Operator
Hello, and thank you for standing by. My name is Bella, and I will be your conference operator today. At this time, I would like to welcome everyone to Q3 2026 Ameresco Inc earnings conference call. (Operator Instructions) I would now like to turn the conference over to Leila Dillon, Chief Marketing Officer. You may begin.
Leila Dillon - Senior Vice President, Chief Marketing Officer
Thank you, Bella, and good afternoon, everyone. We appreciate you joining us for todayâs call. Our speakers on the call today will be George Sakellaris, Amerescoâs Chairman and Chief Executive Officer; Nicole Bulgarino, Co-President of Ameresco; and Josh Baribeau, Chief Investment Officer. In addition, Julie Bradshaw, Vice President of Finance and Interim Principal Financial Officer, will also be available during Q&A to help answer questions.
Before I turn the call over to George, I would like to make a brief statement regarding forward-looking remarks. Todayâs earnings materials contain forward-looking statements, including statements regarding our expectations. All forward-looking statements are subject to risks and uncertainties. Please refer to todayâs earnings materials, the safe harbor language on slide two of our supplemental information, and our SEC filings for a discussion of the major risk factors that could cause our actual results to differ from those in our forward-looking statements.
In addition, we use several non-GAAP measures when presenting our financial results. We have included the reconciliations of these measures and additional information in our supplemental slides that were posted to our website. Please note that all comparisons that we will be discussing today are on a year-over-year basis unless otherwise noted.
I will now turn the call over to George. George?
George Sakellaris - Chairman of the Board, Chief Executive Officer
Thank you, Leila, and good afternoon, everyone. Our strong momentum continued in the third quarter with excellent execution and financial performance across all of our business lines. We also had another great quarter of new business activity, which contributed significantly to our multi-year projects backlog. Importantly, we saw strong contract conversion during the quarter, with $737 million of awards converting into contracted backlog, one of the highest amounts in the companyâs history.
We have seen this new business development momentum continue into the fourth quarter. In specific markets, we saw projects move through our sales cycle at a faster pace than we have historically experienced. This was driven by the tremendous need to upgrade the nationâs existing buildings and public energy infrastructure, coupled with the pressing need for new power generation.
Ameresco is uniquely positioned to address these customer needs through our decades of experience delivering energy savings and diverse on-site power solutions. As I mentioned, all three of our major business lines experienced excellent growth during the third quarter. Our projects business demonstrated strong results from our two core market pillars: buildings and public energy infrastructure, and power infrastructure.
Our buildings and public energy infrastructure pillar continued to show solid results across the markets we serve, anchored by the continued strength of our federal business. Customers across markets and geographies are facing spiking energy costs, as well as the need to pay for decades of deferred maintenance, making our budget-neutral and sustainable solutions a perfect way to solve both problems.
We also continue to expand our offerings within this pillar beyond our core energy efficiency offerings, making us a one-stop shop for a broad range of energy infrastructure solutions for our partners. And the power and infrastructure pillar of our business is uniquely positioned to address the rapidly growing need for reliable and flexible power.
Our diverse portfolio of generation solutions can provide critical backup power to utilities, as well as behind-the-meter on-site power for commercial and industrial customers, seeking to fuel growth and ensure continuity of operations. This is an increasingly important growth opportunity for us, particularly as power constraints intensify and customers look for solutions that can be deployed quickly and tailored to their specific needs.
We are seeing this momentum across geographies, from large-scale infrastructure projects in Canada, utilizing solutions such as natural gas turbines and battery energy storage, to the continued growth of renewables with our Sunel joint venture in Europe. I am very pleased to see that our two recurring revenue businesses, energy assets and O&M, continued to grow and have become a material component of Amerescoâs overall business. We believe these two businesses will continue to provide excellent growth to our long-term recurring revenue and profits. Together, our three major business lines provide Ameresco with great diversification of end markets, customers, and solutions. We expect this to drive our long-term growth and also give us tremendous business resilience.
And finally, I want to take a minute to talk about the election results from last week. One message came through clearly: rising energy costs and affordability are top of mind across the country. We believe Ameresco is exceptionally well-positioned in this environment. Our budget-neutral buildings and public energy infrastructure solutions help customers modernize aging facilities, improve efficiency, resiliency, and reduce energy costs without requiring significant upfront capital.
At the same time, our power infrastructure solutions are helping address a growing need for reliable and cost-effective power. Together, these capabilities directly address many of the energy challenges facing our customers today, and we believe this environment will continue to create meaningful opportunities for our business.
And now, I would like to turn the call over to Nicole to provide additional details on the success that we are seeing in our business development activities. Nicole?
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Thank you, George, and good afternoon, everyone. I want to start off by focusing on our business development successes, which support our expectation for continued revenue growth in the coming years. New project awards of $875 million marked one of the companyâs strongest quarters for awards on record. Awarded backlog reached over $4.5 billion, over 70% higher than it was at this time last year. This highlights the great momentum we are seeing in our business, driven by the confluence of positive industry catalysts.
Our federal business saw record growth, coming from large energy efficiency and infrastructure projects with both the military and civilian agencies. We also continue to see strong demand in the C&I sector, where the need for power and resiliency drove activity in this increasingly important end market. Together, our federal, C&I, and European projects accounted for approximately $675 million, or over 75% of our new awards during this quarter, reflecting the important diversification within our backlog.
We also added approximately $200 million to our awarded backlog related to our data center projects. This is due to scope expansion as the development of these projects progressed. We continue to pursue new data center opportunities that benefit from on-site power solutions. Our offering is differentiated in that we build the power on-site, placing no additional strain on the grid or on the electricity prices in the community. Our solutions also minimize the use of the municipal water supply and bring benefits to the communities.
As we look to the future, we intend to maintain our approach to strategically select the best-fit industry partners and capitalize on the use of our existing federal land. You may have seen our recent announcement with the Army to develop on-site nuclear power generation projects that will be designed to enhance mission readiness and resilience while providing clean power to the greater grid. We believe nuclear technologies have the potential to play a significant role in the future for clean, firm power.
We are actively working with several nuclear technology companies to develop an integrated solution for our customers, and we just signed our first EPC contract for the balance of plant work for a microreactor project. With the growth in our backlog, I want to highlight contract conversions, where we delivered exceptional execution this quarter. Contract conversions accelerated across several of our key end markets, including federal, Canada, and Europe, driven by strong relationships and repeat business from our existing customers.
A great example of this is the US Department of Veterans Affairs, where we are currently engaged in multiple infrastructure improvement projects at facilities across several states. Thanks to the teamâs hard work this quarter, our total backlog, awarded and contracted, has grown to nearly $7.2 billion, up almost 40% from this time last year, giving us revenue visibility for many years to come.
Iâll now turn the call over to Josh to cover our strong Q3 financial performance in more detail. Josh?
Josh Baribeau - Senior Vice President, Chief Investment Officer
Thank you, Nicole, and good afternoon, everyone. Before I cover our Q3 results, I want to briefly walk through an accounting change and a change in our non-GAAP methodology that impacted how we present our results in forward guidance.
First, in the third quarter, we completed a further accounting evaluation of the Neogenyx transaction. In conjunction with external accounting partners, we determined that HLBV accounting is the more appropriate way to reflect this joint venture in our financials. HLBV allocates income or loss based on what each partner would receive if the joint venture were liquidated at book value at each reporting date. This method is commonly used in tax equity and complex partnership structures. Importantly, this change does not affect the underlying economics, cash flows, or operations of our business.
Next, because HLBV results can vary meaningfully from quarter to quarter, our non-GAAP EPS and adjusted EBITDA now reflect 100% of the operating results of our consolidated joint ventures, Neogenyx Fuels and Ameresco Sunel Energy, to make period-to-period comparisons easier. Our ownership of the joint ventures does not change. We continue to own 70% of Neogenyx and 51% of the Sunel JV.
To maintain transparency within our results, we have included net income and adjusted EBITDA for each JV in our press release. Neogenyx results are reflected in our renewable fuel segment, which is substantially all of Neogenyx.
Turning to our great quarterly results. Total revenue increased 10% to $580 million, reflecting strong execution across our three major business lines, as well as excellent business development activity. Project revenue increased 9% to $446 million, with particular strength from federal, C&I, and our Sunel JV.
Our energy asset business had another strong quarter as we continue to benefit from the expansion of our portfolio of owned operating assets, with revenue growing 21% to $75 million. Our operating energy asset base stands at 827 MW, with another 500 megawatts in development. Revenue of assets is consolidated, but the megawatt figures reflect Amerescoâs 70% ownership in the Neogenyx JV.
We also continue to add O&M contracts, driving revenue growth for this business by 20% to $37 million. Our O&M backlog now exceeds $1.5 billion, supporting what we expect to provide many years of recurring profitable revenue visibility.
Gross margin expanded to 18.7% with meaningful improvement on both a sequential and year-over-year basis. Margin improvement was driven by a combination of favorable business mix and strong execution.
During the quarter, we made a change to the useful life assumptions of our energy assets, extending it to 30 years from 20 years previously, bringing us more in line with industry averages. This change reduced the depreciation expense related to our energy assets beginning in Q3 and going forward. Largely offsetting this reduction in Q3 was an increase in depreciation from our planned adoption of tax-based accounting for transferable investment tax credits, which Iâll touch upon in a moment.
Net income attributable to common shareholders was $31.9 million, or $0.59 per diluted share, while non-GAAP EPS was $0.88. Earnings for the quarter included a large tax benefit related to our planned adoption of a tax-based accounting policy.
We believe this better aligns the earnings benefit of investment tax credits with the period in which they are generated, rather than allocating the benefit over the life of the related assets. The retrospective application of this tax accounting policy is reflected in our year-to-date results, as well as the 2025 recast comparisons.
Adjusted EBITDA increased to $92 million and represents the full consolidation of our JVs, as previously discussed. For ease of comparisons with your prior models, without this full consolidation, non-GAAP EPS in Q3 would have been $0.60 per share, and adjusted EBITDA would have been $78 million. We have provided supplemental quarterly details for all of 2025 and 2026, reflecting the retrospective application of our new tax-based accounting policy, as well as the full consolidation of our JV results in our press release.
Turning to our balance sheet. Unrestricted cash was $129 million, with total corporate debt $380 million. Our corporate leverage was 2.9 times, comfortably below our 3.5 covenant. During the quarter, we secured $106 million of new financing commitments, which should give us additional financial flexibility to fund our expected growth, support our working capital needs, and scale our energy asset portfolio in a disciplined way.
As detailed in our press release, we are providing Q4 guidance and updating our full year 2026 guidance. These updates reflect the accounting changes I discussed, as well as the inclusion of 100% of the operating results of our consolidated joint ventures in our non-GAAP EPS and adjusted EBITDA presentations. Our guidance only reflects these changes and does not reflect a change in our operational outlook. Our full year adjusted EBITDA and non-GAAP EPS guidance would have otherwise been unchanged.
Now I would like to turn the call back to George for closing comments.
George Sakellaris - Chairman of the Board, Chief Executive Officer
Thank you, Josh. As you have heard, this was a strong quarter of execution, driving excellent financial performance and significant new business activity.
That momentum has continued into the fourth quarter, positioning us to cap off a tremendous year of execution and development activity. With our growing backlog and the strength of our recurring revenue businesses, we believe we are well-positioned to deliver continued profitable growth in 2027 and beyond. We look forward to connecting with many of you at upcoming meetings, conferences, and events.
In closing, I want to once again thank our employees, customers, and stockholders for their continued support and confidence in Ameresco.
Operator, we would like to open the call to questions now.
Operator
(Operator Instructions) Manish Somaiya, Cantor.
Manish Somaiya - Analyst
Yes, hi. Good afternoon, good evening. Itâs Cantor, of course, I think you know that already. Congrats on backlog conversion on margins. I guess, George, you must be pretty thrilled with how things panned out in the quarter. I just wanted to go back to the comment on the post-election synopsis.
Perhaps, George, if you can just help us understand as to what youâre seeing on the data center side, which is, I think, everybodyâs question at this point, how are customers reacting? Have you heard from any of the regulatory bodies or customers as far as shifting timelines? Maybe if you can just help us understand as to whatâs happening, whatâs been sort of the initial reaction, and how are you sort of planning for the weeks and months ahead?
George Sakellaris - Chairman of the Board, Chief Executive Officer
Thank you, and good question. I will add some color, make some comments, and then I will let Nicole for the data centers add a little bit more color. But overall, the election is a positive for us. You got to think what I said before, that our basic bread-and-butter business is energy efficiency and the budget-neutral solutions that we provide to the customers. I think the election showed that affordability and energy cost, the escalation, is a prime concern, and I think we have a very, very good solution.
The fact that we had the change in Congress and some key government shifts across the country, I think overall itâs going to help us. As far as the data centers are concerned, I think Nicole will add good color, but I think the targets that we have chosen and the projects that we are working, especially since 50% of our data centers, they are in federal land, it will be easier to permit. Ultimately, I think the value proposition for those sites that we have control, of which five of them, I think is going to be good for us, and whatâs going on in the industry.
Nicole, you might want to add some.
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Sure. Yeah. I mean, we remain confident and really excited about our backlog with data center customers. I mean, as I said in the script, what differentiates our solutions is that they are on-site power. They are islanded in some cases even.
So if you look at what has come out against data centers and power, it is exactly that, is they do not want it to be grid impacting, and they certainly do not want it impacting electricity costs. So by doing what we are doing, we are aligned very well with what everyone has been talking about for the past couple months.
The elections, now that they are over, that does clear up this pause that we have been under, waiting to see what is going to happen in anticipation. So now that we are more moving forward, we have a diverse pipeline, as George mentioned, on federal lands and also commercial lands, with different type of end-user tenants.
We are very excited about that, but they are large power plant projects, and just with anything, these projects have to go through the development process. We will work through challenges as they come, but we, at this point, very much think that our solution is in line with what the overall landscape is calling for right now.
Manish Somaiya - Analyst
Nicole, if I could just add one more data center question. I think I saw $200 million data center award in the quarter. I think that was an expansion of an existing project. Maybe if you can just help us have some more color as to what changed in terms of customer commitment, project design, or capacity to support that additional scope.
Then, just kind of moving away from data centers, perhaps if George can also speak to the federal and Europe award momentum. Obviously, we did see some significant awards on that front in 3Q. I think what would be helpful is to understand the pace and the conversion visibility into 2027. Thank you so much.
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Sure, and great questions. The first one on the $200 million expansion, this is really as our project development is maturing, we were able to firm the kind of capacity, the type of generation that we are utilizing, and just match it with the data center load. We are just seeing increase in some of the megawatts to meet that design. So, that is where that has come from.
Addressing your question on the federal movement, we had a lot of contracts convert, particularly with the VA that we mentioned in the script, large infrastructure projects that support both energy efficiency and also much-needed infrastructure, mechanical, electrical upgrades throughout the VA hospitals. Similarly, we had other agency as well.
The Coast Guard is another one that we were able to convert this one, and another Army site as well. So, we had great momentum. Again, having that existing relationship with the customer that weâve been working for many years already certainly helps in those conversions.
George Sakellaris - Chairman of the Board, Chief Executive Officer
And one of the comments that I had earlier on my script was I was particularly pleased with the broad distribution of the conversion of the awards to contracts, representing the C&I, the federal government, some of the smaller utilities or cooperatives, you might say, and so on. And of course, Europe, weâre getting great traction over there, especially with funds that they are investing in solar installations. And itâs going to be a very, very good business.
And the other thing thatâs happening on the C&I, because the demand of electricity is so large and theyâre beginning to be concerned about reliable power in order to expand their business. Thatâs why for the first time, for a long time, weâve seen a great traction in that market. Those contracts, they move faster because the need is there, and then they want to expand. Whatâs happening with the bringing industries back into the US, itâs accelerating that demand.
Manish Somaiya - Analyst
Thank you. Thank you, Nicole and George. Congrats again.
George Sakellaris - Chairman of the Board, Chief Executive Officer
Thank you very much.
Operator
Craig Irwin, Roth Capital Partners.
Unidentified Participant
Hey, guys. Itâs Andrew on for Craig, and congrats on the strong momentum. So first question from me, as the O&M contract-based scales weâve been seeing revenue increase, but we also saw some pretty solid improvement in profitability this quarter. So can you just talk about how much that reflects greater operating leverage versus contract mix, and kind of whatâs a sustainable margin level?
George Sakellaris - Chairman of the Board, Chief Executive Officer
Yeah, that sounds great, and I will take care of the first one because Iâm very, very pleased with the progress we see on the O&M. Right now, we are approaching 4 gigawatts of solar O&M and batteries, and of course, that is going to grow tremendously. In addition to that, the federal government business, you get more contracts, you get more O&M there.
And now, as we get into the data center, and letâs say we build a couple of these power plants down the road, and some of the O&M contracts that I see coming along with those, they are very, very, very good. So Iâm very excited about that part of our business, and of course, it doesnât require that much capital in order to expand that business, do the assets that we own. And you want to add a little bit more color, Tim?
Josh Baribeau - Senior Vice President, Chief Investment Officer
Sure. On the margin specifically, if you are referring just to O&M, so O&M margins the last two quarters did step up very nicely. I think we addressed it last time, talking about some price increases we were able to push through that we actually had been planning on for quite some time. So that had driven some of the price increases.
But O&M can be somewhat variable. I do not want you all to think necessarily that this sort of mid-20%s EBITDA margin is the consistent level going forward for modeling. But we are very happy with that business, and continues to be a driver of value.
If your question was more about consolidated gross margins, we did have a great quarter. It is a little bit above our guidance. The guidance range was 17% to 18%, which is potentially a little conservative for the year. But it certainly is up meaningfully from last year. And that has been driven by some energy assets being placed in service, but also a strategic move that we have talked about to drive higher-margin projects through the business.
We have been doing that in Europe, we have been doing that in the US regions, et cetera. As all the positive things George and Nicole talked about, people need the solutions, and it creates a lot of value, so we are able to get a little bit extra margin on those, a couple of pickups.
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Yeah. We also had great execution this quarter, so that helped. We were able to have margin pickups on closing out projects.
Unidentified Participant
Understood. Really appreciate the detail there. Just a second one from me, a high-level question. You touched upon it in the opening remarks, but can you just give a little more color on how Neogenyx is progressing, how the operating plants are performing? And any progress on the development pipeline would be great.
Josh Baribeau - Senior Vice President, Chief Investment Officer
Yeah. So Neogenyx is -- weâre very happy with that transaction. It was, we think, game-changing for us in terms of how we monetize our assets and how weâre able to fund the growth of our assets, both in this segment and potentially others. I think there were some issues outside of our control since the closing of the transaction in terms of availability of the power plants, like I said, largely outside of our control.
But in terms of the pipeline, in terms of business development, in terms of HASIâs commitment, everything remains exactly as we modeled.
George Sakellaris - Chairman of the Board, Chief Executive Officer
Yeah, if I may add, itâs been an excellent partnership with those people. And a couple of the plants, one of them, a transformer blew up, and thatâs more than six weeks outage there.
Then the other one, Woodland, we had another development on the plant, which both, by the way, have been fixed now.
Unidentified Participant
Great. Really appreciate the color.
Operator
Eric Stine, Craig-Hallum.
Eric Stine - Analyst
Hey, everyone. Maybe if we could go back to the data center topic. You mentioned the $200 million expansion. I know that last quarter in your backlog, you had five contracts, and you had given, I think it was $1.5 billion combined, and you had given a total of what you thought that those could become if expansion happened. Just curious, what you are seeing in the additional projects that you have got in your backlog, and then just in terms of other prospects that are out there that you are chasing. I mean, is this something to expect, kind of a move to larger projects?
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Yeah, I would say first to answer that first part of the question, I mean, this expansion was specific to one project. Again, it really came. The reason that we were adding more capacity was really just fitting it to the customerâs needs of what their data center build-out is.
We certainly anticipate, as we said in the last earnings call, that we expect each of these scopes to continue to be refined as we continue to develop them. At this point, we have been working through the development process, and as we go through that, it is the way that we have been approaching all large projects and just making sure that we are doing it as the development matures.
I think, just based on where we are now, I mean, the AI is continuing to. The market is continuing to grow, and we are also going to see more and more push to behind-meter on-site solutions. I think certainly there will be more opportunities for us to continue to grow this pipeline, not only with the ones that we have in awarded backlog, but more to come as well, especially even more after the elections.
Eric Stine - Analyst
Yeah. No, thatâs very helpful. Maybe then, just in terms of the project conversion, obviously great. You mentioned federal, you mentioned Europe. But also, a lot of the reasons that you talked about, those have been reasons, thatâs kind of been the market backdrop for some time.
So Iâm just curious if there was anything that maybe was a specific driver in the quarter, or was this just a case of, hey, you just happened to have a number of projects that were close? And they all -- or a high percentage of them, reached the finish line?
George Sakellaris - Chairman of the Board, Chief Executive Officer
I think combined. There were many projects that we had done a lot of homework, and they were ready to sign, and the customers, because of the need, they accelerated. There were some projects, especially in Europe, that from the award to the executed contract, itâs considerably shorter than what it has been. The C&I customers, they have much shorter time span. A couple of the co-ops, some of the contracts, they moved much faster than we had contemplated. So thatâs why Iâm very pleased it was across the board.
And I think, we all focus a lot on data centers and what that will do to our business. The side effect of the high demand for electricity or the shortage of power supply is many, what I call, co-ops, smaller utilities, larger industrial commercial customers, that they never talked to us before about backup power or whatever the case might be.
Now they are doing it. Thatâs why the good part of our backlog now, itâs with that space, that particular market segment. We feel very good. Thatâs why we feel good about our business model, the diversification that we have on the various types of markets and customers and solutions we provide.
Eric Stine - Analyst
Okay. This one, just real quick. This came out, I donât know, a month or so ago, and itâs probably very few details, but the Fortress America talking about each military site needing to generate its own power and operate separate of the grid. That would seem to fit quite nicely with what your core capabilities are. Curious if thereâs anything there or if thatâs just down the road?
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
I think that is down the road, but it certainly is one of the objectives. Resiliency, reliability have been objectives of the federal government for quite some time, and now just this push to, because of the constrained grid right now, it is even going to accelerate that even more. But we are seeing more, and again, not just to have onsite generation, but also to have more energy efficiency that is reducing load as well. That works very well for us because they are complementary with each other on those objectives.
Eric Stine - Analyst
Okay. Thank you.
Operator
Ryan Pfingst, B. Riley Securities.
Ryan Pfingst - Analyst
Hey, guys. Thanks for taking the questions. Maybe another follow-up on the data center side. Of the five projects in awarded backlog, how many are you likely to move to contracted in the next, say, 12, 18, 24 months? Or if you prefer to stay away from timing commentary, could you just remind us what some of the milestones are that these projects are waiting on before you feel comfortable moving them to contracted backlog?
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Well, yes. I think 12, 18 months for those five projects is on target, so what weâre seeing in that. And each one has a little bit different of a story, but permitting is one. Finalizing contract with customers and locking in equipment are the three major milestones that weâre working on each one of them for.
Ryan Pfingst - Analyst
Got it. Thanks, Nicole. Could you talk more about the Army project more broadly with the nuclear component? How should we think about next steps there, and who will ultimately be taking on the first-of-a-kind risk on the nuclear phases?
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Sure. Thatâs a good question. The first of a kind is separate from the two Army sites that we released about. Thatâs a separate project, and we are partnered with a microreactor partner who will assume the risk of the nuclear side of that. Our role in that is just the balance of plant, to build around it, the buildings, concrete, generator, connecting the generation, so what we do all the time. But weâre excited about the Army announcement because this really moves just the strategy to something real, and weâre actually now seeing this future for nuclear.
On these two sites that came from the Army, Picatinny and Aberdeen in Maryland, these give us the opportunity to have multiple phases. Weâre early in the development of this. We have to go through permitting. We have to go through design scope. We have to go through several other lease negotiations with the Army to make these end up being something.
However, weâre doing it in phases, where we can have early wins and then go for the longer stretch with various nuclear technologies, from microreactors, which has a shorter time on the permitting, to SMR technology. On both of these, we have a combination of battery storage and also even clean technology like fuel cells, and then leading to the Phase 2 with the nuclear solutions. But itâs really great to see the Army. Yeah, and itâs just great to see the Army supporting that, because that is a key objective with them, with having nuclear solutions.
Ryan Pfingst - Analyst
Thanks, Nicole.
Operator
Stephen Gengaro, Stifel.
Stephen Gengaro - Analyst
Thanks. Good afternoon, everybody.
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Hi.
Stephen Gengaro - Analyst
I think two for me. One, can you talk a little bit about the supply chain and some of the inflationary pressures that are out there, and how thatâs mitigated by how the contracts are structured?
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Sure. I mean, I think supply chainâs interesting. I mean, it depends on which market weâre talking about, but I think, one, weâll definitely see an uptick in supply chain with some of the data centers that were previously connected to the grid or had some other equipment that now have too much equipment that will be coming to the secondary market.
I think overall for us, though, the supply chain has been a challenge for years now. So, we have a large network of distributors for both electrical equipment, for generation equipment, so weâre able to move quickly and have flexibility in how we can design these systems.
But ultimately, too, our contracts that weâre working on will have protections in them and really work with it to be able to protect against tariffs, to protect against change in cost, just because you have seen such an uptick. I mean, just in the past 12 months, 30% to 40% increase on some of this electrical equipment.
Just insane increases in there. So, I think for us, itâs something that weâve been working with on each contract and make sure that weâre protected, but also just to see it still doesnât take away the need for this, and so the drivers are still out there. So, thereâs not really a choice but to move forward with it.
Stephen Gengaro - Analyst
Thanks. And the follow-up to that is, weâve seen several companies where theyâll get. Obviously, the cash requirements to order, especially power gen equipment, are pretty high. Is that something your customers will help fund, or is that something that will be funded by you?
George Sakellaris - Chairman of the Board, Chief Executive Officer
Good question.
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Yeah, thatâs a great question. Our business model does not go out and buy equipment. We made that very clear to our customers. We certainly are relying on them to make that commitment, because that also signals that theyâre ready to move forward and have a project. Thatâs the way that weâve been moving on our projects, and certainly not to fund equipment procurements ourselves.
Stephen Gengaro - Analyst
Great. No, thank you. Itâs been a big topic, so I appreciate the comments. Thanks.
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Sure.
George Sakellaris - Chairman of the Board, Chief Executive Officer
Thank you.
Operator
Ben Kallo, Baird.
Ben Kallo - Analyst
Hey, thanks for taking my question. Nicole, maybe just following up on some of your earlier comments, just about the different technologies. I know it is very early in some of these states adopting rules around data centers, but have you seen any shift, whether it is from a simple cycle turbine to a fuel cell, or a simple cycle turbine to a reciprocating engine, or anything that you are seeing in shifts because of the pushback or not in my backyard? I have a follow-up.
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
I think that is a great question, and there are two different angles here. One is still the need for speed to power, but also balancing it for minimizing water consumption, cleaner emissions. In most of our projects, we are seeing a combination of fuel cells, reciprocating engines, and simple cycle turbines, with a later phase using combined cycle technology that would have more water usage there. I think, too, you still have hyperscalers that are looking to have offsets with clean energy.
On some of these campuses, I would not be surprised to see that there will be solar and battery storage as part of the solution overall, once the base speed to power project is implemented. I think now it is still kind of the same mix, because you need that speed to power, and reciprocating engines and fuel cells are the quickest way to get there.
Ben Kallo - Analyst
Got it. George, I think in your prepared remarks, you mentioned the energy efficiency, you have not seen it this strong in quite a while. Could you just maybe elaborate more if it is mostly government, or where you are seeing this trend there?
George Sakellaris - Chairman of the Board, Chief Executive Officer
We see great traction on the energy efficiency because the energy prices are higher than what they were before, and continue to be. We see it across all markets, colleges, universities, cities, and states, across the board, and then commercial industrial customers.
The other thing that is happening, aging infrastructures. Basically, the fact that we can take the energy savings, securitize them, and then we get them new boilers, new chillers, sometimes new windows. We upgrade bathrooms. We do many, many upgrades on the customer facilities. Nicole, you might want to add something.
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
No, I think itâs both. I mean, higher energy prices combined with just inefficient aged infrastructure. Being able to replace it with latest technology, but also lower maintenance equipment. And weâre seeing that just in simpler boiler replacements, controls, and all of that, certainly is lending to that increase in energy efficiency. But itâs all driving, triggered from higher costs.
George Sakellaris - Chairman of the Board, Chief Executive Officer
I mean, look at the technologies on the water meters. Now you get the automatic water meter reading. That has become a great business line for us across the US. It started down in Texas, and now itâs all over the streetlights. I can keep going on and on, and thatâs why we feel very good about the diversification that we have in our business model. 60% to 70% of our business still comes from what I call bread and butter.
Ben Kallo - Analyst
Yeah. If I may, just on that added controls and technology, are you seeing customers willing now to enter into virtual power plants or demand response programs more?
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
I think certainly on demand response programs, just because of time of use rates and the peak capacity may not even going higher and higher every year. I think thatâs a big part of these projects that weâre seeing is on the controls to reduce peak power.
George Sakellaris - Chairman of the Board, Chief Executive Officer
Yeah. The other one, speaking of the controls, the automatic buildings and so on, very sophisticated. We have bought three little companies on building controls and excellent performance, and we are looking to grow that particular aspect of our business because it has great market traction out there.
Ben Kallo - Analyst
Great. Thank you, guys.
Operator
(Operator Instructions) Moses Sutton, BNP Paribas.
Moses Sutton - Analyst
Hi. Hi. Thanks for squeezing me in. Very helpful updates on the $1.7 billion data center. Have any of these data centers reached full permits and they are just waiting on other matters? Maybe they are waiting on the recips, turbines, fuel cells, et cetera.
For those that actually do not have the equipment yet, do they typically have slots and pricing locked in? I just want to get a sense on where those two sides, which seem to be the things that would lead towards conversion into a contracted backlog. Thanks again for taking my question.
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
I mean, I would say our permitting is very close on a few of them, especially our federal site where we do not have some of the similar, or all of the other local permits that are required at some of the commercial sites. On the equipment, either we have reserved or we are indicating our schedule and cost based on when we finally lock that in. There is ability to adjust that.
Moses Sutton - Analyst
Great. Thanks. Maybe some quick hit ones as follow-up on the data center sites. You have mentioned Arizona and Texas before. Is it fair to say it is weighted toward any of those states? Is Texas the biggest among them? Are these more so bridge sites, the power use for the customer, or are they in more islanded situations for longer term?
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
Second, islanded in case, longer term is what we are providing on these projects. So they will be behind meter, potentially could have the ability to connect to grid later, but for now they are islanded energy plants. On the first question-
Josh Baribeau - Senior Vice President, Chief Investment Officer
It is more heavily weighted toward Texas -- sorry, towards Arizona. But we have, I think, four or five or six different states right now in an opportunity set of about 10, 5 of which are currently in the awarded backlog and five that are moving through the motions. But there is not a heavy concentration in Texas. But as Nicole pointed out, even the ones that are fully behind the meter.
Moses Sutton - Analyst
Got it. Super helpful. And I guess one last on -- I think Josh, you had noted to me in the past on one of the solar ones, there was actually a project with an oversize ratio, four or five times capacity to run behind the meter solar as the primary generation source. Is that still in the mix there, or is this really all recips, turbines, fuel cells, et cetera? And thanks again for taking my question.
Josh Baribeau - Senior Vice President, Chief Investment Officer
Yeah. I do not think it was ever four to five. It might have been like 2x or something like that, but this is the one that we announced last year. But I think that has been re-scoped a little bit in California, right?
Nicole Bulgarino - President - Federal Solutions and Utility Infrastructure
It is now an all fuel cell, just aligning with federal goals of having gas pollution on the federal side.
Moses Sutton - Analyst
Brilliant. Thank you so much for squeezing me in.
Operator
That concludes our Q&A session. Thank you all for joining. You may now disconnect. Everyone, have a great day.