog continues to benefit from this increased demand for coal and power generation as well as the tailwinds from AI data center growth. In total, we saw our continuing operations backlog rise to $2.8 billion, which is a 470% increase compared to the end of 2024.

    煤炭和發電需求的增加以及人工智慧資料中心成長帶來的利好,使我們的積壓訂單持續受益。整體而言,我們的持續經營積壓訂單增加至 28 億美元,比 2024 年底成長了 470%。

  • Our pipeline of over $12 billion grew by roughly 20% in 2025, even with the conversion of this recent project to backlog, and we do see continued pathways for growth moving forward into 2026. During the fourth quarter of 2025, we delivered strong operating results while displaying continued core business momentum. Revenue, operating income and adjusted EBITDA all significantly outperformed company and consensus expectations for the quarter.

    即使將最近的這個項目轉化為積壓訂單,我們超過 120 億美元的項目儲備在 2025 年也增長了約 20%,我們確實看到了在 2026 年繼續增長的途徑。2025年第四季度,我們取得了強勁的經營業績,同時保持了核心業務的持續成長動能。本季營收、營業收入和調整後 EBITDA 均顯著超出公司和市場普遍預期。

  • Adjusted EBITDA was 53% higher compared to the fourth quarter of 2024, and operating income was up 373% when compared to the same period of 2024. These results during the quarter reflect the strong demand for our diverse portfolio of technologies and demonstrate B&W's evolution and strategic advancements over the past year.

    調整後的 EBITDA 比 2024 年第四季成長了 53%,營業收入比 2024 年同期成長了 373%。本季業績反映了市場對我們多元化技術組合的強勁需求,也展現了 B&W 在過去一年中的發展和策略進步。

  • In recent months, we fully paid off the remaining outstanding bonds due in February 2026 and expect to fully pay off the remaining outstanding December 2026 bonds in a timely fashion. These bond payments pair with the continued paydown of our overall debt levels. Across 2025, we achieved a substantial reduction of our debt on our balance sheet, resulting in a net debt of $119.7 million at the end of 2025, which is a $217.3 million improvement compared to the net debt of $337 million at the end of 2024.

    近幾個月來,我們已全額償還了 2026 年 2 月到期的剩餘未償債券,並預計將及時全額償還 2026 年 12 月到期的剩餘未償債券。這些債券支付與我們整體債務水準的持續下降相一致。到 2025 年,我們大幅減少了資產負債表上的債務,到 2025 年底,淨債務為 1.197 億美元,與 2024 年底的淨債務 3.37 億美元相比,減少了 2.173 億美元。

  • Our BrightLoop advancements continue to evolve behind the scenes, including our Masland and Wyoming projects. we are building momentum around the use of chemical looping as a means to convert solid and gas fuels to either hydrogen or steam generation while simultaneously capturing the CO2 that can be used for enhanced oil or methane recovery as well as other beneficial uses.

    我們的BrightLoop技術在幕後持續推進,包括我們在馬斯蘭和懷俄明州的計畫。我們正大力發展化學循環技術,將固體和氣體燃料轉化為氫氣或蒸汽,同時捕獲二氧化碳,用於提高石油或甲烷的採收率以及其他有益用途。

  • The commercial demonstration of BrightLoop at Masland remains an important milestone for B&W as we continue to position the company for additional growth opportunities in the future.

    BrightLoop 在 Masland 的商業簡報對 B&W 來說仍然是一個重要的里程碑,我們將繼續為公司未來的更多成長機會做好準備。

  • I'll now turn the call over to Cameron, who will discuss our full year 2025 results. Cameron?

    現在我將把電話交給卡梅倫,他將討論我們 2025 年全年的表現。卡梅倫?

  • Cameron Frymyer - Executive Vice President, Chief Financial Officer

    Cameron Frymyer - Executive Vice President, Chief Financial Officer

  • Thanks, Kenny. I am pleased to review our full year 2025 financial results, further details of which can be found in the 10-K that was filed with the SEC this afternoon. Our 2025 consolidated revenues were $587.7 million, which is a modest increase compared to the revenue of $581 million in 2024.

    謝謝你,肯尼。我很高興回顧我們 2025 年全年財務業績,更多詳情請參閱今天下午提交給美國證券交易委員會的 10-K 表格。我們 2025 年的合併收入為 5.877 億美元,與 2024 年的 5.81 億美元收入相比,增幅不大。

  • Our core Parts and Services continue to excel across 2025, increasing revenue 17%, outperforming expectations due to higher coal generation usage and growing baseload demand in North America. Continued growth in our Parts and Services is expected throughout 2026.

    2025 年,我們的核心零件和服務業務持續保持優異表現,營收成長 17%,超出預期,這得益於北美煤炭發電量增加和基本負載需求成長。預計到 2026 年,我們的零件和服務業務將持續成長。

  • Our operating income in 2025 was $20.7 million, which was an improvement compared to an operating loss of $6.3 million in 2024. Loss from continuing operations in 2025 was $32.8 million compared to a loss of $104.3 million in 2024. And our loss per share from continuing operations was $0.45 in 2025 compared to a loss per share of $1.30 in 2024. Adjusted EBITDA from continuing operations was $43.7 million compared to $21.2 million in 2024. As Kenny stated earlier, we have announced our full year 2026 adjusted EBITDA target range is between $80 million to $100 million.

    我們2025年的營業收入為2,070萬美元,與2024年630萬美元的營業虧損相比有所改善。2025 年持續經營虧損為 3,280 萬美元,而 2024 年虧損為 1.043 億美元。2025 年,我們持續經營業務的每股虧損為 0.45 美元,而 2024 年的每股虧損為 1.30 美元。持續經營業務的調整後 EBITDA 為 4,370 萬美元,而 2024 年為 2,120 萬美元。正如肯尼之前所說,我們已經宣布,2026 年全年調整後 EBITDA 目標範圍為 8,000 萬美元至 1 億美元。

  • I'll now turn to our balance sheet, cash flow and liquidity. Total debt at December 31, 2025, was $321.1 million, which includes unamortized fees and unamortized gains from our bond swap earlier this year. Our current debt consists of $83.9 million of December 2026 bonds, which, as Kenny stated earlier, will be paid off within the year and $151 million of bonds due in 2030 or $129.5 million of bonds when unamortized fees and unamortized gains are excluded.

    接下來,我將介紹我們的資產負債表、現金流量和流動性。截至 2025 年 12 月 31 日,總債務為 3.211 億美元,其中包括今年稍早債券互換產生的未攤銷費用和未攤銷收益。我們目前的債務包括 2026 年 12 月到期的 8,390 萬美元債券(正如 Kenny 之前所說,這些債券將在一年內償還)以及 2030 年到期的 1.51 億美元債券,或者如果排除未攤銷費用和未攤銷收益,則為 1.295 億美元債券。

  • The company had cash and cash equivalents and restricted cash balance of $201.4 million, giving us a net debt as of December 31, 2025, of $119.7 million or $79.7 million when excluding unamortized gains, fees as well as leases. As Kenny previously mentioned, we delivered a significant year-over-year improvement in our net debt, reducing it by $217.3 million compared to December 31, 2024.

    截至 2025 年 12 月 31 日,本公司擁有現金及現金等價物及受限現金餘額 2.014 億美元,淨債務為 1.197 億美元,若不計入未攤銷收益、費用及租賃,則淨債務為 7,970 萬美元。正如肯尼之前提到的,我們的淨債務實現了顯著的同比改善,與 2024 年 12 月 31 日相比減少了 2.173 億美元。

  • Additionally, in December of 2025, B&W paid off outstanding bonds due in February 2026 and the remaining outstanding December 2026 bonds will be paid off this year.

    此外,B&W 於 2025 年 12 月償還了 2026 年 2 月到期的未償債券,剩餘的 2026 年 12 月到期未償債券將於今年償還。

  • With that, I will now turn the call back over to Kenny.

    接下來,我會把電話轉回給肯尼。

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • Thanks, Cameron. Well, we are excited about our growing opportunities to expand in the power generation for the rapidly evolving AI data center space, and we remain focused on executing against our strategic plan. We remain uniquely positioned to capitalize on the growing global demand for baseload electrical generation, and our pipeline remains robust, exceeding $12 billion in project opportunities with significant tailwinds bolstered by the growing impact of AI data centers.

    謝謝你,卡梅倫。我們很高興有機會在快速發展的人工智慧資料中心領域拓展發電業務,並將繼續專注於執行我們的策略計劃。我們仍然擁有獨特的優勢,可以充分利用全球對基礎負載發電日益增長的需求,而且我們的專案儲備依然強勁,專案機會超過 120 億美元,人工智慧資料中心日益增長的影響也帶來了顯著的利好因素。

  • We anticipate prospects for the new bookings and further strong financial performance throughout 2026. I would like to once again recognize the hard work and expertise of our employees around the world who help us meet our customers' needs today and further strengthen our ability to support the energy needs of the future.

    我們預計2026年新訂單前景良好,財務表現將持續強勁。我再次要感謝我們世界各地員工的辛勤工作和專業技能,他們幫助我們滿足客戶當前的需求,並進一步增強我們支持未來能源需求的能力。

  • We would also like to recognize and thank our vendors and manufacturers around the world who are working to meet the requirements of our initial data center project and importantly, are working closely with us to ensure timely delivery on the next project once booked. These manufacturers are working to ensure we have the necessary resources and delivery schedules to meet our customer demands. We continue to be enthusiastic about the path forward and expect 2026 to be a strong operational year for B&W with resilient global demand for our technologies, driving sustained growth in the quarters ahead.

    我們也要感謝世界各地的供應商和製造商,他們努力滿足我們首個資料中心專案的要求,更重要的是,他們與我們密切合作,確保在預定的下一個專案中及時交付。這些製造商正在努力確保我們擁有必要的資源和交貨時間表,以滿足客戶的需求。我們對未來的發展道路依然充滿熱情,並預計 2026 年將是 B&W 營運強勁的一年,全球對我們技術的需求將保持強勁,從而推動未來幾季的持續成長。

  • In closing, B&W is also celebrating its 160th year, and it's a good time to reflect on some of the milestones and firsts that have defined our company history from playing a leading role in the global industrial revolution of the 19th century to helping make universal electrification from coal and natural gas possible to developing some of the world's most efficient and effective environmental emissions control, renewable energy and hydrogen generation and carbon capture technologies.

    最後,B&W 也迎來了成立 160 週年紀念日,這是一個回顧公司發展歷程中一些里程碑和首創事件的好時機,這些里程碑和首創事件定義了我們公司的歷史,從在 19 世紀全球工業革命中發揮領導作用,到幫助實現煤炭和天然氣的普遍電氣化,再到開發世界上一些最有效、最高效的環境排放量

  • B&W has constantly been at the forefront of innovation, but it all began with creating steam for power and B&W boilers and steam generation technologies have contributed to more than 400 gigawatts of total electrical capacity worldwide. We're proud of our history, and we're excited about what lies ahead for our company.

    B&W 一直走在創新的前沿,但這一切都始於為電力生產蒸汽,B&W 的鍋爐和蒸汽發生技術已為全球提供了超過 400 吉瓦的總電力容量。我們為我們的歷史感到自豪,也對公司未來的發展充滿期待。

  • And with that, I'll now turn the call back over to Tamita, who will help us with a few questions. Tamita?

    接下來,我將把電話轉回給塔米塔,她將幫助我們回答幾個問題。塔米塔?

  • Operator

    Operator

  • (Operator Instructions) Aaron Spychalla, Craig-Hallum.

    (操作說明)Aaron Spychalla,Craig-Hallum。

  • Aaron Spychalla - Analyst

    Aaron Spychalla - Analyst

  • Maybe first for us, just on the Base Electron project moving to $2.4 billion. Can you just talk about the dynamics there versus the limited notice? And then just on the project, any other color on time line? You talked a little bit about some of the milestones, but maybe just a little bit more detail there and then timing of kind of working capital needs and cash flows on year-end?

    也許對我們來說,首先是基礎 Electron 專案預算達到 24 億美元。您能否談談這方面的動態變化以及通知時間有限的情況?然後,就項目本身而言,時間線上還有其他顏色嗎?您剛才談到了一些里程碑事件,但能否再詳細說說年底的營運資金需求和現金流的時間表?

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • Sure. Let me see if I can capture that. So to back up, as you indicated, obviously, we announced the limited notice proceed last November, I believe, for $1.4 billion on the project. We -- typical in large projects until we get to the final notice to proceed, there's always variability in the exact scope and final amounts of the project at that time. So that's why we'd like to take that approach.

    當然。我看看能不能拍。所以,正如您所指出的,顯然,我們去年 11 月宣布了該項目的有限通知融資,金額為 14 億美元。在大型專案中,直到收到最終開工通知之前,專案的確切範圍和最終金額總是會有所變化,這是很常見的。所以這就是我們想採取這種方法的原因。

  • So as we were working through the final scope on the project, the final terms and conditions of the contract, as we mentioned the firm versus time or cost-plus scenarios on it, we were able then to complete the contract plus the final scope of those negotiations, which led us then to the $2.4 billion announcement for the gigawatts being provided.

    因此,當我們著手確定專案的最終範圍、合約的最終條款和條件時,正如我們之前提到的,合約是按時間還是按成本加成,我們最終完成了合約以及談判的最終範圍,這促使我們宣布了提供 24 億美元千兆瓦電力的決定。

  • So it's kind of normal evolution from a limit to notice to proceed to final notice to proceed and there's some variability always in the dollar amounts depending on that final scope as well as contract terms and conditions in that regard. So I think that was one question.

    因此,從限製到開工通知再到最終開工通知,這是一個正常的演變過程,而金額總是會根據最終範圍以及合約條款和條件而有所不同。所以,我想這就是其中一個問題。

  • The other on kind of the milestones and what's happening, as I mentioned in the remarks, we're beginning -- the site visits are underway on that particular piece. We have the manufacturing processes going at various locations around the world, both from a turbine standpoint and the processes for the boiler pressure parts construction at various locations around the world.

    至於其他里程碑和進展情況,正如我在發言中提到的,我們已經開始——該特定項目的現場考察正在進行中。我們在世界各地多個地點開展製造流程,包括渦輪機製造流程和鍋爐壓力零件製造流程。

  • And obviously, very confident in meeting the schedule and the time lines for delivery. So some of the variability right now is waiting to get some specific dates on when construction on site will begin. Obviously, we're working through those, there's details behind the scenes on that, but we're anticipating some work beginning this year at this point in time. And then obviously, a bulk of this will move into 2027 and 2028 once we are well into the construction phase of this standpoint.

    顯然,我們非常有信心按時按計劃完成交付。因此,目前存在的一些不確定因素是,需要等待確定特定的施工日期。顯然,我們正在處理這些問題,幕後還有一些細節需要處理,但我們預計今年這個時候會有一些工作開始。然後很顯然,一旦我們進入這一立場的建設階段,其中大部分工作將轉移到 2027 年和 2028 年。

  • So I think the exciting aspect is working, obviously, with our manufacturers as well as with Siemens on the turbines, along with the boiler makers in the union, obviously, getting the labor force ready, we do feel confident that we can meet those time frames. And the fact that we're using previously engineered boilers eliminates a significant amount of time frames in this project schedule. So it gives us confidence in being able to complete this on time.

    所以我認為令人興奮的是,顯然,我們要與我們的製造商以及西門子合作生產渦輪機,還要與工會的鍋爐製造商合作,讓勞動力做好準備,我們有信心能夠按時完成這些工作。而且,由於我們使用了先前設計好的鍋爐,因此可以大大縮短專案進度。因此,這讓我們有信心按時完成這項工作。

  • Aaron Spychalla - Analyst

    Aaron Spychalla - Analyst

  • Good. And then on the guidance increase, can you maybe just talk to visibility into that and maybe cadence throughout the year? And then any expected contribution on the power generation project?

    好的。關於指導意見的成長,您能否談談這方面的透明度,以及全年的成長節奏?那麼,您對發電專案有任何預期貢獻嗎?

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • Yes. So obviously, there's a little bit baked in from the contribution of the power project into that increase for sure on that. It's, again, variable until we know more specifically when we get cost to the site, and that's obviously where our revenue recognition is based on cost, as you know. So the key component there is that we're able to drive cost to the project on the site on that. So we wanted to increase, obviously, inclusive of that.

    是的。所以很明顯,電力專案的貢獻肯定會對這一成長產生一定影響。同樣,在我們更具體地了解網站成本之前,這個數字是可變的,而正如你所知,我們的收入確認顯然是基於成本的。因此,關鍵在於我們能夠以此為依據,在現場控制專案成本。所以,很顯然,我們希望增加這方面的投入。

  • And obviously, there's some elevated increases that we're seeing just in some of the general parts, services and upgrades and usage around some of the coal and natural gas projects that we're involved in as well, too. So the combinations of those gave us the confidence to increase that. We also, I think, extended the range a little bit, $80 million to $100 million because of some of the variability when we specifically start some of the construction on site as it relates to the base electron contract.

    顯然,在我們參與的一些煤炭和天然氣項目相關的零件、服務、升級和使用方面,我們也看到了一些顯著的成長。因此,這些因素的組合給了我們信心增加投入。我認為,由於我們在現場開始一些與基礎電子合約相關的建設工作時存在一些變數,我們也稍微擴大了範圍,從 8000 萬美元擴大到 1 億美元。

  • Cameron Frymyer - Executive Vice President, Chief Financial Officer

    Cameron Frymyer - Executive Vice President, Chief Financial Officer

  • Yes, Aaron, I think typically, you'll see kind of the growth in adjusted EBITDA revenue throughout the year.

    是的,Aaron,我認為通常情況下,你會看到調整後的 EBITDA 收入在全年持續成長。

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • Yes, the cyclical aspect was --

    是的,循環方面是--

  • Cameron Frymyer - Executive Vice President, Chief Financial Officer

    Cameron Frymyer - Executive Vice President, Chief Financial Officer

  • I think it will step up each quarter.

    我認為它每個季度都會有所進步。

  • Aaron Spychalla - Analyst

    Aaron Spychalla - Analyst

  • Okay. Okay. And then maybe one last one, just on that coal-to-gas project. Can you maybe give an update there, how far you are into that project, time line to finish that up? And then just any other thoughts on the pipeline for those types of opportunities as well?

    好的。好的。最後,或許還可以再問一個問題,就關於那個煤製氣計畫。您能否更新一下專案進展,例如進行到什麼程度了,以及預計何時完成?那麼,對於這類機會的後續發展,您還有其他想法嗎?

  • Cameron Frymyer - Executive Vice President, Chief Financial Officer

    Cameron Frymyer - Executive Vice President, Chief Financial Officer

  • Yes. So as of right now, we're on schedule, Aaron. I think we'll finish up really bulk of the '27 or '26 going to '27. So no issues there.

    是的。所以就目前而言,我們一切按計劃進行,亞倫。我認為我們能夠完成 2027 年或 2026 年的大部分工作,直到 2027 年。所以這方面沒有問題。

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • And on the pipeline side, we've got other -- not that large, but there's other conversion projects that we're in discussions on as it relates to that. Again, interestingly enough because some of the developments that are coming out of Capitol Hill and some of the recent remarks by President Trump, there's some mandates and some of the utilities are looking at extending coal power generation further, some of that due to, as I mentioned in the remarks, on the higher price of natural gas, right?

    在管道方面,我們還有其他一些——雖然規模不大,但還有其他一些相關的改造項目正在討論中。有趣的是,由於國會山莊的一些進展以及川普總統最近的一些講話,一些公用事業公司正在考慮進一步延長煤炭發電,正如我在講話中提到的,部分原因是天然氣價格上漲,對吧?

  • So they're extending out some of the coal plants to last longer. So some of the natural gas conversions or a few of them are shifting out in later years. But in the meantime, some of those plants now are going through a little bit higher or increased upgrades or parts replacements to continue operating those in as efficiently as possible. So it both help us, obviously, on those, but we're seeing a little bit of that impact as well, too.

    所以他們正在延長一些燃煤電廠的使用壽命。因此,部分天然氣改造項目或少數項目將在後期進行調整。但與此同時,其中一些工廠正在進行更高級別的升級或零件更換,以盡可能有效地繼續運作。所以,顯然這對我們都有幫助,但我們也看到了一些負面影響。

  • Operator

    Operator

  • Rob Brown, Lake Street Capital Markets.

    羅布布朗,湖街資本市場。

  • Robert Brown - Analyst

    Robert Brown - Analyst

  • Congratulations on all the progress. I just wanted to dig into the pipeline a little more. I think you said you had a potential second project from Base Electron and then several other AI data center projects. Could you just give us a sense of maybe the sizing of the pipeline type projects and maybe the kind of time line of those projects?

    祝賀你們取得的所有進展。我只是想更深入地了解這條管道。我想你說過你還有一個基於 Base Electron 的潛在項目,然後還有幾個其他的 AI 資料中心項目。能否簡單介紹一下管道類專案的規模以及這些專案的大致時間表?

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • Yes. So we're -- as mentioned, obviously, Base Electron has expressed interest in an additional 1 gigawatt or 1.2 gigawatt worth of power on that. We are also in discussions, I would say, again, as I mentioned in the comments, real-time discussions with one or two other projects outside of Base Electron and Applied that are looking at the similar solution, the boiler size may vary.

    是的。所以,正如前面提到的,Base Electron 顯然對在該項目上額外增加 1 吉瓦或 1.2 吉瓦的電力表示了興趣。正如我在評論中提到的,我們也正在與 Base Electron 和 Applied 之外的一兩個其他項目進行即時討論,這些項目也在研究類似的解決方案,鍋爐規模可能會有所不同。

  • There's a project or two looking at smaller boilers, but more -- but it's still in the 1 gigawatt range. So most of the data center projects usually are -- when we have discussions, it's in the -- one or two could be in the 500-megawatt range. Most are in the 1 to 2 gigawatt range when we get in discussions about the Power Solutions.

    目前有一兩個項目正在研究小型鍋爐,但更多的是——不過仍然在 1 吉瓦的範圍內。所以大多數資料中心專案通常是——當我們討論時,通常是——一兩個專案可能在 500 兆瓦的範圍內。當我們討論電力解決方案時,大多數方案的功率都在 1 到 2 吉瓦的範圍內。

  • Our specific scope on some of those will vary a little bit. In some cases, it will be a little more turnkey like we're doing at base electron. Others are -- we're in discussions on right now would be more for us to provide the boiler and the steam turbines. But under a different EPC structure.

    我們對其中一些項目的具體範圍會略有不同。在某些情況下,它會更像我們在基礎 Electron 中所做的那樣,提供更便捷的解決方案。其他方面——我們目前正在討論,現在更多的是由我們提供鍋爐和蒸汽渦輪機。但採用的是不同的EPC結構。

  • So there are different levels of scope that we're involved in. But from an overall size standpoint, most of those discussions are in a very similar size, both in the gigawatt aspect. Some are different scope on a total project basis. So they'll have different pricing elements. But you can kind of get a sense of the general project impact that would come from these additional projects if we can get them booked.

    所以我們參與的專案範圍各不相同。但從整體規模來看,大多數討論的規模都非常相似,無論是以千兆瓦為單位還是其他方面。有些項目在整個專案範圍內有所不同。所以它們的定價要素會有所不同。但是,如果我們能夠落實這些額外的項目,您就能大致了解這些項目將對整個項目產生的影響。

  • Robert Brown - Analyst

    Robert Brown - Analyst

  • Okay. Great. And then in terms of capacity to do these, like there's, call it, total of two to three projects that are in the works. What's sort of the ability to do or the capacity to take that work on? Or does it need to spread out over time?

    好的。偉大的。至於開展這些項目的能力,目前總共有兩到三個項目正在進行中。他/她是否有能力或條件承擔這項工作?或是需要隨著時間的推移而逐漸顯現?

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • Yes. No, great question. So we are -- as I mentioned or tried to mention in the remarks, we are working closely with Siemens and other turbine companies, but working with them closely. We've got several meetings coming up over the next few weeks, but trying to establish increased capacity on the steam turbine side of this. So again, either through Siemens and that relationship or depending on the size with one or two other turbine companies around the world.

    是的。不,問得好。所以,正如我在演講中提到的,我們正在與西門子和其他渦輪機公司密切合作,但只是與他們密切合作。接下來幾週我們將召開幾次會議,目的是提高蒸汽渦輪機方面的產能。所以,要嘛透過西門子及其合作關係,要嘛根據規模大小,與世界上其他一兩家渦輪機公司合作。

  • The great aspect around using steam turbines versus combustion turbines is that there is -- especially when we get to smaller turbines, there is more manufacturers and a little bit better excess capacity that we can leverage within the manufacturing process on that side.

    使用蒸汽渦輪機而不是燃氣渦輪機的最大優勢在於——尤其是在小型渦輪機方面——有更多的製造商,而且在製造過程中有更好的剩餘產能可以利用。

  • So we're -- when we negotiated the first set of turbines with Siemens, we were also working with them and continue to do so to identify places where we can leverage and get to increased capacity with them to move on to another four possible steam turbines with Siemens, also discussions with others out there to ensure that we have the capacity to meet those data center project needs.

    所以,當我們與西門子就第一批渦輪機進行談判時,我們也一直在與他們合作,並且繼續這樣做,以確定我們可以利用他們的優勢來提高產能的地方,以便與西門子再進行四台可能的蒸汽渦輪機的採購。同時,我們也與其他公司進行討論,以確保我們有能力滿足這些資料中心專案的需求。

  • We've also taken that same approach on the boiler pressure pump manufacturing side, both with that steel aspects here in the US, fabrication here in the US, but also with our manufacturing partners and companies and our own manufacturing facilities that we have, but also our partner manufacturing facilities that we have in Central Asia and Southeast Asia to make sure that we have the right resources and everything lined up on those raw materials from various components on the steel pressure parts to be able to make the manufacturing schedules and have those shipped.

    在鍋爐壓力泵製造方面,我們也採取了同樣的做法,不僅包括在美國本土的鋼材加工和製造,還包括與我們的製造合作夥伴和公司以及我們自己的製造工廠,以及我們在中亞和東南亞的合作夥伴製造工廠,以確保我們擁有合適的資源,並安排好各種鋼製壓力部件的原材料,從而能夠制定製造計劃並按時發貨。

  • We're looking at one case where we're looking for the possibility to ship a modular boiler approach through, obviously, a water access shipping standpoint, but that can be delivered directly to site on one of the opportunities that we're in discussions on more of a -- instead of a stick build on site, it would be more of a modular aspect on site.

    我們正在研究一個案例,探討能否透過水路運輸的方式,將模組化鍋爐直接運送到現場。我們正在討論的其中一個機會是,與其在現場進行現場搭建,不如採用模組化方式。

  • And those -- by spreading those across different manufacturers because they're different sized boilers and different sized turbines, we can -- we have confidence in having the capacity and the manufacturing to meet these next two or three projects that we're in discussions on as well.

    而且,由於鍋爐和渦輪機的尺寸各不相同,我們將這些項目分散到不同的製造商進行生產,因此我們有信心具備足夠的產能和製造能力來滿足我們正在討論的接下來的兩到三個項目。

  • On top of that, a critical component is the labor force and the boiler makers who we have a really good relationship with has been instrumental in helping us prep and prepare for these particular project sites on the readiness of a labor force and availability as we look down the road to have these construction schedules outlined and obviously eventually move under contract. So we're looking at it both on that side.

    此外,勞動力也是一個關鍵因素,而我們與之保持良好關係的鍋爐製造商們,在幫助我們為這些特定的項目現場做好準備方面發揮了重要作用,確保勞動力的準備和可用性,以便我們能夠制定施工計劃,並最終簽訂合約。所以我們正在從這兩個方面來考慮。

  • And then, of course, in B&W internally as it relates to having the right team aspects ready to go to project manage these from the procurement phase all the way to the construction phase to the delivery phase to the on-site phase to the commissioning and obviously, the project completion phase as well.

    當然,在 B&W 內部,還需要組成合適的團隊,從採購階段到施工階段、交付階段、現場階段、調試階段,以及專案完成階段,對專案進行專案管理。

  • The good news about this, and I think that's where it helps show is that B&W is not actually engineering new boilers here. So the pressure usually on scope for us is if we have to actually extend beyond the engineering resources that we have, which we're slowly adding to that, but we don't have an immediate impact on those engineering resources because we're leveraging previously designed boilers. And that -- all of those things combined to give us the confidence in the capacity to deliver these.

    這件事的好消息是,而且我認為這恰恰說明了,B&W 實際上並沒有在這裡設計新的鍋爐。因此,我們面臨的範圍壓力通常是,我們是否必須超出我們現有的工程資源,而我們正在慢慢增加這些資源,但由於我們利用的是以前設計的鍋爐,所以我們不會立即對這些工程資源產生影響。所有這些因素加在一起,使我們有信心實現這些目標。

  • Operator

    Operator

  • Jeff Grampp, Northland Capital.

    Jeff Grampp,北地資本。

  • Jeffrey Grampp - Analyst

    Jeffrey Grampp - Analyst

  • Kenny, on the -- on your prepared remarks, it sounded like some of these conversations on some of these other projects are fairly mature. And I guess just wanted to verify if that's a fair read here. I don't know if it's appropriate to try to get you to quote how many months behind maybe relative to the base electron kind of progression. But it sounds like some of these conversations are pretty far down the path, but I want to make sure we kind of appropriately set our expectations regarding timing.

    肯尼,關於你事先準備好的發言,聽起來你們對其他一些項目的討論已經相當成熟了。我只是想確認一下,這種解讀是否準確。我不知道是否應該讓你估算一下相對於基礎電子進度而言,你落後了多少個月。但聽起來其中一些對話已經進行得相當深入了,但我希望確保我們對時間安排有適當的預期。

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • Yes. No, good question. Obviously, we don't want to get too out of front negotiate contracts in the public space. But we are in discussions.

    是的。不,問得好。顯然,我們不想在公共場合過於主動地進行合約談判。但我們正在進行討論。

  • I think like most projects for us, right, there would be an evolution where we would -- if we do get it booked or announced, we would enter into some sort of an initial phase, whether that's a limit to notice proceed or some other form of agreement, right, that would give us the ability to map out all of the site elements at this specific location on this other opportunity, the delivery schedules, the layout aspects of it, and it allows them also then to use our technologies in various permits and other aspects around the project while we ready the full manufacturing process for those specific boilers and turbines on that front.

    我認為,就像我們的大多數項目一樣,對吧,如果這個項目最終被預定或宣布,我們會進入某種初始階段,無論是發出開工通知的期限,還是其他形式的協議,對吧,這將使我們能夠在這個特定地點規劃出所有場地要素,包括交付時間表、佈局等方面,並且允許他們在各種渦輪和項目其他方面使用我們的技術,同時我們也為這些特定的鍋爐和流程準備。

  • So we are in discussions there. I hate to put a time frame on those. Hopefully, we can get to at least an initial discussion or announcement in the next several weeks, but we'll just have to see how that goes. But we are in that level of discussion with one or two other opportunities at the moment.

    所以我們正在就此進行討論。我不想給這些事情設定時間期限。希望在接下來的幾週內,我們至少能進行初步討論或發佈公告,但我們還得看看情況如何。但目前我們還在與其他一兩個機會進行類似的討論。

  • Jeffrey Grampp - Analyst

    Jeffrey Grampp - Analyst

  • That's great to hear. And for my follow-up, I'm just kind of curious, as you guys are kind of seeing things play out, how much of a catalysts have some of these announcements been for you guys with respect to the APLD project? Do you feel the market participants were generally already aware of what you guys bring to the table and so it didn't really bring any new people to the fold? Or does that announcement and some of the progress you guys have had provide some kind of, I don't know, validation that this is a real solution that people can look to, to address power capacity issues?

    聽到這個消息真是太好了。我的後續問題是,我很好奇,隨著事情的發展,這些公告對你們來說,在 APLD 專案方面起到了多大的推動作用?您是否覺得市場參與者普遍已經了解您能為市場帶來什麼,因此並沒有真正吸引任何新人加入?或者說,你們的聲明和取得的一些進展是否在某種程度上證實了這確實是一個可以供人們參考的、解決電力容量問題的真正解決方案?

  • Kenneth Young - Chairman of the Board, Chief Executive Officer

    Kenneth Young - Chairman of the Board, Chief Executive Officer

  • Yes. For sure, one or two of the projects that we're contemplating that potential -- immediate potential here, we're also underway in parallel with the discussions with Applied for certain.

    是的。當然,我們正在考慮的一個或兩個項目具有這種潛力——這裡指的是眼前的潛力,我們也在與 Applied 進行討論的同時進行著這些項目。

  • But I would say also as a result of the announcement of the Applied contract, the amount of inbound interest from both hyperscalers, utilities and other developers and other IPPs has been extremely, boy, lack of a better term, I mean, very significant, right? So -- and that's, I would say, around the world, not just here in North America, but in other locations around the world as well, too, on that. So some of those are -- come from very mature clients, meaning they've got real projects behind them.

    但我想說,由於 Applied 合約的公佈,來自超大規模資料中心營運商、公用事業公司、其他開發商和其他獨立電力生產商的興趣量非常大,哎,找不到更好的詞來形容了,我的意思是,非常重要,對吧?所以——而且我認為,這種情況不僅在北美,而且在世界其他地方也是如此。所以其中一些客戶非常成熟,這意味著他們背後有真正的專案。

  • Some of those opportunities come from developers and other aspects that don't, right? But it's -- I think the amount of attention that we picked up on not only, I will say, in the marketplace, but I would also say within the Department of Energy and the Energy Dominance Council has also been significant on this and the support of this as well, too.

    有些機會來自開發人員,有些則來自其他方面,對吧?但我認為,我們不僅在市場上,而且在能源部和能源主導委員會內部也獲得了相當大的關注和支持。

  • So we have -- we're in discussions with a lot on Capitol Hill as well as the Department of Energy, and they're very much aware of the progress, not only on the Applied Base Electron project, but also potentially on one or two of these others as well. So all of that has been very much a positive for us today, but we'll see how that goes in the future. But it's pretty exciting at this point in time.

    所以我們正在與國會山莊的許多人以及能源部進行討論,他們非常清楚我們取得的進展,不僅是應用基礎電子專案的進展,而且可能也清楚其他一兩個專案的進展。所以今天這一切對我們來說都是非常積極的,但未來會如何發展,我們拭目以待。但就目前而言,這相當令人興奮。

  • Jeffrey Grampp - Analyst

    Jeffrey Grampp - Analyst

  • Great. That's helpful. If I can sneak one more in, maybe for Cameron. Is there a way to kind of bifurcate how much of the increase in the guide is related to the kind of core business outperformance versus contribution from this project?

    偉大的。那很有幫助。如果我能再偷偷加一個,也許可以給卡麥隆。有沒有辦法區分一下,指南中的成長有多少是由於核心業務的超額收益,又有多少是由於這個專案的貢獻?

  • Cameron Frymyer - Executive Vice President, Chief Financial Officer

    Cameron Frymyer - Executive Vice President, Chief Financial Officer

  • Yes. I mean, Jeff, I think right now, it's with Applied being such a large contract in days, weeks of POC accounting, we can move that one way or the other. I don't think we're going in that kind of detail at this point in time just because it could move depending on how all the stuff works out, which is also why we got that larger range.

    是的。我的意思是,傑夫,我認為現在的情況是,Applied 的合約金額巨大,幾天、幾週內就能完成 POC 會計核算,我們可以朝這個方向發展。我認為目前我們不會深入探討那麼詳細的細節,因為情況可能會根據所有事情的進展而變化,這也是我們制定更大範圍的原因。

  • Operator

    Operator

  • There are currently no other questions in queue. So I'll pass it back to Sharyn Brooks for closing remarks.

    目前隊列中沒有其他問題。那麼,我將把發言權交還給莎倫布魯克斯,請她作總結發言。

  • Sharyn Brooks - Director of Communications

    Sharyn Brooks - Director of Communications

  • Thank you, everyone, for joining us. That concludes our conference call. A replay will be available for a limited time on our website later today.